Regulation 7

SCHEDULE 4QUALIFYING AUTHORITIES

TABLE OF FEES APPLICABLE ON AND AFTER 1ST OCTOBER 1997

Category of development for which approval is sought:Fee payable:

1.  PLANS AND SPECIFICATIONS FOR THE FOLLOWING OPERATIONS OR WORKS

(i)A.  The erection, construction, alteration or extension of a building (including any transformer or telecommunication mast) excluding anything within C below.

(ii)The erection, construction, alteration or extension of any fences, walls or other barriers (including bunds) for visual or noise screening or dust suppression, or any other fences or walls.

(iii)The erection or construction of gantries or overhead line supports.

(iv)The erection, construction, or installation of lighting equipment.

(a)Where no gross floor space is to be created by the development, £95;

(b)where the area of gross floor space to be created by the development does not exceed 40 square metres, £95;

(c)where the area of gross floor space to be created by the development exceeds 40 square metres but does not exceed 75 square metres, £190; and

(d)where the area of gross floor space to be created by the development exceeds 75 square metres, £190 for each 75 square metres, subject to a maximum of £9,500.

B.  The erection, construction, alteration or extension of a road vehicle park.

£95.

C.  The construction, alteration or extension of any terracing, cuttings, embankments or other earth works.

£95 for each 0.1 hectare of the site area, subject to a maximum of £950.

(i)D.  The formation, laying out or alteration of any means of access to a highway used, or proposed highway proposed to be used, by vehicular traffic.

(ii)The erection, construction, alteration or extension of a pedestrian access to the railway line.

£95.

E.  The disposal of waste or spoil or the excavation of bulk materials from borrow pits.

£95 for each 0.1 hectare of the site area, subject to a maximum of £14,250.

2.  ARRANGEMENTS

A.  Road transport; handling of re-usable spoil or top soil; screening; hours of working; artificial lighting; suppression of noise, dust and vibration; mud on highway; or highway access.

£95.

B.  Storage sites or construction camps.

£95 for each 0.1 hectare of the site area, subject to a maximum of £950.

3.  BRINGING WORKS INTO USE

Bringing into use works referred to in paragraph 9(2) or 17(2) of the Schedule.£95.

4.  MITIGATION OR SITE RESTORATION SCHEMES

Mitigation or site restoration schemes.£95 for each 0.1 hectare of the site area, subject to a maximum of £14,250.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources