1. A description of the proposed pipe-line works, including in particular—
(a)a description of the physical characteristics of the proposed pipe-line works and the proposed pipe-line, and the land-use requirements during the construction and operational phases;
(b)a description of the main characteristics of the production processes proposed, for instance, the nature and quality of the materials to be used;
(c)an estimate, by type and quantity, of expected residues and emissions (including, without limitation, water, air and soil pollution, noise, vibration, light, heat and radiation) resulting from the proposed pipe-line works and the proposed pipe-line when in operation.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: