- Latest available (Revised)
- Original (As made)
This is the original version (as it was originally made).
48.—(1) Subject to paragraphs (3) and (7), but otherwise without prejudice to any other powers of the Court, in proceedings brought under this Part the Court—
(a)may by interim order suspend—
(i)the procedure leading to the award of a contract, the conclusion of a framework agreement, the establishment of a dynamic purchasing system or the determination of a design contest; and
(ii)the implementation of any decision or action taken by the contracting authority or concessionaire, as the case may be, in the course of following a procedure referred to in paragraph (i); and
(b)if satisfied that a decision or action taken by a contracting authority or concessionaire was in breach of the duty owed under regulation 47(1) or (2), may—
(i)order the setting aside of that decision or action;
(ii)order the contracting authority to amend any document; and
(iii)award damages to an economic operator which has suffered loss or damage as a consequence of the breach.
(2) In any interim proceedings under this Part the Court may decide not to grant an interim order when the negative consequences of such an order are likely to outweigh the benefits, having regard to the following considerations—
(a)that decisions taken by a contracting authority must be reviewed effectively and, in particular, as rapidly as possible;
(b)the probable consequences of an interim order for all interests likely to be harmed; and
(c)the public interest.
(3) Where the Court is satisfied that regulation 49(7)(a) applies but the second ground for ineffectiveness is not otherwise met, the Court must, without prejudice to the other powers of the Court, order—
(a)the payment by the contracting authority of a financial penalty; or
(b)where the contract in relation to which the breach occurred has been entered into, or the framework agreement in relation to which the breach occurred has been concluded, the shortening of the duration of the contract or framework agreement.
(4) In determining what order to make under paragraph (3) the Court must—
(a)ensure that the order is effective, proportionate and dissuasive; and
(b)have regard to all relevant factors including—
(i)the seriousness of the breach; and
(ii)the behaviour of the contracting authority.
(5) Where the Court makes an order under paragraph (3)(b) the Court must, without prejudice to the other powers of the Court, make such other order as the Court considers appropriate to address the consequences of the shortening of the duration of the contract or framework agreement on the rights and obligations of the parties to the contract or framework agreement.
(6) Before making an order under paragraph (5), the Court must have regard to any terms of the contract or framework agreement relating to the rights and obligations of the parties should the duration of the contract or framework agreement be shortened.
(7) Subject to paragraph (3) and regulation 49, in proceedings under this Part the Court does not have power to order any remedy other than an award of damages in respect of a breach of the duty owed under regulation 47(1) or (2) if the contract in relation to which the breach occurred has been entered into, or the framework agreement in relation to which the breach occurred has been concluded.
(8) Sections 21 and 42 of the Crown Proceedings Act 1947(1) do not apply in proceedings brought under this Part against the Crown.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Executive Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: