Sometimes the text of a provision is changed, but the change(s) only apply to a particular geographical area. In some limited cases where this happens, the editorial team create a version for each different geographical area. Multiple versions are only created in this way where the change in question is a substitution so that there are different versions of the text for the different extents. Insertions and repeals of text do not give rise to such multiple versions.
The Building Regulations 2010, Section 17A is up to date with all changes known to be in force on or before 25 September 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):
17A.—(1) A [F2relevant authority] shall within the specified period give a completion certificate in respect of part or all of a building where building work is being carried out and where all of the following circumstances apply—
(a)part or all of the building is to be occupied before the work is completed;
(b)the building is subject to the Regulatory Reform (Fire Safety) Order 2005; and
(c)the authority is satisfied, after taking all reasonable steps, that, regardless of completion of the current building work, [F3regulation 38 and Part B of Schedule 1 are currently complied with in relation to those parts of the building which are to be occupied before completion of the work].
(2) The specified period referred to in paragraph (1) is four weeks starting from the date that notice is received by the [F4relevant authority] in accordance with regulation 16(5).
(3) A certificate given in accordance with this regulation shall be evidence (but not conclusive evidence) that the requirements specified in the certificate have been complied with, and the certificate shall contain this wording.
(4) The certificate must include a statement describing its evidentiary effect, in terms substantially the same as paragraph (3).
[F5(5) Where the relevant authority is the regulator, it must send a copy of each certificate it gives under this regulation in relation to a building to the local authority for the area in which the building is situated.]]
Extent Information
E1This version of this provision applies to England only; a separate version has been created for Wales only
Textual Amendments
F1Reg. 17A inserted (E., but only in relation to excepted energy buildings in W.) (9.1.2013) by The Building Regulations &c. (Amendment) Regulations 2012 (S.I. 2012/3119), reg. 11, Sch. 1 (with regs. 1(3), 45-47)
Reg. 17A inserted (W. for remaining purposes) (19.4.2013) by The Building Regulations &c. (Amendment) (Wales) Regulations 2013 (S.I. 2013/747), regs. 1(4), 9 (with reg. 1(2)(3))
F2Words in reg. 17A(1) substituted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(7)(a) (with regs. 22-24)
F3Words in reg. 17A(1)(c) substituted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 13(3) (with regs. 22-24)
F4Words in reg. 17A(2) substituted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(7)(a) (with regs. 22-24)
F5Reg. 17A(5) inserted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(7)(b) (with regs. 22-24)
17A.—(1) A local authority shall within the specified period give a completion certificate in respect of part or all of a building where building work is being carried out and where all of the following circumstances apply—
(a)part or all of the building is to be occupied before the work is completed;
(b)the building is subject to the Regulatory Reform (Fire Safety) Order 2005; and
(c)the authority is satisfied, after taking all reasonable steps, that, regardless of completion of the current building work, those parts of the building which are to be occupied before completion of the work currently comply with regulation 38 and Part B of Schedule 1.
(2) The specified period referred to in paragraph (1) is four weeks starting from the date that notice is received by the local authority in accordance with regulation 16(5).
(3) A certificate given in accordance with this regulation shall be evidence (but not conclusive evidence) that the requirements specified in the certificate have been complied with, and the certificate shall contain this wording.
(4) The certificate must include a statement describing its evidentiary effect, in terms substantially the same as paragraph (3).]
Extent Information
E2This version of this provision applies to Wales only; a separate version has been created for England only
Textual Amendments
F6Reg. 17A inserted (E., but only in relation to excepted energy buildings in W.) (9.1.2013) by The Building Regulations &c. (Amendment) Regulations 2012 (S.I. 2012/3119), reg. 11, Sch. 1 (with regs. 1(3), 45-47)
Reg. 17A inserted (W. for remaining purposes) (19.4.2013) by The Building Regulations &c. (Amendment) (Wales) Regulations 2013 (S.I. 2013/747), regs. 1(4), 9 (with reg. 1(2)(3))
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: