36.—(1) No incineration of waste in Work No. 1 may take place, apart from during commissioning, until a grid connection comprised in Works No. 6A, 6B, 6C, 6D, 6E, 6F, 6G and 6H has been installed and is capable of transmitting electricity generated by Work No. 1.
(2) No waste may then be incinerated in Work No. 1 unless electricity is being generated by Work No. 1 except during periods of maintenance, inspection or repair or at the direction of the holder of a licence under section 6(1)(b) or (c) of the Electricity Act 1989 who is entitled to give such direction in relation to transmission of electricity from Work No. 1 to the national grid.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: