2.  The works referred to in article 13(1) are as follows—

Dredging Work No. 1 — An area of the riverbed—

(a)

for use as a manoeuvring area for vessels;

(b)

bounded to the north by the berthing pocket authorised to be dredged by Dredging Work No. 4 for the length of that work and extending southwards into the river to the northern limit of the main channel; and

(c)

dredged to a maximum depth of 14.5 metres below chart datum.

Dredging Work No. 2 — A deep water channel—

(a)

which provides access for vessels navigating to and from London Gateway Port;

(b)

with a centre line (illustratively shown on Sheets Nos. 211 to 213 of the deposited plans) commencing at reference point E571807 and N180266 and continuing east along the Yantlet Channel, The Oaze, the Knock John Channel and parts of the Black Deep and terminating in the area of the sea known as The Sunk;

(c)

300 metres wide at the base of the channel; and

(d)

dredged to the following maximum depths and subject to Dredging Works Nos. 1 and 4—

(i)

in the Yantlet Channel to 14.5 metres below chart datum;

(ii)

in The Oaze to 16.5 metres below chart datum;

(iii)

in the Knock John Channel to 15 metres below chart datum;

(iv)

in the Black Deep to 16.5 metres below chart datum; and

(v)

in The Sunk to 16.5 metres below chart datum.

Dredging Work No. 3 — A deep water anchorage—

(a)

which provides a safe anchorage for deep draught vessels navigating to and from London Gateway Port;

(b)

in the position of the existing Zulu 3 anchorage at reference point E595852 and N181215, 183 degrees and 0.54 nautical miles from Shoebury Beacon;

(c)

with a diameter of 926 metres at the base of the anchorage; and

(d)

dredged to a depth not exceeding 16 metres below chart datum.

Dredging Work No. 4 — An area of the river—

(a)

for use as a berthing pocket for vessels;

(b)

bounded to the north by the quay wall authorised to be constructed by a line commencing at Coordinates Reference D1, passing eastwards and terminating at Coordinates Reference D3, to the south by a line commencing at Coordinates Reference D2, passing eastwards and terminating at Coordinates Reference D4, to the west by a line commencing at Coordinates Reference D2, passing north and terminating at Coordinates Reference D1 and to the east by a line commencing at Coordinates Reference D4, passing northwards and terminating at Coordinates Reference D3, as shown on the deposited plans; and

(c)

dredged to a maximum depth of 16 metres below chart datum.

Dredging Work No. 5 — Works ancillary to Work No. 17 and to the reclamation works authorised by Works Nos. 11 and 12 as required—

(a)

for a temporary reclamation bund in order to facilitate those reclamation works, such a bund, where it is along the southern side of Works Nos. 11 and 12, not to extend into the river for a distance exceeding 60 metres southward of the general line of the quay wall authorised by those reclamation works; and

(b)

to accommodate on the riverbed in the berthing pocket authorised by Dredging Work No. 4 permanent rock armour as scour protection for the quay wall.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources