MODEL CLAUSES

PART 1Preliminary

Interpretation

1.(1) In this Order—

“the 1961 Act” means the Land Compensation Act 1961(1);

“the 1965 Act” means the Compulsory Purchase Act 1965(2);

“the 1990 Act” means the Town and Country Planning Act 1990(3);

“the 1991 Act” means the New Roads and Street Works Act 1991(4);

“address” includes any number or address used for the purposes of electronic transmission;

“authorised works” means the scheduled works and any other works authorised by this Order;

“building” includes any structure or erection or any part of a building, structure or erection;

“the book of reference” means the book of reference certified by the Secretary of State as the book of reference for the purposes of this Order;

“carriageway” has the same meaning as in the Highways Act 1980(5);

“electronic transmission” means a communication transmitted—

(a)

by means of an electronic communications network; or

(b)

by other means but while in electronic form;

“footway” has the same meaning as in the Highways Act 1980;

“highway” and “highway authority” have the same meaning as in the Highways Act 1980;

“the land plan” means the plan prepared in pursuance of rule 12(5) of the Transport and Works (Applications and Objections Procedure) (England and Wales) Rules 2006(6) and certified by the Secretary of State as the land plan for the purposes of this Order;

“the limits of deviation” means the limits of deviation for the scheduled works shown on the works plan;

“maintain” includes inspect, repair, adjust, alter, remove, reconstruct and replace, and “maintenance” shall be construed accordingly;

“the Order limits” means any limits of deviation and any additional limits of land to be acquired or used which are shown on the land plan or the works plan;

“owner”, in relation to land, has the same meaning as in the Acquisition of Land Act 1981(7);

“the scheduled works” means the works specified in Schedule 1 to this Order or any part of them;

“the sections” means the sections prepared in pursuance of rule 12(3) of the Transport and Works (Applications and Objections Procedure) (England and Wales) Rules 2006 and certified by the Secretary of State as the sections for the purposes of this Order;

“street” includes part of a street;

“street authority”, in relation to a street, has the same meaning as in Part 3 of the 1991 Act;

the tribunal” means the Lands Tribunal;

“the undertaker” means [ ];

“watercourse” includes all rivers, streams, ditches, drains, canals, cuts, culverts, dykes, sluices, sewers and passages through which water flows except a public sewer or drain; and

“the works plan” means the plan prepared in pursuance of rule 12(1)(a) of the Transport and Works (Applications and Objections Procedure) (England and Wales) Rules 2006 and certified by the Secretary of State as the works plan for the purposes of this Order.

(2) References in this Order to rights over land include references to rights to do, or to place and maintain, anything in, on or under land or in the air-space above its surface.

(3) All distances, directions and lengths stated in the description of the scheduled works or in any description of powers or lands shall be construed as if the words “or thereabouts” were inserted after each such distance, direction and length, and distances between points on a scheduled work shall be taken to be measured along the scheduled work.

Incorporation of Railways Clauses Acts

2.(1) The following provisions of the Railways Clauses Consolidation Act 1845(8) shall be incorporated in this Order—

  • section 46 (crossing of roads—level crossings), subject to paragraph (4);

  • section 58 (company to repair roads used by them), except for the words from “and if any question” to the end;

  • section 61 (company to make sufficient approaches and fences to highways crossing on the level);

  • section 68 (accommodation works by company);

  • section 71 (additional accommodation works by owners), except for the words “or directed by such justices to be made by the company” and “or, in case of difference, as shall be authorised by two justices”;

  • section 72 and 73 (supplementary provisions relating to accommodation works);

  • section 75 (omission to fasten gates);

  • section 77 (presumption that minerals excepted from acquisition of land);

  • sections 78 to 85E and Schedules 1 to 3 (minerals under railways), as respectively substituted and inserted by section 15 of the Mines (Working Facilities and Support) Act 1923(9);

  • section 103 and 104 (refusal to quit carriage at destination);

  • section 105 (carriage of dangerous goods on railway);

  • section 145 (recovery of penalties); and

  • section 154 (transient offenders).

(2) The following provisions of the Railways Clauses Act 1863(10) shall be incorporated in this Order—

  • sections 5 and 7 (level crossings), and

  • section 12 (signals, watchmen etc.).

(3) In those provisions, as incorporated in this Order—

“the company” means the undertaker;

“goods” includes any thing conveyed on the railway authorised to be constructed by this Order;

“lease” includes an agreement for a lease;

“prescribed”, in relation to any such provision means prescribed by this Order for the purposes of that provision;

“the railway” means any railway authorised to be constructed by this Order and any other authorised works;

“the special Act” means this Order;

“toll” includes any rate or charge or other payment payable under this Order or any other enactment for any passenger or goods conveyed on any railway authorised to be constructed by this Order.

(4) In section 46 of the Act of 1845, as incorporated in this Order, for the proviso there shall be substituted the words “Provided always that, with the consent of the highway authority and subject to such conditions as the authority may reasonably impose, the railway may be carried across a highway on the level.”.

Application of the 1991 Act

3.(1) Works executed under this Order in relation to a highway which consists of or includes a carriageway shall be treated for the purposes of Part 3 of the 1991 Act (street works) as major transport works if—

(a)they are of a description mentioned in any of paragraphs (a), (c) to (e), (g) and (h) of section 86(3) of that Act (which defines what highway authority works are major highway works); or

(b)they are works which, had they been executed by the highway authority, might have been carried out in exercise of the powers conferred by section 64 of the Highways Act 1980 (dual carriageways and roundabouts).

(2) The provisions of the 1991 Act mentioned in paragraph (3) which, together with other provisions of that Act, apply in relation to the execution of street works and any regulations made or code of practice issued or approved under those provisions shall apply (with the necessary modifications) in relation to any stopping up, alteration or diversion of a street of a temporary nature by the undertaker under the powers conferred by article 8 (temporary stopping up of streets) whether or not the stopping up, alteration or diversion constitutes street works within the meaning of that Act.

(3) The provisions of the 1991 Act referred to in paragraph (2) are—

  • section 54 (advance notice of certain works), subject to paragraph (4);

  • section 55 (notice of starting date of works), subject to paragraph (4);

  • section 57 (notice of emergency works);

  • section 59 (general duty of street authority to co-ordinate works);

  • section 60 (general duty of undertakers to co-operate);

  • section 68 (facilities to be afforded to street authority);

  • section 69 (works likely to affect other apparatus in the street);

  • section 76 (liability for cost of temporary traffic regulation);

  • section 77 (liability for cost of use of alternative route); and

all such other provisions as apply for the purposes of the provisions mentioned above.

(4) Sections 54 and 55 of the 1991 Act as applied by paragraph (2) shall have effect as if references in section 57 of that Act to emergency works were a reference to a stopping up, alteration or diversion (as the case may be) required in a case of emergency.

(5) Nothing in article 10 (construction and maintenance of new or altered streets) shall—

(a)prejudice the operation of section 87 of the 1991 Act (prospectively maintainable highways); and the undertaker shall not by reason of any duty under that article to maintain a street be taken to be a street authority in relation to that street for the purposes of Part 3 of that Act; or

(b)have effect in relation to street works with regard to which the provisions of Part 3 of the 1991 Act apply.

PART 2Works Provisions

Principal powers
Power to construct and maintain works

4.(1) The undertaker may construct and maintain the scheduled works.

(2) Subject to article 5 (power to deviate), the scheduled works may only be constructed in the lines or situations shown on the works plan and in accordance with the levels shown on the sections.

(3) Subject to paragraph (5), the undertaker may carry out and maintain such of the following works as may be necessary or expedient for the purposes of, or for purposes ancillary to, the construction of the scheduled works, namely—

(a)works to alter the position of apparatus, including mains, sewers, drains and cables;

(b)works to alter the course of, or otherwise interfere with, a watercourse other than a navigable watercourse;

(c)landscaping and other works to mitigate any adverse effects of the construction, maintenance or operation of the scheduled works; and

(d)works for the benefit or protection of premises affected by the scheduled works.

(4) Subject to paragraph (5), the undertaker may carry out such other works (of whatever nature) as may be necessary or expedient for the purposes of, or for purposes ancillary to, the construction of the scheduled works, other than works that would interfere with a navigable watercourse.

(5) Paragraphs (3) and (4) shall only authorise the carrying out or maintenance of works outside the limits of deviation if such works are carried out on land specified in columns (1) and (2) of Schedule 2 to this Order for the purpose specified in relation to that land in column (3) of that Schedule.

Power to deviate

5.  In constructing or maintaining any of the scheduled works, the undertaker may—

(a)deviate laterally from the lines or situations shown on the works plan to the extent of the limits of deviation for that work; and

(b)deviate vertically from the levels shown on the sections—

(i)to any extent not exceeding [3 ] metres upwards; or

(ii)to any extent downwards as may be found to be necessary or convenient.

Streets
Power to execute street works

6.(1) The undertaker may, for the purposes of the authorised works, enter upon so much of any of the streets specified in Schedule 3 to this Order as is within the Order limits and may—

(a)break up or open the street, or any sewer, drain or tunnel under it, or tunnel or bore under the street;

(b)place apparatus in the street;

(c)maintain apparatus in the street or change its position; and

(d)execute any works required for or incidental to any works referred to in sub-paragraphs (a), (b) and (c).

(2) This article is subject to paragraph 3 of Schedule 11 (provisions relating to statutory undertakers etc.) to this Order.

(3) In this article “apparatus” has the same meaning as in Part 3 of the 1991 Act.

Stopping up of streets

7.(1) Subject to the provisions of this article, the undertaker may, in connection with the construction of the authorised works, stop up each of the streets specified in columns (1) and (2) of Parts 1 and 2 of Schedule 4 to this Order to the extent specified, by reference to the letters and numbers shown on the works plan, in column (3) of those Parts of that Schedule.

(2) No street specified in columns (1) and (2) of Part 1 of Schedule 4 to this Order (being a street to be stopped up for which a substitute is to be provided) shall be wholly or partly stopped up under this article unless—

(a)the new street to be substituted for it, which is specified in column (4) of that Part of that Schedule, has been completed to the reasonable satisfaction of the street authority and is open for use; or

(b)a temporary alternative route for the passage of such traffic as could have used the street to be stopped up is first provided and thereafter maintained by the undertaker, to the reasonable satisfaction of the street authority, between the commencement and termination points for the stopping up of the street until the completion and opening of the new street in accordance with sub-paragraph (a).

(3) No street specified in columns (1) and (2) of Part 2 of Schedule 4 to this Order (being a street to be stopped up for which no substitute is to be provided) shall be wholly or partly stopped up under this article unless the condition specified in paragraph (4) is satisfied in relation to all the land which abuts on either side of the street to be stopped up.

(4) The condition referred to in paragraph (3) is that—

(a)the undertaker is in possession of the land; or

(b)there is no right of access to the land from the street concerned; or

(c)there is reasonably convenient access to the land otherwise than from the street concerned; or

(d)the owners and occupiers of the land have agreed to the stopping up.

(5) Where a street has been stopped up under this article—

(a)all rights of way over or along the street so stopped up shall be extinguished; and

(b)the undertaker may appropriate and use for the purposes of its railway undertaking so much of the site of the street as is bounded on both sides by land owned by the undertaker.

(6) Any person who suffers loss by the suspension or extinguishment of any private right of way under this article shall be entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

(7) This article is subject to paragraph 2 of Schedule 11 (provisions relating to statutory undertakers etc.) to this Order.

Temporary stopping up of streets

8.(1) The undertaker, during and for the purposes of the execution of the authorised works, may temporarily stop up, alter or divert any street and may for any reasonable time—

(a)divert the traffic from the street; and

(b)subject to paragraph (2), prevent all persons from passing along the street.

(2) The undertaker shall provide reasonable access for pedestrians going to or from premises abutting a street affected by the exercise of the powers conferred by this article if there would otherwise be no such access.

(3) Without prejudice to the generality of paragraph (1), the undertaker may exercise the powers conferred by this article in relation to the streets specified in columns (1) and (2) of Schedule 5 to this Order to the extent specified, by reference to the letters and numbers shown on the works plan, in column (3) of that Schedule.

(4) The undertaker shall not exercise the powers conferred by this article—

(a)in relation to any street specified as mentioned in paragraph (3) without first consulting the street authority; and

(b)in relation to any other street without the consent of the street authority which may attach reasonable conditions to any consent, but such consent shall not be unreasonably withheld.

(5) Any person who suffers loss by the suspension of any private right of way under this article shall be entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

Access to works

9.  The undertaker may, for the purposes of the authorised works—

(a)form and lay out means of access, or improve existing means of access, in the location specified in columns (1) and (2) of Schedule 6 (access to works) to this Order; and

(b)with the approval of the highway authority, such approval not to be unreasonably withheld, form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as the undertaker reasonably requires for the purposes of the authorised works.

Construction and maintenance of new or altered streets

10.(1) Any street (other than [specified private streets]) to be constructed under this Order shall be completed to the reasonable satisfaction of the highway authority and shall be maintained by and at the expense of the undertaker for a period of 12 months from its completion and at the expiry of that period by and at the expense of the highway authority.

(2) Where a street is altered or diverted under this Order, the altered or diverted part of the street shall, when completed to the reasonable satisfaction of the street authority, be maintained by and at the expense of the undertaker for a period of 12 months from its completion and at the expiry of that period by and at the expense of the street authority.

(3) Paragraphs (1) and (2) do not apply in relation to the structure of any bridge or tunnel carrying a street over or under any railway of the undertaker.

(4) In any action against the undertaker in respect of loss or damage resulting from any failure by it to maintain a street under this article, it shall be a defence (without prejudice to any other defence or the application of the law relating to contributory negligence) to prove that the undertaker had taken such care as in all the circumstances was reasonably required to secure that the part of the street to which the action relates was not dangerous to traffic.

(5) For the purposes of a defence under paragraph (4), the court shall in particular have regard to the following matters—

(a)the character of the street and the traffic which was reasonably to be expected to use it;

(b)the standard of maintenance appropriate for a street of that character and used by such traffic;

(c)the state of repair in which a reasonable person would have expected to find the street;

(d)whether the undertaker knew, or could reasonably have been expected to know, that the condition of the part of the street to which the action relates was likely to cause danger to users of the street;

(e)where the undertaker could not reasonably have been expected to repair that part of the street before the cause of action arose, what warning notices of its condition had been displayed,

but for the purposes of such a defence it is not relevant to prove that the undertaker had arranged for a competent person to carry out or supervise the maintenance of the part of the street to which the action relates unless it is also proved that the undertaker had given him proper instructions with regard to the maintenance of the street and that he had carried out those instructions.

NOTE: Where a private street is to be constructed it should be excepted from paragraph (1) and the article should specify the person by whom the street is to be maintained at the expiry of the 12 month period.

Construction of bridges and tunnels

11.  Any bridge or tunnel to be constructed under this Order for carrying a highway over or under a railway shall be constructed in accordance with the plans and specifications approved by the highway authority, but such approval shall not be unreasonably withheld.

Agreements with street authorities

12.(1) A street authority and the undertaker may enter into agreements with respect to—

(a)the construction of any new street (including any structure carrying the street over or under a railway) under the powers conferred by this Order;

(b)the maintenance of the structure of any bridge or tunnel carrying a street over or under a railway;

(c)any stopping up, alteration or diversion of a street under the powers conferred by this Order; or

(d)the execution in the street of any of the works referred to in article 6(1) (power to execute street works).

(2) Such an agreement may, without prejudice to the generality of paragraph (1)—

(a)make provision for the street authority to carry out any function under this Order which relates to the street in question; and

(b)contain such terms as to payment and otherwise as the parties consider appropriate.

Level crossings

13.(1) The undertaker may construct the railway so as to carry it on the level across the highways specified in Schedule 7 to this Order.

(2) The undertaker may in the exercise of the powers conferred by this article alter the level of any highway specified in Schedule 7 to this Order.

(3) The highway authority and the undertaker may enter into agreements with respect to the construction and maintenance of any new level crossing; and such an agreement may contain such terms as to payment or otherwise as the parties consider appropriate.

(4) In this article—

“new level crossing” means the place at which the railway crosses a highway on the level under the powers conferred by this article;

“the railway” means [ ].

Supplemental powers
Discharge of water

14.(1) The undertaker may use any watercourse or any public sewer or drain for the drainage of water in connection with the construction or maintenance of the authorised works and for that purpose may lay down, take up and alter pipes and may, on any land within the Order limits, make openings into, and connections with, the watercourse, public sewer or drain.

(2) Any dispute arising from the exercise of the powers in paragraph (1) to connect to or use a public sewer or drain shall be determined as if it were a dispute under section 106 of the Water Industry Act 1991(11).

(3) The undertaker shall not discharge any water into any watercourse, public sewer or drain except with the consent of the person to whom it belongs; and such consent may be given subject to such terms and conditions as he may reasonably impose, but shall not be unreasonably withheld.

(4) The undertaker shall not make any opening into any public sewer or drain except—

(a)in accordance with plans approved by the person to whom the sewer or drain belongs, but such approval shall not be unreasonably withheld; and

(b)where that person has been given the opportunity to supervise the making of the opening.

(5) The undertaker shall not, in the exercise of the powers conferred by this article, damage or interfere with the bed or banks of any watercourse forming part of a main river.

(6) The undertaker shall take such steps as are reasonably practicable to secure that any water discharged into a watercourse or public sewer or drain under the powers conferred by this article is as free as may be practicable from gravel, soil or other solid substance, oil or matter in suspension.

(7) This article does not authorise the entry into controlled waters of any matter whose entry or discharge into controlled waters is prohibited by section 85(1), (2) or (3) of the Water Resources Act 1991(12).

(8) In this article—

(a)“public sewer or drain” means a sewer or drain which belongs to the Commission for the New Towns, the Environment Agency, a harbour authority within the meaning of the Harbours Act 1964(13), an internal drainage board, a joint planning board, a local authority, a National Park Authority, a sewerage undertaker or an urban development corporation; and

(b)other expressions, excluding watercourses, used both in this article and in the Water Resources Act 1991 have the same meaning as in that Act.

Protective works to buildings

15.(1) Subject to the following provisions of this article, the undertaker may at its own expense carry out such protective works to any building lying within the Order limits as the undertaker considers to be necessary or expedient.

(2) Protective works may be carried out—

(a)at any time before or during the construction in the vicinity of the building of any part of the authorised works; or

(b)after the completion of the construction of that part of the authorised works in the vicinity of the building at any time up to the end of the period of 5 years beginning with the day on which that part of the authorised works is first opened for use.

(3) For the purpose of determining how the functions under this article are to be exercised the undertaker may enter and survey any building falling within paragraph (1) and any land within its curtilage.

(4) For the purpose of carrying out protective works under this article to a building the undertaker may (subject to paragraphs (5) and (6))—

(a)enter the building and any land within its curtilage; and

(b)where the works cannot be carried out reasonably conveniently without entering land which is adjacent to the building but outside its curtilage, enter the adjacent land (but not any building erected on it).

(5) Before exercising—

(a)a right under paragraph (1) to carry out protective works to a building;

(b)a right under paragraph (3) to enter a building and land within its curtilage;

(c)a right under paragraph (4)(a) to enter a building and land within its curtilage; or

(d)a right under paragraph (4)(b) to enter land,

the undertaker shall, except in the case of emergency, serve on the owners and occupiers of the building or land not less than 14 days' notice of its intention to exercise that right and, in a case falling within sub-paragraph (a) or (c), specifying the protective works proposed to be carried out.

(6) Where a notice is served under paragraph (5)(a), (c) or (d), the owner or occupier of the building or land concerned may, by serving a counter-notice within the period of 10 days beginning with the day on which the notice was served, require the question whether it is necessary or expedient to carry out the protective works or to enter the building or land to be referred to arbitration under article 45 (arbitration).

(7) The undertaker shall compensate the owners and occupiers of any building or land in relation to which the powers conferred by this article have been exercised for any loss or damage arising to them by reason of the exercise of those powers.

(8) Where—

(a)protective works are carried out under this article to a building; and

(b)within the period of 5 years beginning with the day on which the part of the authorised works constructed in the vicinity of the building is first opened for use it appears that the protective works are inadequate to protect the building against damage caused by the construction or operation of that part of the authorised works,

the undertaker shall compensate the owners and occupiers of the building for any loss or damage sustained by them.

(9) Without prejudice to article 44 (no double recovery) nothing in this article shall relieve the undertaker from any liability to pay compensation under section 10(2) of the 1965 Act.

(10) Any compensation payable under paragraph (7) or (8) shall be determined, in case of dispute, under Part 1 of the 1961 Act.

(11) In this article “protective works” in relation to a building means—

(a)underpinning, strengthening and any other works the purpose of which is to prevent damage which may be caused to the building by the construction, maintenance or operation of the authorised works; and

(b)any works the purpose of which is to remedy any damage which has been caused to the building by the construction, maintenance or operation of the authorised works.

Power to survey and investigate land

16.(1) The undertaker may for the purposes of this Order—

(a)survey or investigate any land shown within the Order limits or which may be affected by the authorised works;

(b)without prejudice to the generality of sub-paragraph (a), make trial holes in such positions as the undertaker thinks fit on the land to investigate the nature of the surface layer and subsoil and remove soil samples;

(c)without prejudice to the generality of paragraph (a), carry out ecological or archaeological investigations on such land;

(d)place on, leave on and remove from the land apparatus for use in connection with the survey and investigation of land and making of trial holes; and

(e)enter on the land for the purpose of exercising the powers conferred by sub-paragraphs (a) to (d).

(2) No land may be entered or equipment placed or left on or removed from the land under paragraph (1), unless at least 7 days' notice has been served on every owner and occupier of the land.

(3) Any person entering land under this article on behalf of the undertaker—

(a)shall, if so required, before or after entering the land produce written evidence of his authority to do so; and

(b) may take with him such vehicles and equipment as are necessary to carry out the survey or investigation or to make the trial holes.

(4) No trial holes shall be made under this article—

(a)in a carriageway or footway without the consent of the highway authority; or

(b)in a private street without the consent of the street authority,

but such consent shall not be unreasonably withheld.

(5) The undertaker shall compensate the owners and occupiers of the land for any loss or damage arising by reason of the exercise of the powers conferred by this article, such compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

(6) Nothing in this article shall obviate the need to obtain scheduled monument consent under the Ancient Monuments and Archaeological Areas Act 1979(14).

PART 3Acquisition and Possession of Land

Powers of acquisition
Power to acquire land

17.(1) The undertaker may acquire compulsorily—

(a)so much of the land shown on the land plan within the limits of deviation as land to be acquired compulsorily and described in the book of reference as may be required for the purposes of the authorised works; and

(b)so much of the land specified in columns (1) and (2) of Schedule 2 to this Order (being land shown on the land plan and described in the book of reference) as may be required for the purpose specified in relation to that land in column (3) of that Schedule,

and may use any land so acquired for those purposes or for any other purposes that are ancillary to its railway undertaking.

(2) This article is subject to article 22 (power to acquire land limited to subsoil lying more than 9 metres beneath surface) and article 24 (temporary use of land for construction of works).

Application of Part 1 of the Compulsory Purchase Act 1965

18.(1) Part 1 of the 1965 Act, in so far as not modified by or inconsistent with the provisions of this Order, shall apply to the acquisition of land under this Order—

(a)as it applies to a compulsory purchase to which the Acquisition of Land Act 1981(15) applies; and

(b)as if this Order were a compulsory purchase order under that Act.

(2) Part 1 of the 1965 Act, as so applied, shall have effect as if section 4 (which provides a time limit for compulsory purchase of land) and paragraph 3(3) of Schedule 3 (which makes provision as to the giving of bonds) were omitted.

Application of the Compulsory Purchase (Vesting Declarations) Act 1981

19.(1) The Compulsory Purchase (Vesting Declarations) Act 1981(16) shall apply as if this Order were a compulsory purchase order.

(2) The Compulsory Purchase (Vesting Declarations) Act 1981, as so applied by paragraph (1), shall have effect with the following modifications.

(3) In section 3 (preliminary notices) for subsection (1) there shall be substituted—

(1) Before making a declaration under section 4 with respect to any land which is subject to a compulsory purchase order the acquiring authority shall include the particulars specified in subsection (3) in a notice which is—

(a)given to every person with a relevant interest in the land with respect to which the declaration is to be made (other than a mortgagee who is not in possession); and

(b)published in a local newspaper circulating in the area in which the land is situated..

(4) In that section, in subsection (2), for “(1)(b)” there shall be substituted “(1)” and after “given” there shall be inserted “and published”.

(5) In that section, for subsections (5) and (6) there shall be substituted—

(5) For the purposes of this section, a person has a relevant interest in land if—

(a)he is for the time being entitled to dispose of the fee simple of the land, whether in possession or in reversion; or

(b)he holds, or is entitled to the rents and profits of, the land under a lease or agreement, the unexpired term of which exceeds one month..

(6) In section 5 (earliest date for execution of declaration)—

(a)in subsection (1), after “publication” there shall be inserted “in a local newspaper circulating in the area in which the land is situated”; and

(b)subsection (2) shall be omitted.

(7) In section 7 (constructive notice to treat) in subsection (1)(a), the words “(as modified by section 4 of the Acquisition of Land Act 1981)” shall be omitted.

(8) References to the 1965 Act shall be construed as references to that Act as applied to the acquisition of land under article 17 (power to acquire land).

Power to acquire new rights

20.(1) The undertaker may acquire compulsorily such easements or other rights over any land referred to in paragraph (1)(a) or (b) of article 17 (power to acquire land) as may be required for any purpose for which that land may be acquired under that provision, by creating them as well as by acquiring easements or other rights already in existence.

(2) Subject to section 8 of the 1965 Act (as substituted by paragraph 5 of Schedule 8 to this Order) where the undertaker acquires a right over land under paragraph (1) the undertaker shall not be required to acquire a greater interest in that land.

(3) Schedule 8 to this Order shall have effect for the purpose of modifying the enactments relating to compensation and the provisions of the 1965 Act in their application in relation to the compulsory acquisition under this article of a right over land by the creation of a new right.

Power to acquire subsoil only

21.(1) The undertaker may acquire compulsorily so much of, or such rights in, the subsoil of the land referred to in paragraph (1)(a) or (b) of article 17 (power to acquire land) as may be required for any purpose for which that land may be acquired under that provision instead of acquiring the whole of the land.

(2) Where the undertaker acquires any part of or rights in the subsoil of land under paragraph (1) it shall not be required to acquire an interest in any other part of the land.

(3) Paragraph (2) shall not prevent article 28 (acquisition of part of certain properties) from applying where the undertaker acquires a cellar, vault, arch or other construction forming part of a house, building or manufactory.

Power to acquire land limited to subsoil lying more than 9 metres beneath surface

22.(1) This article applies to the land specified in Schedule 9 to this Order.

(2) In the case of land to which this article applies, the undertaker’s powers of compulsory acquisition under article 17 (power to acquire land) shall be limited to the acquisition of, or rights in, so much of the subsoil of the land as may be required for the purposes of the authorised works.

(3) Where the undertaker acquires any part of, or rights in, the subsoil of the land to which this article applies, it shall not be required to acquire a greater interest in the land or an interest in any other part of it.

(4) References in this article to the subsoil of land are references to the subsoil lying more than 9 metres beneath the level of the surface of the land; and for this purpose “level of the surface of the land” means—

(a)in the case of any land on which a building is erected, the level of the surface of the ground adjoining the building;

(b)in the case of a watercourse or other water area, the level of the surface of the ground nearest to it which is at all times above water level; or

(c)in any other case, ground surface level.

Rights under or over streets

23.(1) The undertaker may enter upon and appropriate so much of the subsoil of, or air-space over, any street within the Order limits as may be required for the purposes of the authorised works and may use the subsoil or air-space for those purposes or any other purpose ancillary to its railway undertaking.

(2) Subject to paragraph (4), the power under paragraph (1) may be exercised in relation to a street without the undertaker being required to acquire any part of the street or any easement or right in the street.

(3) Subject to paragraph (5), any person who is an owner or occupier of land in respect of which the power of appropriation conferred by paragraph (1) is exercised without the undertaker acquiring any part of that person’s interest in the land, and who suffers loss by the exercise of that power, shall be entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

(4) Paragraph (2) shall not apply in relation to—

(a)any subway or underground building; or

(b)any cellar, vault, arch or other construction in, on or under a street which forms part of a building fronting onto the street.

(5) Compensation shall not be payable under paragraph (3) to any person who is an undertaker to whom section 85 of the 1991 Act applies in respect of measures of which the allowable costs are to be borne in accordance with that section.

Temporary Possession of Land
Temporary use of land for construction of works

24.(1) The undertaker may, in connection with the carrying out of the authorised works—

(a)enter upon and take temporary possession of the land specified in columns (1) and (2) of Schedule 10 to this Order for the purpose specified in relation to that land in column (3) of that Schedule relating to the authorised works specified in column (4) of that Schedule;

(b)remove any buildings and vegetation from that land; and

(c)construct temporary works (including the provision of means of access) and buildings on that land.

(2) Not less than 14 days before entering upon and taking temporary possession of land under this article the undertaker shall serve notice of the intended entry on the owners and occupiers of the land.

(3) The undertaker may not, without the agreement of the owners of the land, remain in possession of any land under this article after the end of the period of one year beginning with the date of completion of the work specified in relation to that land in column (4) of Schedule 10 to this Order.

(4) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker shall remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but the undertaker shall not be required to replace a building removed under this article.

(5) The undertaker shall pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the powers conferred by this article.

(6) Any dispute as to a person’s entitlement to compensation under paragraph (5), or as to the amount of the compensation, shall be determined under Part 1 of the 1961 Act.

(7) Without prejudice to article 44 (no double recovery), nothing in this article shall affect any liability to pay compensation under section 10(2) of the 1965 Act or under any other enactment in respect of loss or damage arising from the execution of any works, other than loss or damage for which compensation is payable under paragraph (5).

(8) The powers of compulsory acquisition of land conferred by this Order shall not apply in relation to the land referred to in paragraph (1) except that the undertaker shall not be precluded from—

(a)acquiring new rights over any part of that land under article 20 (power to acquire new rights); or

(b)acquiring any part of the subsoil (or rights in the subsoil) of that land under article 21 (power to acquire subsoil only) or in accordance with article 22 (power to acquire land limited to subsoil lying more than 9 metres beneath surface).

(9) Where the undertaker takes possession of land under this article, it shall not be required to acquire the land or any interest in it.

(10) Section 13 of the 1965 Act shall apply to the temporary use of land pursuant to this article to the same extent as it applies to the acquisition of land under this Order by virtue of article 18(1) (application of Part 1 of the Compulsory Purchase Act 1965).

Temporary use of land for maintenance of works

25.(1) Subject to paragraph (2), at any time during the maintenance period relating to any of the scheduled works, the undertaker may—

(a)enter upon and take temporary possession of any land within the Order limits if such possession is reasonably required for the purpose of maintaining the work or any ancillary works connected with it; and

(b)construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.

(2) Paragraph (1) shall not authorise the undertaker to take temporary possession of—

(a)any house or garden belonging to a house; or

(b)any building (other than a house) if it is for the time being occupied.

(3) Not less than 28 days before entering upon and taking temporary possession of land under this article the undertaker shall serve notice of the intended entry on the owners and occupiers of the land.

(4) The undertaker may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of works for which possession of the land was taken.

(5) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker shall remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.

(6) The undertaker shall pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the powers conferred by this article.

(7) Any dispute as to a person’s entitlement to compensation under paragraph (6), or as to the amount of the compensation, shall be determined under Part 1 of the 1961 Act.

(8) Without prejudice to article 44 (no double recovery), nothing in this article shall affect any liability to pay compensation under section 10(2) of the 1965 Act or under any other enactment in respect of loss or damage arising from the execution of any works, other than loss or damage for which compensation is payable under paragraph (6).

(9) Where the undertaker takes possession of land under this article, it shall not be required to acquire the land or any interest in it.

(10) Section 13 of the 1965 Act shall apply to the temporary use of land pursuant to this article to the same extent as it applies to the acquisition of land under this Order by virtue of article 18(1) (application of Part 1 of the Compulsory Purchase Act 1965).

(11) In this article “the maintenance period”, in relation to a scheduled work, means the period of 5 years beginning with the date on which the work is opened for use.

Compensation
Disregard of certain interests and improvements

26.(1) assessing the compensation payable to any person on the acquisition from him of any land under this Order, the tribunal shall not take into account—

(a)any interest in land; or

(b)any enhancement of the value of any interest in land by reason of any building erected, works executed or improvement or alteration made on relevant land,

if the tribunal is satisfied that the creation of the interest, the erection of the building, the execution of the works or the making of the improvement or alteration was not reasonably necessary and was undertaken with a view to obtaining compensation or increased compensation.

(2) In paragraph (1) “relevant land” means the land acquired from the person concerned or any other land with which he is, or was at the time when the building was erected, the works executed or the improvement or alteration made, directly or indirectly concerned.

Set-off for enhancement in value of retained land

27.(1) In assessing the compensation payable to any person in respect of the acquisition from him under this Order of any land (including the subsoil) the tribunal shall set off against the value of the land so acquired any increase in value of any contiguous or adjacent land belonging to that person in the same capacity which will accrue to him by reason of the construction of the authorised works.

(2) In assessing the compensation payable to any person in respect of the acquisition from him of any new rights over land (including the subsoil) under article 20 (power to acquire new rights), the tribunal shall set-off against the value of the rights so acquired—

(a)any increase in the value of the land over which the new rights are required; and

(b)any increase in value of any contiguous or adjacent land belonging to that person in the same capacity,

which will accrue to him by reason of the construction of the authorised works.

(3) The 1961 Act shall have effect, subject to paragraphs (1) and (2), as if this Order were a local enactment for the purposes of that Act.

Supplementary
Acquisition of part of certain properties

28.(1) This article shall apply instead of section 8(1) of the 1965 Act (as applied by article 18 (application of Part 1 of the Compulsory Purchase Act 1965)) in any case where—

(a)a notice to treat is served on a person (“the owner”) under the 1965 Act (as so applied) in respect of land forming only part of a house, building or manufactory or of land consisting of a house with a park or garden (“the land subject to the notice to treat”); and

(b) a copy of this article is served on the owner with the notice to treat.

(2) In such a case, the owner may, within the period of 21 days beginning with the day on which the notice was served, serve on the undertaker a counter-notice objecting to the sale of the land subject to the notice to treat and stating that he is willing and able to sell the whole (“the land subject to the counter-notice”).

(3) If no such counter-notice is served within that period, the owner shall be required to sell the land subject to the notice to treat.

(4) If such a counter-notice is served within that period, the question whether the owner shall be required to sell only the land subject to the notice to treat shall, unless the undertaker agrees to take the land subject to the counter-notice, be referred to the tribunal.

(5) If on such a reference the tribunal determine that the land subject to the notice to treat can be taken—

(a)without material detriment to the remainder of the land subject to the counter-notice; or

(b)in the case of part of the land consisting of a house with a park or garden, without material detriment to the remainder of the land subject to the counter-notice and without seriously affecting the amenity and convenience of the house,

the owner shall be required to sell the land subject to the notice to treat.

(6) If on such a reference the tribunal determine that only part of the land subject to the notice to treat can be taken—

(a)without material detriment to the remainder of the land subject to the counter-notice; or

(b)in the case of part of land consisting of a house with a park or garden, without material detriment to the remainder of the land subject to the counter-notice and without seriously affecting the amenity and convenience of the house,

the notice to treat shall be deemed to be a notice to treat for that part.

(7) If on such a reference the tribunal determine that—

(a)the land subject to the notice to treat cannot be taken without material detriment to the remainder of the land subject to the counter-notice; but

(b)the material detriment is confined to a part of the land subject to the counter-notice,

the notice to treat shall be deemed to be a notice to treat for the land to which the material detriment is confined in addition to the land already subject to the notice, whether or not the additional land is land which the undertaker is authorised to acquire compulsorily under this Order.

(8) If the undertaker agrees to take the land subject to the counter-notice, or if the tribunal determine that—

(a)none of the land subject to the notice to treat can be taken without material detriment to the remainder of the land subject to the counter-notice or, as the case may be, without material detriment to the remainder of the land subject to the counter-notice and without seriously affecting the amenity and convenience of the house; and

(b)the material detriment is not confined to a part of the land subject to the counter-notice,

the notice to treat shall be deemed to be a notice to treat for the land subject to the counter-notice whether or not the whole of that land is land which the undertaker is authorised to acquire compulsorily under this Order.

(9) In any case where by virtue of a determination by the tribunal under this article a notice to treat is deemed to be a notice to treat for less land or more land than that specified in the notice, the undertaker may, within the period of 6 weeks beginning with the day on which the determination is made, withdraw the notice to treat; and if it does so shall pay the owner compensation for any loss or expense occasioned to him by the giving and withdrawal of the notice, to be determined in case of dispute by the tribunal.

(10) Where the owner is required under this article to sell only part of a house, building or manufactory or of land consisting of a house with a park or garden, the undertaker shall pay him compensation for any loss sustained by him due to the severance of that part in addition to the value of the interest acquired.

Extinction or suspension of private rights of way

29.(1) All private rights of way over land subject to compulsory acquisition under this Order shall be extinguished—

(a)as from the date of acquisition of the land by the undertaker, whether compulsorily or by agreement; or

(b)on the date of entry on the land by the undertaker under section 11(1) of the 1965 Act,

whichever is the sooner.

(2) All private rights of way over land owned by the undertaker which, being within the limits of land which may be acquired shown on the land plan, are required for the purposes of this Order shall be extinguished on the appropriation of the land for any of those purposes by the undertaker.

(3) All private rights of way over land of which the undertaker takes temporary possession under this Order shall be suspended and unenforceable for as long as the undertaker remains in lawful possession of the land.

(4) Any person who suffers loss by the extinguishment or suspension of any private right of way under this article shall be entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

(5) This article does not apply in relation to any right of way to which section 271 or 272 of the 1990 Act (extinguishment of rights of statutory undertakers etc.) or paragraph 2 of Schedule 11 (provisions relating to statutory undertakers etc.) to this Order applies.

Time limit for exercise of powers of acquisition

30.(1) After the end of the period of 5 years beginning with the day on which this Order comes into force—

(a)no notice to treat shall be served under Part 1 of the 1965 Act as applied to the acquisition of land by article 18 (application of Part 1 of the Compulsory Purchase Act 1965); and

(b)no declaration shall be executed under section 4 of the Compulsory Purchase (Vesting Declarations) Act 1981 as applied by article 19 (application of the Compulsory Purchase (Vesting Declarations) Act 1981).

(2) The powers conferred by article 24 (temporary use of land for construction of works) shall cease at the end of the period referred to in paragraph (1), save that nothing in this paragraph shall prevent the undertaker remaining in possession of land after the end of that period, if the land was entered and possession of it was taken before the end of that period.

PART 4Miscellaneous and General

Planning permission and supplementary matters

31.(1) In relation to the application of paragraph 3(c) of the Second Schedule of the Form of Tree Preservation Order set out in the Schedule to the Town and Country Planning (Tree Preservation Order) Regulations 1969(17) (including that paragraph as applied by regulation 3(ii) of the Town and Country Planning (Tree Preservation Order) (Amendment) and (Trees in Conservation Areas) (Exempted Cases) Regulations 1975(18), or as incorporated in any tree preservation order), any direction under section 90(2A) of the 1990 Act deeming planning permission to be granted in relation to works authorised by this Order shall be treated as deeming the permission to have been granted on application made under Part 3 of that Act for the purposes of that Part.

(2) In relation to the application of article 5(1)(d) of the Form of Tree Preservation Order set out in the Schedule to the Town and Country Planning (Trees) Regulations 1999(19) as incorporated in any tree preservation order or as having effect by virtue of regulation 10(1)(a) of those Regulations, any direction under section 90(2A) of the 1990 Act deeming planning permission to be granted in relation to works authorised by this Order shall not be treated as an outline planning permission.

(3) Planning permission which is deemed by a direction under section 90(2A) of the 1990 Act to be granted in relation to works authorised by this Order shall be treated as specific planning permission for the purposes of section 264(3)(a) of that Act (cases in which land is to be treated as operational land of the purposes of that Act).

Power to lop trees overhanging the authorised works

32.(1) The undertaker may fell or lop any tree or shrub near any part of the authorised works, or cut back its roots, if it reasonably believes it to be necessary to do so to prevent the tree or shrub—

(a)from obstructing or interfering with the construction, maintenance or operation of the authorised works or any apparatus used on the authorised works; or

(b)from constituting a danger to passengers or other persons using the authorised works.

(2) In exercising the powers of paragraph (1), the undertaker shall do no unnecessary damage to any tree or shrub and shall pay compensation to any person for any loss or damage arising from the exercise of those powers.

(3) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount of compensation, shall be determined under Part 1 of the 1961 Act.

Open space

33.(1) The special category land shall not vest in the undertaker until the undertaker has acquired the exchange land and [insert name of local authority] has certified that a scheme for the provision of the exchange land as open space has been implemented to its satisfaction.

(2) Upon the requirements of paragraph (1) being satisfied, the exchange land shall vest in [insert name of local authority] subject to the like rights, trusts and incidents as attached to the special category land; and the special category land shall thereupon be discharged from all rights, trusts and incidents to which it was previously subject.

(3) In this article—

“the special category land” means the land described as open space on the plan entitled “Open Space Plan” attached to the land plan, which may be acquired compulsorily under this Order and for which exchange land is to be provided; and

“the exchange land” means the land described as exchange land on the plan entitled “Open Space Plan” attached to the land plan.

Power to operate and use railway

34.(1) The undertaker may operate and use the railway and other authorised works as a system, or part of a system, of transport for the carriage of passengers and goods.

(2) Nothing in this Order, or in any enactment incorporated with or applied by this Order, shall prejudice or affect the operation of Part 1 of the Railways Act 1993(20).

Power to transfer undertaking

35.(1) The undertaker may, with the consent of the Secretary of State—

(a)transfer to another person (“the transferee”) its right to construct, maintain, use or operate the authorised works (or any part of them) and such related statutory rights as may be agreed between the undertaker and the transferee; or

(b)grant to another person (“the lessee”) for a period agreed between the undertaker and the lessee the right to construct, maintain, use or operate the authorised works (or any part of them) and such related statutory rights as may be so agreed.

(2) Where an agreement has been made by virtue of paragraph (1) references in this Order to the undertaker shall include references to the transferee or the lessee.

(3) The exercise of the powers conferred by any enactment by any person in pursuance of any transfer or grant under paragraph (1) shall be subject to the same restrictions, liabilities and obligations as would apply under this Order if those powers were exercised by the undertaker.

Power to charge fares

36.  The undertaker may demand, take and recover or waive such charges for carrying passengers or goods on the railway comprised in the authorised works, or for any other services or facilities provided in connection with the operation of that railway, as it thinks fit.

Application of landlord and tenant law

37.(1) This article applies to—

(a)any agreement for leasing to any person the whole or any part of the authorised works or the right to operate the same; and

(b)any agreement entered into by the undertaker with any person for the construction, maintenance, use or operation of the authorised works, or any part of them,

so far as any such agreement relates to the terms on which any land which is the subject of a lease granted by or under that agreement is to be provided for that person’s use.

(2) No enactment or rule of law regulating the rights and obligations of landlords and tenants shall prejudice the operation of any agreement to which this article applies.

(3) Accordingly, no such enactment or rule of law shall apply in relation to the rights and obligations of the parties to any lease granted by or under any such agreement so as to—

(a)exclude or in any respect modify any of the rights and obligations of those parties under the terms of the lease, whether with respect to the termination of the tenancy or any other matter;

(b)confer or impose on any such party any right or obligation arising out of or connected with anything done or omitted on or in relation to land which is the subject of the lease, in addition to any such right or obligation provided for by the terms of the lease; or

(c)restrict the enforcement (whether by action for damages or otherwise) by any party to the lease of any obligation of any other party under the lease.

Obstruction of construction of authorised works

38.  Any person who, without reasonable excuse—

(a)obstructs any person acting under the authority of the undertaker in setting out the lines of the scheduled works or in constructing any authorised work; or

(b)interferes with, moves or removes any apparatus belonging to any person acting under the authority of the undertaker,

shall be guilty of an offence and liable on summary conviction to a fine not exceeding level 3 on the standard scale.

Trespass

39.(1) Any person who—

(a)trespasses on any part of the railway; or

(b)trespasses on any land of the undertaker in dangerous proximity to the railway or to any electrical or other apparatus used for or in connection with the operation of the railway,

shall be guilty of an offence and liable on summary conviction to a fine not exceeding level 3 on the standard scale.

(2) No person shall be convicted of an offence under this article unless it is shown that a notice warning the public not to trespass on the railway was clearly exhibited and maintained at the station on the railway nearest the place where the offence is alleged to have been committed.

(3) In this article “the railway” means the railway forming part of the authorised works.

Disclosure of confidential information

40.  A person who—

(a)enters a factory, workshop or workplace in pursuance of the provisions of article 15 (protective works to buildings) or article 16 (power to survey and investigate land); and

(b)discloses to any person any information obtained by him relating to any manufacturing process or trade secret,

shall be guilty of an offence and liable on summary conviction to a fine not exceeding level 3 on the standard scale unless the disclosure is made in the course of performing his duty in connection with the purposes for which he was authorised to enter the land.

Statutory undertakers etc.

41.  The provisions of Schedule 11 (provisions relating to statutory undertakers etc.) to this Order shall have effect.

Certification of plans etc.

42.  The undertaker shall, as soon as practicable after the making of this Order, submit copies of the book of reference, the sections, the land plan and the works plan to the Secretary of State for certification that they are, respectively, true copies of the book of reference, sections and plans referred to in this Order; and a document so certified shall be admissible in any proceedings as evidence of the contents of the document of which it is a copy.

Service of notices

43.(1) A notice or other document required or authorised to be served for the purposes of this Order may be served—

(a)by post; or

(b)with the consent of the recipient and subject to paragraphs (6) to (8) by electronic transmission.

(2) Where the person on whom a notice or other document to be served for the purposes of this Order is a body corporate, the notice or document is duly served if it is served on the secretary or clerk of that body.

(3) For the purposes of section 7 of the Interpretation Act 1978(21) as it applies for the purposes of this article, the proper address of any person in relation to the service on him of a notice or document under paragraph (1) is, if he has given an address for service, that address, and otherwise—

(a)in the case of the secretary or clerk of a body corporate, the registered or principal office of that body; and

(b)in any other case, his last known address at the time of service.

(4) Where for the purposes of this Order a notice or other document is required or authorised to be served on a person as having any interest in, or as the occupier of, land and his name or address cannot be ascertained after reasonable enquiry, the notice may be served by—

(a)addressing it to him by name or by the description of “owner”, or as the case may be “occupier”, of the land (describing it); and

(b)either leaving it in the hands of a person who is or appears to be resident or employed on the land or leaving it conspicuously affixed to some building or object on or near the land.

(5) Where a notice or other document required to be served or sent for the purposes of this Order is served or sent by electronic transmission the requirement shall be taken to be fulfilled where the recipient of the notice or other document to be transmitted has given his consent to the use of electronic transmission either in writing or by electronic transmission.

(6) Where the recipient of a notice or other document served or sent by electronic transmission notifies the sender within 7 days of receipt that he requires a paper copy of all or any part of that notice or other document the sender shall provide such a copy as soon as reasonably practicable.

(7) A person may revoke his consent to the use of electronic transmission in accordance with paragraph (8).

(8) Where a person is no longer willing to accept the use of electronic transmission for any of the purposes of this Order—

(a)he shall give notice in writing or by electronic transmission revoking any consent given by him for that purpose; and

(b)such revocation shall be final and shall take effect on a date specified by the person in the notice but that date shall not be less than 7 days after the date on which the notice is given.

(9) This article shall not be taken to exclude the employment of any method of service not expressly provided for by it.

No double recovery

44.  Compensation shall not be payable in respect of the same matter both under this Order and under any other enactment, any contract or any rule of law.

Arbitration

45.  Any difference under any provision of this Order, unless otherwise provided for, shall be referred to and settled by a single arbitrator to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by the President of the Institution of Civil Engineers.

Article 1

SCHEDULE 1SCHEDULED WORKS

Articles 4 and 17

SCHEDULE 2ACQUISITION OF CERTAIN LANDS FOR ANCILLARY WORKS

(1)(2)(3)
AreaNumber of land shown on land planPurpose for which land may be acquired

Article 6

SCHEDULE 3STREETS SUBJECT TO STREET WORKS

(1)(2)
AreaStreet subject to street works

Article 7

SCHEDULE 4STREETS TO BE STOPPED UP

PART 1STREETS FOR WHICH A SUBSTITUTE IS TO BE PROVIDED
(1)(2)(3)(4)
AreaStreet to be stopped upExtent of stopping upNew street to be substituted
PART 2STREETS FOR WHICH NO SUBSTITUTE IS TO BE PROVIDED
(1)(2)(3)
AreaStreet to be stopped upExtent of stopping up

Article 8

SCHEDULE 5STREETS TO BE TEMPORARILY STOPPED UP

(1)(2)(3)
AreaStreet to be temporarily stopped upExtent of temporary stopping up

Article 9

SCHEDULE 6ACCESS TO WORKS

(1)(2)
AreaDescription of access

Article 13

SCHEDULE 7LEVEL CROSSINGS

(1)(2)
AreaHighway to be crossed on the level

Article 20

SCHEDULE 8MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS

Compensation enactments

1.  The enactments for the time being in force with respect to compensation for the compulsory purchase of land shall apply with the necessary modifications as respects compensation in the case of a compulsory acquisition under this Order of a right by the creation of a new right as they apply as respects compensation on the compulsory purchase of land and interests in land.

2.(1) Without prejudice to the generality of paragraph 1, the Land Compensation Act 1973(22) shall have effect subject to the modifications set out in sub-paragraphs (2) and (3).

(2) In section 44(1) (compensation for injurious affection), as it applies to compensation for injurious affection under section 7 of the 1965 Act as substituted by paragraph 4—

(a)for the words “land is acquired or taken” there shall be substituted the words “a right over land is purchased”; and

(b)for the words “acquired or taken from him” there shall be substituted the words “over which the right is exercisable”.

(3) In section 58(1) (determination of material detriment where part of house etc. proposed for compulsory acquisition), as it applies to determinations under section 8 of the 1965 Act as substituted by paragraph 5—

(a)for the word “part” in paragraphs (a) and (b) there shall be substituted the words “a right over land consisting”;

(b)for the word “severance” there shall be substituted the words “right over the whole of the house, building or manufactory or of the house and the park or garden”;

(c)for the words “part proposed” there shall be substituted the words “right proposed”; and

(d)for the words “part is” there shall be substituted the words “right is”.

Application of the 1965 Act

3.(1) The 1965 Act shall have effect with the modifications necessary to make it apply to the compulsory acquisition under this Order of a right by the creation of a new right as it applies to the compulsory acquisition under this Order of land, so that, in appropriate contexts, references in that Act to land are to be read (according to the requirements of the particular context) as referring to, or as including references to—

(a)the right acquired or to be acquired, or

(b)the land over which the right is or is to be exercisable.

(2) Without prejudice to the generality of sub-paragraph (1), Part 1 of the 1965 Act shall apply in relation to the compulsory acquisition under this Order of a right by the creation of a new right with the modifications specified in the following provisions of this Schedule.

4.  For section 7 of the 1965 Act (measure of compensation) there shall be substituted the following section—

In assessing the compensation to be paid by the acquiring authority under this Act regard shall be had not only to the extent (if any) to which the value of the land over which the right is to be acquired is depreciated by the acquisition of the right but also to the damage (if any) to be sustained by the owner of the land by reason of its severance from other land of his, or injuriously affecting that other land by the exercise of the powers conferred by this or the special Act..

5.  For section 8 of the 1965 Act (provisions as to divided land) there shall be substituted the following—

(1) Where in consequence of the service on a person under section 5 of this Act of a notice to treat in respect of a right over land consisting of a house, building or manufactory or of a park or garden belonging to a house (“the relevant land”)—

(a)a question of disputed compensation in respect of the purchase of the right would apart from this section fall to be determined by the Lands Tribunal (“the tribunal”); and

(b)before the tribunal has determined that question the person satisfies the tribunal that he has an interest which he is able and willing to sell in the whole of the relevant land and—

(i)where that land consists of a house, building or manufactory, that the right cannot be purchased without material detriment to that land; or

(ii)where that land consists of such a park or garden, that the right cannot be purchased without seriously affecting the amenity or convenience of the house to which that land belongs,

the [ ] Order 200[ ] (“the Order”) shall, in relation to that person, cease to authorise the purchase of the right and be deemed to authorise the purchase of that person’s interest in the whole of the relevant land including, where the land consists of such a park or garden, the house to which it belongs, and the notice shall be deemed to have been served in respect of that interest on such date as the tribunal directs.

(2) Any question as to the extent of the land in which the Order is deemed to authorise the purchase of an interest by virtue of subsection (1) of this section shall be determined by the tribunal.

(3) Where in consequence of a determination of the tribunal that it is satisfied as mentioned in subsection (1) of this section the Order is deemed by virtue of that subsection to authorise the purchase of an interest in land, the acquiring authority may, at any time within the period of 6 weeks beginning with the date of the determination, withdraw the notice to treat in consequence of which the determination was made; but nothing in this subsection prejudices any other power of the authority to withdraw the notice..

6.  The following provisions of the 1965 Act (which state the effect of a deed poll executed in various circumstances where there is no conveyance by persons with interests in the land), that is to say—

(a)section 9(4) (failure by owners to convey);

(b)paragraph 10(3) of Schedule 1 (owners under incapacity);

(c)paragraph 2(3) of Schedule 2 (absent and untraced owners); and

(d)paragraphs 2(3) and 7(2) of Schedule 4 (common land),

shall be so modified as to secure that, as against persons with interests in the land which are expressed to be overridden by the deed, the right which is to be compulsorily acquired is vested absolutely in the acquiring authority.

7.  Section 11 of the 1965 Act (powers of entry) shall be so modified as to secure that, as from the date on which the acquiring authority has served notice to treat in respect of any right, it has power, exercisable in the like circumstances and subject to the like conditions, to enter for the purpose of exercising that right (which shall be deemed for this purpose to have been created on the date of service of the notice); and sections 12 (penalty for unauthorised entry) and 13 (entry on warrant in the event of obstruction) of the 1965 Act shall be modified correspondingly.

8.  Section 20 of the 1965 Act (protection for interests of tenants at will etc.) shall apply with the modifications necessary to secure that persons with such interests in land as are mentioned in that section are compensated in a manner corresponding to that in which they would be compensated on a compulsory acquisition under this Order of that land, but taking into account only the extent (if any) of such interference with such an interest as is actually caused, or likely to be caused, by the exercise of the right in question.

9.  Section 22 of the 1965 Act (protection of acquiring authority’s possession where by inadvertence an estate, right or interest has not been got in) shall be so modified as to enable the acquiring authority, in circumstances corresponding to those referred to in that section, to continue to be entitled to exercise the right acquired, subject to compliance with that section as respects compensation.

Article 22

SCHEDULE 9LAND OF WHICH ONLY SUBSOIL MORE THAN 9 METRES BENEATH SURFACE MAY BE ACQUIRED

(1)(2)
AreaNumber of land shown on land plan

Article 24

SCHEDULE 10LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

(1)(2)(3)(4)
AreaNumber of land shown on land planPurpose for which temporary possession may be takenAuthorised work

Articles 6, 7, 29 and 41

SCHEDULE 11PROVISIONS RELATING TO STATUTORY UNDERTAKERS ETC.

Apparatus of statutory undertakers etc. on land acquired

1.(1) Sections 271 to 274 of the 1990 Act (power to extinguish rights of statutory undertakers etc. and power of statutory undertakers etc. to remove or re-site apparatus) shall apply in relation to any land acquired or appropriated by the undertaker under this Order subject to the following provisions of this paragraph: and all such other provisions of that Act as apply for the purposes of those provisions (including sections 275 to 278, which contain provisions consequential on the extinguishment of any rights under sections 271 and 272, and sections 279(2) to (4), 280 and 282, which provide for the payment of compensation) shall have effect accordingly.

(2) In the provisions of the 1990 Act, as applied by sub-paragraph (1), references to the appropriate Minister are references to the Secretary of State.

(3) Where any apparatus of public utility undertakers or of a public communications provider is removed in pursuance of a notice or order given or made under section 271, 272 or 273 of the 1990 Act, as applied by sub-paragraph (1), any person who is the owner or occupier of premises to which a supply was given from that apparatus shall be entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by him, in consequence of the removal, for the purpose of effecting a connection between the premises and any other apparatus from which a supply is given.

(4) Sub-paragraph (3) shall not apply in the case of the removal of a public sewer but where such a sewer is removed in pursuance of such a notice or order as is mentioned in that paragraph, any person who is—

(a)the owner or occupier of premises the drains of which communicated with that sewer; or

(b)the owner of a private sewer which communicated with that sewer,

shall be entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by him, in consequence of the removal, for the purpose of making his drain or sewer communicate with any other public sewer or with a private sewerage disposal plant.

(5) The provisions of the 1990 Act mentioned in sub-paragraph (1), as applied by that sub-paragraph, shall not have effect in relation to apparatus as respects which paragraph 2 or Part 3 of the 1991 Act applies.

(6) In this paragraph—

“public communications provider” has the same meaning as in section 151(1) of the Communications Act 2003(23); and

“public utility undertakers” has the same meaning as in the Highways Act 1980(24).

Apparatus of statutory undertakers etc. in stopped up streets

2.(1) Where a street is stopped up under article 7 (stopping up of streets) any statutory utility whose apparatus is under, in, upon, along or across the street shall have the same powers and rights in respect of that apparatus, subject to the provisions of this paragraph, as if this Order had not been made.

(2) Where a street is stopped up under article 7 (stopping up of streets) any statutory utility whose apparatus is under, in, upon, over, along or across the street may, and if reasonably requested to do so by the undertaker shall—

(a)remove the apparatus and place it or other apparatus provided in substitution for it in such other position as the utility may reasonably determine and have power to place it; or

(b)provide other apparatus in substitution for the existing apparatus and place it in such position as aforesaid.

(3) Subject to the following provisions of this paragraph, the undertaker shall pay to any statutory utility an amount equal to the cost reasonably incurred by the utility in or in connection with—

(a)the execution of the relocation works required in consequence of the stopping up of the street; and

(b)the doing of any other work or thing rendered necessary by the execution of the relocation works.

(4) If in the course of the execution of relocation works under sub-paragraph (2)—

(a)apparatus of a better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus; or

(b)apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was,

and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker, or, in default of agreement, is not determined by arbitration to be necessary, then, if it involves cost in the execution of the relocation works exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this paragraph would be payable to the statutory utility by virtue of sub-paragraph (3) shall be reduced by the amount of that excess.

(5) For the purposes of sub-paragraph (4)—

(a)an extension of apparatus to a length greater than the length of existing apparatus shall not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and

(b)where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole shall be treated as if it also had been agreed or had been so determined.

(6) An amount which apart from this sub-paragraph would be payable to a statutory utility in respect of works by virtue of sub-paragraph (3) (and having regard, where relevant, to sub-paragraph (4)) shall, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the utility any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.

(7) Sub-paragraphs (3) to (6) shall not apply where the authorised works constitute major transport works for the purposes of Part 3 of the 1991 Act, but instead—

(a)the allowable costs of the relocation works shall be determined in accordance with section 85 of that Act (sharing of cost of necessary measures) and any regulations for the time being having effect under that section; and

(b)the allowable costs shall be borne by the undertaker and the statutory utility in such proportions as may be prescribed by any such regulations.

(8) In this paragraph—

“apparatus” has the same meaning as in Part 3 of the 1991 Act,

“relocation works” means work executed, or apparatus provided, under sub-paragraph (2), and

“statutory utility” means a statutory undertaker for the purposes of the Highways Act 1980 or a public communications provider as defined in paragraph 1(6).

Railway and navigation undertakings

3.(1) Subject to the following provisions of this paragraph, the powers under article 6 (power to execute street works) of this Order to break up or open a street shall not be exercisable where the street, not being a highway maintainable at public expense (within the meaning of the Highways Act 1980)—

(a)is under the control or management of, or is maintainable by, railway or tramway undertakers or a navigation authority; or

(b)forms part of a level crossing belonging to any such undertakers or to such an authority or to any other person,

except with the consent of the undertakers or authority or, as the case may be, of the person to whom the level crossing belongs.

(2) Sub-paragraph (1) shall not apply to the carrying out under this Order of emergency works, within the meaning of Part 3 of the 1991 Act.

(3) A consent given for the purpose of sub-paragraph (1) may be made subject to such reasonable conditions as may be specified by the person giving it but shall not be unreasonably withheld.

(4) In this paragraph “navigation authority” means any person who has a duty or power under any enactment to work, maintain, conserve, improve or control any canal or other inland navigation, navigable river, estuary, harbour or dock.

(6)

S.I. 2006/1466.

(17)

S.I. 1969/17.

(18)

S.I. 1975/148.

(19)

S.I. 1999/1892.

(20)

1993 c. 43 as amended by the Transport Act 2000 (c. 38) and the Railways Act 2005 (c. 14).

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details