- Latest available (Revised)
- Original (As made)
This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
14.—(1) Subject to paragraphs (2) and (3), the undertaker may construct boreholes and wells and install such pumps and equipment as are required to provide a viable water supply suitable for the Canal and to supply sufficient water to the Canal for the needs of navigation.
(2) Nothing in paragraph (1) shall authorise the carrying out of any works, or the abstraction or discharge of water, except in accordance with the appropriate licence or consent granted by the Environment Agency.
(3) The undertaker may construct boreholes or wells only on land which is shown on the land plans or described in the book of reference.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: