(1)Any person who without planning permission—
(a)uses land, or causes or permits land to be used—
(i)for any purpose for which an order under section 71 or paragraph 1 of Schedule 8 has required that its use shall be discontinued, or
(ii)in contravention of any condition imposed by such an order by virtue of subsection (1) of that section or, as the case may be, sub-paragraph (1) of that paragraph,
(b)resumes, or causes or permits to be resumed, development consisting of the winning and working of minerals or involving the depositing of mineral waste the resumption of which an order under paragraph 3 of that Schedule has prohibited, or
(c)contravenes, or causes or permits to be contravened, any such requirement as is specified in sub-paragraph (3) or (4) of that paragraph,
shall be guilty of an offence.
(2)Any person who contravenes any requirement of a suspension order or a supplementary suspension order under paragraph 5 or 6 of Schedule 8 or who causes or permits any requirement of such an order to be contravened shall be guilty of an offence.
(3)Any person guilty of an offence under this section shall be liable—
(a)on summary conviction, to a fine not exceeding the statutory maximum, and
(b)on conviction on indictment, to a fine.
(4)It shall be a defence for a person charged with an offence under this section to prove that he took all reasonable measures and exercised all due diligence to avoid commission of the offence by himself or by any person under his control.
(5)If in any case the defence provided by subsection (4) involves an allegation that the commission of the offence was due to the act or default of another person or due to reliance on information supplied by another person, the person charged shall not, without the leave of the court, be entitled to rely on the defence unless, within a period ending 7 clear days before the hearing, he has served on the prosecutor a notice in writing giving such information identifying or assisting in the identification of the other person as was then in his possession.
(1)This section applies where—
(a)any step required by an order under section 71 or paragraph 1 of Schedule 8 to be taken for the alteration or removal of any buildings or works or any plant or machinery,
(b)any step required by an order under paragraph 3 of that Schedule to be taken—
(i)for the alteration or removal of plant or machinery, or
(ii)for the removal or alleviation of any injury to amenity, or
(c)any step for the protection of the environment required to be taken by a suspension order or a supplementary suspension order under paragraph 5 or 6 of that Schedule,
has not been taken within the period specified in the order or within such extended period as the planning authority may allow.
(2)Where this section applies the planning authority may enter the land and take the required step and may recover from the person who is then the owner of the land any expenses reasonably incurred by them in doing so.
(3)A planning authority taking any step under subsection (1) may sell any materials removed by them from any land unless those materials are claimed by the owner within 3 days of their removal by the planning authority.
(4)Where such materials have been sold the planning authority shall pay the owner the net proceeds of the sale after deducting any expenses recoverable by them from him.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: