(1)Where a dwelling which is subject to a controlled tenancy does not satisfy the qualifying conditions, and the works required for those conditions to be satisfied cannot be carried out without the consent of the tenant, then, if those works are specified in an application for a certificate of fair rent, his consent shall be of no effect unless given or confirmed in writing after the issue of the certificate.
(2)Where a dwelling which is subject to a statutory tenancy (whether a controlled or a regulated tenancy) does not satisfy the qualifying conditions and the works required for those conditions to be satisfied cannot be carried out without the consent of the tenant but the tenant is unwilling to give or confirm his consent, then, if the conditions specified in subsection (3) of this section are satisfied, the county court may, on the application of the landlord, make an order empowering him to enter and carry out the works.
(3)The said conditions are—
(a)that the works were specified in an application for a certificate of fair rent and the certificate has been issued; and
(b)that, if the statutory tenancy is a regulated tenancy, the works were also specified in an application for a grant under Part I of this Act and the application has been approved; and
(c)that the court is not precluded from making the order by section 55 of this Act.
(4)An order under subsection (2) of this section may be made subject to such conditions as to the time at which the works are to be carried out and as to any provision to be made for the accommodation of the tenant and his household whilst they are carried out as the court may think fit; and where such an order is made subject to any condition as to time, compliance with that condition shall be deemed to be also compliance with any condition imposed by the local authority under section 4(4) or section 10 of this Act.
(5)In determining whether to make such an order and, if it is made, subject to what, if any, conditions, the court shall have regard to all the circumstances and, in particular, to any disadvantage to the tenant that might be expected to result from the works, the accommodation that might be available for him whilst the works are carried out, his means in relation to the increase of rent that would result and the stages in which that increase would become recoverable under the provisions of this Part of this Act.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: