For the protection of the British Railways Board (in this section referred to as “the railways board”) the following provisions shall unless otherwise agreed in writing between the Corporation and the railways board apply:—
(1)In this section—
“construction” includes execution, placing, alteration and reconstruction and “construct” and “constructed” have corresponding meanings;
“the engineer” means an engineer to be appointed by the railways board;
“plans” includes sections, drawings, specifications, soil reports, calculations and descriptions (including descriptions of methods of construction);
“railway property” means any railway of the railways board and any works connected therewith for the maintenance or operation of which the railways board are responsible and includes any land held or used by the railways board for the purposes of such railway or works;
“specified works” means so much of the works and operations authorised by this Act (whether temporary or permanent) as may be situated upon, across, under or over or within 15 metres of, or may in any way affect railway property and includes the construction, maintenance and renewal of such works:
(2)The exercise of the powers of the [1845 c. 20.] Railways Clauses Consolidation Act 1845 with respect to the temporary occupation of land, as applied by section 3 (Incorporation of general enactments) of, and incorporated with, this Act, shall not prevent the exercise by the railways board of such rights as the railways board may have of access (with or without vehicles, machinery and materials) for the railways board and their agents and employees over any such land to and from railway property:
(3)The Corporation shall before commencing the specified works (other than works of maintenance or repair) furnish to the railways board proper and sufficient plans, sections and particulars thereof for the reasonable approval of the engineer and shall not commence the specified works until plans thereof have been approved in writing by the engineer or settled by arbitration:
Provided that if within 56 days after such plans, sections and particulars have been furnished to the railways board the engineer has not intimated his disapproval thereof and the grounds of his disapproval he shall be deemed to have approved the same:
(4)If within 56 days after such plans have been furnished to the railways board, the railways board give notice to the Corporation that the railways board desire themselves to construct any part of the specified works which in the opinion of the engineer will or may affect the stability of railway property then, if the Corporation desires such part of the specified works to be constructed, the railways board shall construct the same with all reasonable dispatch on behalf of and to the reasonable satisfaction of the Corporation in accordance with the plans approved or deemed to be approved or settled as aforesaid:
(5)Upon signifying his approval or disapproval of the plans the engineer may specify any protective works (whether temporary or permanent) which in his opinion should be carried out before the commencement of the specified works to ensure the safety or stability of railway property and such protective works as may be reasonably necessary for those purposes shall be constructed by the railways board or by the Corporation, if the railways board so desire, with all reasonable dispatch and the Corporation shall not commence the construction of the specified works until the engineer has notified the Corporation that the protective works have been completed to his reasonable satisfaction:
(6)The Corporation shall give to the railways board not less than 28 days' notice in writing of its intention to commence the construction of any of the specified works and, (except in emergency when the Corporation shall give such notice as may be reasonably practicable), also of its intention to carry out any works for the repair or maintenance of the specified works:
(7)The specified works shall, when commenced, be carried out—
(a)with all reasonable dispatch in accordance with the plans approved or deemed to have been approved or settled as aforesaid;
(b)under the supervision (if given) and to the reasonable satisfaction of the engineer;
(c)in such manner as to cause as little damage to railway property as may be; and
(d)so far as is reasonably practicable, so as not to interfere with or obstruct the free, uninterrupted and safe user of any railway of the railways board or the traffic thereon and the use by passengers of railway property;and, if any damage to railway property or any such interference or obstruction shall be caused or take place, the Corporation shall, notwithstanding any such approval as aforesaid, make good such damage and shall on demand pay to the railways board all reasonable expenses to which they may be put and compensation for any loss which they may sustain by reason of any such damage, interference or obstruction:
(8)The Corporation shall—
(a)at all times afford reasonable facilities to the engineer for access to the specified works during their construction;
(b)ensure access for the engineer at all reasonable times to all working sites, depots and premises at which materials to be employed in the construction of the specified works are being made, constructed or assembled;
(c)supply the engineer with all such information as he may reasonably require with regard to the specified works or the method of construction thereof:
(9)The railways board shall at all times afford reasonable facilities to the Corporation and its agents for access to any works carried out by the railways board under this section during their construction and shall supply the Corporation with such information as it may reasonably require with regard to such works or the method of construction thereof:
(10)If any alterations or additions, either permanent or temporary, to railway property are reasonably necessary in consequence of the construction of the specified works, such alterations and additions may be effected by the railways board after not less than 28 days' notice has been given to the Corporation and the Corporation shall pay to the railways board on demand the cost thereof as certified by the engineer including, in respect of permanent alterations and additions, a capitalised sum representing the increased or additional cost of maintaining, working and, when necessary, renewing any such alterations or additions:
(11)The Corporation shall repay to the railways board all costs and charges and expenses reasonably incurred by the railways board—
(a)in constructing any part of the specified works on behalf of the Corporation as provided by paragraph (4) of this section or in constructing any protective works under the provisions of paragraph (5) of this section including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works;
(b)in respect of the employment of any inspectors, signalmen, watchmen and other persons whom it is reasonably necessary to appoint for inspecting, watching, lighting and signalling railway property and for preventing as far as may be all interference, obstruction, danger or accident arising from the construction, maintenance, repair or failure of the specified works;
(c)in respect of any special traffic working resulting from any speed restrictions which are necessary as a result of the construction, maintenance, repair or failure of the specified works and which may in the opinion of the engineer be required to be imposed or from the substitution, suspension or diversion of services which may be necessary for the same reason;
(d)in respect of any additional temporary lighting of railway property in the vicinity of the specified works being lighting made reasonably necessary as a result of the specified works or the failure thereof;
(e)in respect of the approval by the engineer of plans submitted by the Corporation and the supervision by him of the specified works:
(12)If at any time after the completion of the specified works, not being works vested in the railways board, the railways board give notice to the Corporation informing it that the state of repair of the specified works appears to be such as prejudicially to affect railway property, the Corporation shall, on receipt of such notice, take such steps as may be reasonably necessary to put the specified works in such state of repair as not prejudicially to affect railway property and, if and whenever the Corporation fails to do so, the railways board may make and do in and upon the land of the railways board or of the Corporation all such works and things as shall be requisite to put the specified works in such state of repair as aforesaid and the costs and expenses reasonably incurred by the railways board in so doing shall be repaid to them by the Corporation:
(13)The Corporation shall not exercise the powers of section 11 (Dredging and other operations in river) of this Act within a distance of 50 metres of any railway property otherwise than in accordance with the provisions of this section:
(14)Any difference arising between the Corporation and the railways board under this section (other than a difference as to the meaning or construction of this section) shall be referred to and settled by arbitration.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: