10(1)Subject to sub-paragraph (2), nothing in a suspension order or a supplementary suspension order shall prevent the recommencement of development consisting of the winning and working of minerals in, on or under the land in relation to which the order has effect.
(2)No person shall recommence such development without first giving the mineral planning authority notice of his intention to do so.
(3)A notice under sub-paragraph (2) shall specify the date on which the person giving the notice intends to recommence development consisting of the winning and working of minerals.
(4)The mineral planning authority shall revoke the order if development consisting of the winning and working of minerals has recommenced to a substantial extent in, on or under the land in relation to which the order has effect.
(5)If the authority do not revoke the order before the end of the period of two months from the date specified in the notice under sub-paragraph (2), the person who gave that notice may apply to the Secretary of State for the revocation of the order.
(6)Notice of an application under sub-paragraph (5) shall be given by the applicant to the mineral planning authority.
(7)If he is required to do so by the person who gave the notice or by the mineral planning authority, the Secretary of State shall, before deciding whether to revoke the order, give him and the mineral planning authority an opportunity of appearing before, and being heard by, a person appointed by the Secretary of State for the purpose.
(8)If the Secretary of State is satisfied that development consisting of the winning and working of minerals in, on or under the land has recommenced to a substantial extent, he shall revoke the order.
(9)If the Secretary of State revokes an order by virtue of sub-paragraph (8), he shall give notice of its revocation—
(a)to the person who applied to him for the revocation, and
(b)to the mineral planning authority.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: