Search Legislation

The Construction Contracts (Scotland) Exclusion Order 1998

What Version

 Help about what version
  • Latest available (Revised)
  • Original (As made)

Opening Options

 Help about opening options

Status:

This is the original version (as it was originally made). UK Statutory Instruments are not carried in their revised form on this site.

Development agreements

6.—(1) A construction contract is excluded from the operation of Part II if it is a development agreement, within the meaning given below.

(2) A contract is a development agreement if it includes provision for the grant or disposal of a relevant interest in the land on which take place the principal construction operations to which the contract relates.

(3) In paragraph (2) above, a relevant interest in land means–

(a)ownership; or

(b)a tenant’s interest under a lease for a period which is to expire no earlier than 12 months after the completion of the construction operations under the contract.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made):The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once