- Latest available (Revised)
- Original (As enacted)
This is the original version (as it was originally enacted).
Section 15
1(1)The nominated undertaker may enter upon and take possession of the land specified in the table in Part 4 of this Schedule—
(a)for the purpose specified in relation to the land in column (3) of the table in connection with the authorised works specified in column (4) of the table,
(b)for the purpose of constructing such works as are mentioned in column (5) of the table in relation to the land, or
(c)otherwise for Phase One purposes.
(2)The nominated undertaker may (subject to paragraph 2(1)) enter upon and take possession of any other land within the Act limits for Phase One purposes.
(3)The reference in sub-paragraph (1)(a) to the authorised works specified in column (4) of the table includes a reference to any works which are necessary or expedient for the purposes of or in connection with those works.
2(1)Paragraph 1(2) does not apply in relation to—
(a)land which is subject to a restricted power of compulsory acquisition,
(b)land in respect of which a notice of entry has been served under section 11 of the Compulsory Purchase Act 1965 (as applied by section 4(3) to the acquisition of land under section 4(1)), other than in connection with the acquisition of rights or subsoil only or the imposition of a restrictive covenant, or
(c)land in respect of which a declaration has been made under section 4 of the Compulsory Purchase (Vesting Declarations) Act 1981 (as applied by section 4(4) to the acquisition of land under section 4(1)), other than in connection with the acquisition of rights or subsoil only or the imposition of a restrictive covenant.
(2)The power under section 4(1) (power to acquire land compulsorily) is not exercisable in relation to land specified in the table in Part 4 of this Schedule.
(3)But sub-paragraph (2) does not apply in relation to land specified in the table to the extent (if any) that—
(a)the land is subject to a restricted power of compulsory acquisition, or
(b)there is power by virtue of section 5(3) to impose restrictive covenants over the land.
(4)For the purposes of this Schedule, land is subject to a restricted power of compulsory acquisition if the power under section 4(1) may be exercised in relation to the land only—
(a)so as to acquire rights relating to the land (see section 5(4)),
(b)so as to acquire the subsoil or under-surface of the land or so as to acquire rights of passage over the land (see paragraphs 1 and 2 of Schedule 11),
(ignoring any power by virtue of section 5(3) to impose restrictive covenants over the land).
3(1)Where under paragraph 1(1) or (2) the nominated undertaker has entered upon and taken possession of land, the nominated undertaker may, for the purposes of or in connection with the construction of the works authorised by this Act—
(a)remove any structure or vegetation from the land,
(b)construct such works as are mentioned in relation to the land in column (5) of the table in Part 4 of this Schedule,
(c)construct temporary works (including the provision of means of access) and structures on the land, and
(d)construct landscaping and other works on the land to mitigate any adverse effects of the construction, maintenance or operation of the works authorised by this Act.
(2)The other works referred to in sub-paragraph (1)(d) include works involving the planting of trees and shrubs and the provision of replacement habitat for wild animals.
(3)In this paragraph, “structure” includes any erection.
4(1)Not less than 28 days before entering upon and taking possession of land under paragraph 1(1) or (2), the nominated undertaker must give notice to the owners and occupiers of the land of its intention to do so.
(2)The nominated undertaker may not, without the agreement of the owners of the land, remain in possession of land under paragraph 1(1) or (2) after the end of the period of one year beginning with the date of completion of the work for which temporary possession of the land was taken.
(3)Sub-paragraph (2) does not apply, in the case of land mentioned in paragraph 1(2), if before the end of the one-year period either of the following powers has been exercised in relation to the land—
(a)the power to serve a notice to treat under Part 1 of the Compulsory Purchase Act 1965 (as applied by section 4(3) of this Act to the acquisition of land under section 4(1));
(b)the power to execute a declaration under section 4 of the Compulsory Purchase (Vesting Declarations) Act 1981 (as applied by section 4(4) of this Act to the acquisition of land under section 4(1)).
(4)The nominated undertaker must pay compensation to the owners and occupiers of land of which possession is taken under paragraph 1(1) or (2) for any loss which they may suffer by reason of the exercise in relation to the land of the power or powers under that paragraph.
(5)Any dispute as to a person’s entitlement to compensation under sub-paragraph (4), or as to the amount of compensation, must be determined under and in accordance with Part 1 of the Land Compensation Act 1961.
(6)Nothing in this paragraph affects any liability to pay compensation under section 10(2) of the Compulsory Purchase Act 1965 (as applied by section 4(3) to the acquisition of land under section 4(1)) or under any other enactment, otherwise than for loss for which compensation is payable under sub-paragraph (4).
5(1)Before giving up possession of land of which possession has been taken under paragraph 1(1) or (2), the nominated undertaker must, in accordance with a scheme agreed with the owners of the land and the relevant planning authority, put the land into such condition as the scheme may provide.
(2)If no scheme has been agreed for the purposes of this paragraph within 6 months of the date of completion mentioned in paragraph 4(2) in relation to the land, the scheme is to be such as may be determined by the appropriate Ministers after consulting the nominated undertaker, the owners of the land and the relevant planning authority.
(3)Unless the owners of the land and the nominated undertaker otherwise agree, a scheme determined under sub-paragraph (2) must provide for land to be restored to its former condition.
(4)Sub-paragraph (3) does not require land on which works referred to in paragraph 1(1)(b) or 3(1)(d) have been constructed to be restored to its former condition.
(5)Unless the nominated undertaker otherwise agrees, a scheme determined under sub-paragraph (2) may not provide for the nominated undertaker to replace a structure removed under paragraph 3, other than a fence.
(6)Where the appropriate Ministers ask the relevant planning authority for assistance in connection with the carrying out by them of their function under sub-paragraph (2), they may require the nominated undertaker to reimburse to the relevant planning authority any expenses which it reasonably incurs in meeting the request.
(7)The duty under sub-paragraph (1) in relation to any land is owed separately to the owners of the land and to the relevant planning authority.
(8)Where a scheme for the purposes of this paragraph provides for any step to be taken by the nominated undertaker before a specified date and that step has not been taken before that date, the relevant planning authority may—
(a)enter the land concerned and take that step, and
(b)require the nominated undertaker to reimburse to it any expenses which it reasonably incurs in acting under paragraph (a).
(9)In this paragraph—
“appropriate Ministers” means the Secretary of State for Communities and Local Government and the Secretary of State for Transport and, in relation to the carrying out of any function, means those Ministers acting jointly;
“relevant planning authority” means the unitary authority or, in a non-unitary area, the district council in whose area the land is situated.
(10)But where—
(a)the unitary authority in whose area the land is situated is a London borough council, and
(b)as a result of a Localism Act TCPA order, a Mayoral development corporation is the local planning authority for the purposes of Part 3 of the Town and Country Planning Act 1990 for that area,
the relevant planning authority is the Mayoral development corporation instead of the London borough council.
6(1)The Secretary of State may make regulations modifying the operation of this Part of this Schedule—
(a)in consequence of an order under section 198(2) of the Localism Act 2011 giving effect to a decision under section 204(2) of that Act (decision removing or restricting planning functions), or
(b)to make transitional provision relating to—
(i)an order mentioned in paragraph (a),
(ii)a Localism Act TCPA order, or
(iii)an order under section 217 of the Localism Act 2011 (order dissolving Mayoral development corporation).
(2)Regulations under this paragraph—
(a)must be made by statutory instrument;
(b)may make different provision for different purposes.
(3)A statutory instrument containing regulations under this paragraph is subject to annulment in pursuance of a resolution of either House of Parliament.
7(1)At any time during the maintenance period relating to any of the scheduled works, the nominated undertaker may—
(a)enter upon and take possession of any land which is—
(i)within 20 metres from that work, and
(ii)within the Act limits,
if possession of the land is reasonably required for the purposes of or in connection with maintaining the work or any ancillary works connected with it, and
(b)construct on the land such temporary works (including the provision of means of access) and structures as may be reasonably so required, unless the land is specified in the table in Part 4 of this Schedule.
(2)Sub-paragraph (1) does not authorise the nominated undertaker to take possession of—
(a)a house, any other structure which is for the time being occupied, or a garden belonging to a house, or
(b)land which is subject to a restricted power of compulsory acquisition.
(3)The nominated undertaker may only remain in possession of the land for so long as may be reasonably required to carry out the maintenance works for which possession of the land was taken.
(4)In this paragraph—
(a)“the maintenance period”, in relation to any work, means the period beginning with the date on which the work is completed and ending 5 years after the date on which it is brought into general use;
(b)“structure” includes any erection;
(c)the reference in sub-paragraph (1)(a) to land within a specified distance of a work includes, in the case of a work under the surface of the ground, a reference to land within the specified distance of any point on the surface below which the work is situated.
8(1)Not less than 28 days before entering upon and taking possession of land under paragraph 7, the nominated undertaker must give notice to the owners and occupiers of the land of its intention to do so.
(2)Before giving up possession of the land, the nominated undertaker must restore the land to the reasonable satisfaction of its owners.
(3)The nominated undertaker must pay compensation to the owners and occupiers of the land for any loss which they may suffer by reason of the exercise in relation to the land of the powers under paragraph 7.
(4)Any dispute as to a person’s entitlement to compensation under sub-paragraph (3), or as to the amount of compensation, must be determined under and in accordance with Part 1 of the Land Compensation Act 1961.
(5)Nothing in this paragraph affects any liability to pay compensation under section 10(2) of the Compulsory Purchase Act 1965 (as applied by section 4(3) of this Act to the acquisition of land under section 4(1)), or under any other enactment, otherwise than for loss for which compensation is payable under sub-paragraph (3).
9(1)All private rights over land of which the nominated undertaker takes possession under paragraph 1 (1) or (2) or 7 are suspended and unenforceable for as long as the nominated undertaker remains in lawful possession of the land.
(2)The nominated undertaker may, in relation to a private right, direct—
(a)that sub-paragraph (1) does not apply to the right, or
(b)that sub-paragraph (1) applies to the right only to the extent specified in the direction.
(3)In this paragraph, “private rights” include—
(a)private rights of way over land,
(b)rights of common,
(c)easements, liberties, privileges, rights or advantages annexed to land and adversely affecting other land, including any natural right to support, and
(d)restrictions as to the user of land arising under a contract.
(4)Any person who suffers loss by reason of the suspension of a right under sub-paragraph (1) is entitled to be compensated by the nominated undertaker.
(5)Any dispute as to a person’s entitlement to compensation under sub-paragraph (4), or as to the amount of compensation, must be determined under and in accordance with Part 1 of the Land Compensation Act 1961.
(6)This paragraph applies to a private right which is for the benefit of Crown land if the Crown authority consents (and consent may be subject to conditions).
10(1)All general rights over land of which the nominated undertaker takes possession under paragraph 1 (1) or (2) or 7 are suspended and unenforceable for as long as the nominated undertaker remains in lawful possession of the land.
(2)The nominated undertaker may, in relation to a general right, direct—
(a)that sub-paragraph (1) does not apply to the right, or
(b)that sub-paragraph (1) applies to the right only to the extent specified in the direction.
(3)In this paragraph, references to “general rights” over land are to—
(a)rights to access land (however expressed) which are exercisable as a result of section 2(1) of the Countryside and Rights of Way Act 2000 or an enactment mentioned in section 15 of that Act,
(b)other public rights over land which are conferred by an enactment, and
(c)rights exercisable as a result of trusts or incidents to which a common, town or village green, open space or allotment is subject.
11(1)Section 13 of the Compulsory Purchase Act 1965 (refusal to give possession to acquiring authority) applies for the purposes of this Schedule as if—
(a)references to the acquiring authority were to the nominated undertaker,
(b)references to compensation payable to the person refusing to give possession were to compensation payable under this Schedule, and
(c)in subsection (1), for “this Act” there were substituted “Schedule 16 to the High Speed Rail (London - West Midlands) Act 2017”.
(2)In the case of Crown land, that section does not, by virtue of sub-paragraph (1), apply as against the Crown authority for that land.
(1) | (2) | (3) | (4) | (5) |
---|---|---|---|---|
Area | Number of land shown on deposited plans | Purpose for which temporary possession may be taken | Specified authorised works | Specified works which may be carried out |
London Borough of Camden | 192, AP3-27 | Provision of worksite and access for construction | 1/18 | |
291 to 305307, 308 | Provision of access for utility works | 1/1 | ||
312, 313, 314, 317, 346, 350 to 360, 771 to 776 | Diversion or installation of, or works to, utilities apparatus | 1/1 | ||
705, 706, 708 | Diversion or installation of, or works to, utilities apparatus | 1/15 | ||
London Borough of Brent | 22, 24, 30, 31, 34, 44, 45, 67, 71, 73, 382, 390 to 393 | Diversion or installation of, or works to, utilities apparatus | 1/15 | |
60, 61, 114, 118, 121 | Diversion or installation of, or works to, utilities apparatus | 1/1 | ||
82, 85 | Diversion or installation of, or works to, utilities apparatus | 1/21 | ||
AP2-2 | Provision of access for utility works | 1/52 | ||
AP4-15a | Provision of worksite and access for construction | 1/1 | ||
London Borough of Hammersmith & Fulham | 15 | Diversion or installation of, or works to, utilities apparatus | 1/1 | |
24, 25a, 25b | Diversion or installation of, or works to utilities apparatus | 1/15 | ||
London Borough of Ealing | 23 | Diversion or installation of, or works to, utilities apparatus | 1/40 | |
878, 879 | Provision of worksite and access for construction | 1/1 | ||
Diversion or installation of, or works to, utilities apparatus | ||||
473, 475, 478, 479, 481, 482, 485, 488, 513 to 516, 527 to 535, 537 to 539, 543, 546, 549, 552, 554, 559, 563 to 566, 568 to 578, 690, 701, 881 to 883, 965, 966, 983 | Diversion or installation of, or works to, utilities apparatus | 1/1 | ||
676 to 682 | Diversion or installation of, or works to, utilities apparatus | 1/15 | ||
708, 954 | Provision of worksite and access for construction | |||
871, 873, 874 | Worksite and access for construction | 1/55 | ||
Diversion or installation of, or works to, utilities apparatus | ||||
1028, 1029, 1031 to 1034 | Provision worksite and access for construction | Diversion or installation of, or works to, utilities apparatus | ||
Provision of environmental mitigation | ||||
London Borough of Hillingdon | 34, 187 to 189, 249, 254 | Provision of access for utility works | Diversion or installation of, or works to, utilities apparatus | |
59, 60, 76, 174 | Provision of worksite and access for construction | Diversion or installation of, or works to, utilities apparatus | ||
81, 82, 83, 86,144 to 147, 222, 226, 228,250, 252, 253 | Diversion or installation of, or works to utilities apparatus | 1/15 | ||
157, 159, 161, 162 | Provision of worksite and access for construction | 1/57 | ||
372 to 375, 380 to 383 | Diversion or installation of, or works to, utilities apparatus | 1/1 and 1/15 | ||
720e | Provision of access for construction | Provision of environmental mitigation | ||
598, 602, 681, 682, 684 to 687, 689 to 691 | Diversion and installation of overhead electric lines | 2/1 | ||
703a, 703b,704 to 706747c, 750 | Provision of worksite and access for construction | 2/1 | ||
720a, AP5-15 to AP5-20 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | ||
733 | Diversion or installation of, or works to utilities apparatus | 2/1 | ||
County of Buckinghamshire District of South Bucks Parish of Denham | 4, 5, 5a, 6 | Provision of worksite and access for construction | Provision of environmental mitigation | |
9, 10, 13 | Provision of worksite and access for construction | 2/5 | ||
20 | Provision of worksite and access for construction | 2/6 | ||
County of Hertfordshire District of Three Rivers | 118 | Provision of worksite and access for construction | 2/10a | |
County of Buckinghamshire District of Chiltern Parish of Chalfont St Peter | 15, 17, 18, 20 | Provision of worksite and access for construction | 2/1 | |
73 | Provision of access for construction | |||
Parish of Chalfont St Giles | 1, 3 | Provision of access for construction | ||
9, 46, 59, 93 to 95, 99, 101, 102 | Provision of protective works to watercourse | 2/1 | Protective works to watercourse | |
Parish of Amersham | AP4-1, AP4-3 | Reprofiling of ground | 2/1 | Reprofiling of ground |
40, 58 | Dewatering operations | 2/1 | Dewatering operations | |
61 | Provision of access for site investigation | 2/1 | ||
75 | Provision of access for construction | 2/1 | ||
Parish of Great Missenden | AP4-16, AP4-17 | Provision of worksite and access for construction | 2/14 | |
District of Aylesbury Vale Parish of Wendover | 105, 106, AP1-2 to AP1-7, AP1-9 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
107, AP1-1, AP1-8 | Implementation of protective measures for land beneath overhead line works | Diversion and installation of overhead electric lines | ||
200, 201 | Diversion and installation of overhead electric lines | 2/28 | ||
District of Wycombe Parish of Ellesborough | 1, 3, 7, 9, 29, 31, 43, AP1-2, AP1-3 | Diversion and installation of overhead electric lines | 2/28 | |
District of Aylesbury Vale Parish of Stoke Mandeville | 1 to 3118a, 121 | Diversion and installation of overhead electric lines | 2/28 | |
Parish of Stone with Bishopstone and Hartwell | 2, 5, 12 | Diversion and installation of overhead electric lines | 2/28 | |
AP5-1, AP5-2 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | ||
Parish of Aylesbury | 4, 7 to 14, 16, 17, 19, 25 to 27, AP1-1 to AP1-3 | Implementation of protective measures for land beneath overhead line works | Diversion and installation of overhead electric lines | |
Parish of Waddesdon | 12, 22, 23 | Reprofiling of ground | ||
99 | Removal of utility apparatus | 2/49 | ||
Parish of Quainton | 15, 26, 28, 30, 34 | Removal of utility apparatus | ||
236, 238, 242, AP1-2, AP1-3, AP1-6 to AP1-14, AP1-21 | Diversion and installation of overhead electric lines | |||
Parish of Grendon Underwood | AP1-10, AP1-11 | Diversion and installation of overhead electric lines | ||
AP5-1, AP5-2 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | ||
Parish of Hogshaw | 3 to 6, 8, 13, 15, 16 | Diversion and installation of overhead electric lines | ||
AP5-1 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | ||
Parish of Steeple Claydon | 104 | Provision of access for construction | ||
Provision of new public right of way | ||||
Parish of Chetwode | 61, 81, 82 | Removal of utility apparatus | 2/49 | |
County of Oxfordshire District of Cherwell Parish of Newton Purcell with Shelswell | 69a, 87 | Removal of utility apparatus | ||
89 to 91 | Provision of new public right of way | |||
Parish of Finmere | 1 to 3 | Provision of new public right of way | ||
20, 27b, 43a, 44, AP1-5, AP1-7 | Removal of utility apparatus | |||
50, 53, 61 to 66, 69, 70 | Diversion and installation of overhead electric lines | |||
67 and 68 | Provision of access for utility works | |||
Parish of Mixbury | 30, 58, 59, 61 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
45a | Provision of new public right of way | 2/49 | ||
55, 65 | Removal of utility apparatus | 2/49 | ||
County of Buckinghamshire District of Aylesbury Vale Parish of Westbury | 2 to 4, 15 to 17 | Removal of utility apparatus | 2/49 | |
10 to 13 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | ||
Parish of Turweston | 1, 1a, 2, 2a, 3a, 4a, 5a, 6a, 7a, 8a, 10a, 11a, 34, 92, 93 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
22, 23, 26, 27a | Removal of utility apparatus | 2/49 | ||
County of Northamptonshire District of South Northamptonshire Parish of Evenly | 2 to 5 | Diversion and installation of overhead electric lines | ||
Parish of Greatworth | 2, 8a, 40, 41 | Provision of new public right of way | 2/111 | |
12a, 37, 45 | Removal of utility apparatus | 2/111 | ||
AP2-4 | Provision of temporary public right of way | 1/52 | ||
Parish of Thorpe Manderville | 34, 37, 38 | Removal of utility apparatus | 2/111 | |
Parish of Culworth | 3 | Removal of utility apparatus | 2/111 | |
Parish of Chipping Warden and Edgcote | 42, 55, 56, 70 | Removal of utility apparatus | 2/111 | |
102 | Provision of new public right of way | 2/128b | ||
Parish of Aston Le Walls | 12 | Provision of new public right of way | 2/111 | |
Parish of Boddington | 5 | Provision of new public right of way | 2/111 | |
21 | Diversion or installation of, or works to, utilities apparatus | 2/129 | ||
44, 79, 83, 84, 100, 102 | Removal of utility apparatus | 2/111 | ||
County of Warwickshire District of Stratford-on-Avon Parish of Wormleighton | 33 | Reprofiling of ground | 2/133 | Reprofiling of ground |
37 | Provision of worksite and access for construction | 2/137 | ||
41 | Provision of worksite and access for construction | 2/133 | ||
45, 51, 57 | Provision of worksite and access for construction | 2/133 | Reprofiling of ground | |
Reprofiling of ground | ||||
Parish of Stoneton | 23 | Provision of worksite and access for construction and maintenance | 2/133 | |
26 | Provision of worksite and access for construction and maintenance | 2/133 | Provision of environmental mitigation | |
Parish of Radbourn | 17, 27 | Provision of worksite and access for construction | 2/139 | |
4 | Provision of worksite and access for construction | 2/133 | Reprofiling of ground | |
Reprofiling of ground | ||||
Parish of Ladbroke | 4, 11 | Provision of worksite and access for construction | 2/133 | Reprofiling of ground |
Reprofiling of ground | ||||
Parish of Southam | 20 | Provision of worksite and access for construction | 2/142c | |
District of Warwick Parish of Offchurch | 14, 16 | Provision of worksite and access for construction | 2/146 | Reprofiling of ground |
Reprofiling of ground | ||||
46 | Reprofiling of ground | 2/146 | Reprofiling of ground | |
72 | Provision of access for construction and maintenance | 2/146 | ||
Parish of Cubbington | 8 | Provision of balancing pond and associated works and access for maintenance | Provision of balancing pond and associated works and access for maintenance | |
63 | Provision of worksite and access for construction | 2/163 | ||
Parish of Stoneleigh | 30, 46 | Removal of utility apparatus | Utility diversion | |
156 | Provision of environmental mitigation | 2/175 | ||
Parish of Burton Green | 36 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
Metropolitan Borough of Solihull Parish of Berkswell | 19a, 19b, 20 to 22, 23a, 27a, 29a | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
18b, 30b | Provision of access for utility works | Diversion and installation of overhead electric lines | ||
AP4-1 | Provision of access for utility works | |||
Parish of Chelmsley Wood | 10, 16, 70 | Provision of worksite and access for construction | 3/25 | |
19 to 63, 65, 66, 68 | Implementation of protective measures for land beneath overhead line works | Diversion and installation of overhead electric lines | ||
Parish of Hampton-in-Arden | AP4-1, AP4-2 | Provision of a temporary parking facility | ||
County of Warwickshire District of North Warwickshire Parish of Coleshill | 1d | Provision of access for utility works | Diversion and installation of overhead electric lines | |
72, 76, 79, 80, 81, 82, 84, 86, 88, 112a, 261, 262, 265, 273, 307, 311, 356 | Provision of access for utility works | Diversion and installation of overhead electric lines | ||
418 | Reprofiling of ground | Reprofiling of ground | ||
Removal of utility apparatus | ||||
421, 423, 426, 429 | Implementation of protective measures for land beneath overhead line works | Diversion and installation of overhead electric lines | ||
AP1-1 to AP1-10 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | ||
Parish of Curdworth | 20, 198, 207, 232, AP4-34 to AP4-36, AP4-38 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
53 | Implementation of protective measures for land beneath overhead line works | Diversion and installation of overhead electric lines | ||
124, 158 | Provision of worksite and access for construction | 3/36 | ||
AP1-9 to AP1-11 | Provision of worksite and access for construction | 3/45A | ||
Parish of Lea Marston | AP4-7 to AP4-9 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
Parish of Wishaw and Moxhull | 4, 6c, 7, 9a, 10, AP1-6 to AP1-10 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
AP1-2 | Provision of worksite and access for construction | 3/45A | ||
Parish of Middleton | 14, AP1-1 to AP1-3, AP1-4a, AP1-5 to AP1-7, AP1-12, AP2-23, AP2-26, AP2-27 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
36, 64 | Removal of utility apparatus | 3/48A | ||
68a | Provision of access for utility works | 3/50a | ||
86 | Reprofiling of ground | 3/48A | Reprofiling of ground | |
25a, AP1-4a | Diversion and installation of overhead electric lines | |||
Access for construction | ||||
37b | Removal of utility apparatus | 3/48A | ||
County of Staffordshire District of Lichfield Parish of Drayton Bassett | 91, 125, 121, 126, 127, AP1-1 to AP1-9 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
Parish of Fazeley | 1 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
Parish of Hints | 32, 34, 36, 40 to 44, 46 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
136 to 138 | Removal of utility apparatus | Diversion or installation of, or works to, utilities apparatus | ||
Parish of Weeford | 1, 2, 3a, 4, AP1-2, AP5-1 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
Parish of Swinfen and Packington | 13a, AP2-3 | Provision of access for construction | 3/48A | |
AP1-1, AP1-2 | Implementation of protective measures for land beneath overhead line works | Diversion and installation of overhead electric lines | ||
Parish of Lichfield | AP4-4 to AP4-10 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
5 | Provision of worksite and access for construction | 3/112 | ||
Parish of Fradley and Streethay | AP4-1, AP4-2 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
139 | Provision of worksite and access for construction | 3/112 | ||
Parish of Curborough and Elmhurst | 4, 5, AP4-1, AP4-2, AP4-10 to AP4-12 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
Parish of Longdon | 12b, AP1-1a, AP1-2a, AP5-1, AP5-2 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
Parish of King’s Bromley | 153 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
Parish of Armitage with Handsacre | 21, 22 | Provision of worksite and access for construction | 3/106 | |
Parish of Mavesyn Ridware | 1, 2, 3, 4 | Provision of worksite and access for construction | Installation of signal gantries | Installation of signal gantries |
2a | Installation of signal gantries | Installation of signal gantries | Installation of signal gantries | |
Parish of Colton | 1, 20 | Provision of worksite and access for construction | Installation of signal gantries | Installation of signal gantries |
2, 3, 5, 6, 8, 13, 14, 19, 21, 22 | Provision of worksite and access for construction | Installation of signal gantries | ||
County of Staffordshire Borough of Stafford Parish of Colwich | 1, 3, 7, 9 | Provision of worksite and access for construction | Installation of signal gantries | Installation of signal gantries |
7a, 2, 4, 5, 6, 8, 19a, 20, 21, 22, 23, 26, AP2-2 to AP2-6 | Provision of worksite and access for construction | Installation of signal gantries | ||
Metropolitan Borough of Solihull Parish of Bickenhill | 3b | Provision of access for utility works | Diversion and installation of overhead electric lines | |
38 | Provision of worksite and access for construction | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | |
41a | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | ||
County of Warwickshire District of North Warwickshire Parish of Little Packington | 6a | Provision of access for utility works | Diversion and installation of overhead electric lines | |
City of Birmingham | 57, 59, 61 | Diversion or installation of, or works to, utilities apparatus | 3/200 | |
172, 174, 176 | Provision of worksite and access for construction | 3/207 | ||
191 | Use of sidings | 3/205 | ||
300 | Provision of worksite and access for constructionDiversion and installation of overhead electric lines | Diversion and installation of overhead electric lines | ||
412 | Provision of drainage and associated works | Highway works | Provision of drainage and associated works | |
446, 451 | Provision of worksite and access for constructionDiversion and installation of overhead electric lines | 3/205 | Diversion and installation of overhead electric lines | |
AP4-3 to AP4-7, AP4-11 to AP4-19 | Diversion and installation of overhead electric lines | Diversion and installation of overhead electric lines |
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: