The restricted procedure

This section has no associated Executive Note

16.—(1) A contracting authority using the restricted procedure must comply with this regulation.

(2) The contracting authority must publicise its intention to seek offers in relation to the public contract by sending to the Official Journal as soon as possible after forming the intention a notice, in the form of the contract notice in Annex II to Commission Regulation (EC) No 1564/2005(1), inviting requests to be selected to tender and containing the information therein specified.

(3) Subject to paragraph (5), the date which the contracting authority fixes as the last date for the receipt by it of requests to be selected to tender must be specified in the contract notice and must be not less than 37 days from the date of the dispatch of the notice.

(4) Subject to any minimum time limit specified by this regulation, the contracting authority must take account of all the circumstances, in particular, the complexity of the contract and the time required for drawing up tenders when fixing time limits for the receipt of requests to be selected to tender and for receipt by it of tenders.

(5) Where the contracting authority has transmitted a contract notice by electronic means in accordance with the format and procedures referred to in paragraph (3) of Annex VIII to the Public Sector Directive, the time limit referred to in paragraph (3) may be reduced by 7 days.

(6) Where compliance with the minimum time limit of 37 days referred to in paragraph (3) is rendered impractical for reasons of urgency, the contracting authority may substitute for that time limit—

(a)a time limit of not less than 15 days from the date of dispatch of the contract notice; or

(b)where the contracting authority has transmitted the contract notice by electronic means in accordance with paragraph (5), a time limit of not less than 10 days from the date of dispatch of the contract notice.

(7) The contracting authority must make its evaluation in accordance with regulations 23 to 26 and may exclude an economic operator from those economic operators from which it will make the selection of economic operators to be invited to tender only if the economic operator—

(a)may be treated as ineligible to tender on a ground specified in regulation 23; or

(b)fails to satisfy the minimum standards required of economic operators by the contracting authority of—

(i)economic and financial standing; or

(ii)technical or professional ability.

(8) The contracting authority must make the selection of the economic operators to be invited to tender in accordance with regulations 23 to 26 and must award the contract in accordance with regulation 30.

(9) Where there are a sufficient number of economic operators suitable to be selected to be invited to tender, the contracting authority may limit the number of economic operators which it intends to invite to tender provided that the contract notice specifies—

(a)the objective and non-discriminatory criteria to be applied in order to limit the number of economic operators in accordance with this paragraph; and

(b)the minimum number of economic operators, which must be not less than 5, which the contracting authority intends to invite to tender and, where appropriate, the maximum number.

(10) The contracting authority must ensure that the number of economic operators invited to tender is—

(a)sufficient to ensure genuine competition; and

(b)at least equal to the minimum number specified by the contracting authority in accordance with paragraph (9)(b).

(11) Subject to paragraph (10)(a), where—

(a)the contracting authority carries out a selection in accordance with regulations 23 to 26; and

(b)the number of economic operators selected to be invited to tender is less than the minimum number specified by the contracting authority in the contract notice,

the contracting authority may continue the award procedure with the economic operators which have been selected, provided that any economic operator not selected or which did not request to participate is not included.

(12) The contracting authority may require an economic operator to satisfy minimum levels of—

(a)economic and financial standing; and/or

(b)technical or professional ability,

provided that those minimum levels are specified in the contract notice and are related to and proportionate to the subject matter of the contract.

(13) The contracting authority must send invitations in writing simultaneously to each economic operator selected to tender for the contract and the invitation must—

(a)be accompanied by the contract documents;

(b)specify the internet address which offers unrestricted and full direct access by electronic means to the contract documents; or

(c)where the contract documents are held by an entity other than the contracting authority, specify the address to which requests for contract documents should be sent including any final date for making such requests and the amount and any method of payment of any fee which may be charged for supplying that information.

(14) Where the contract documents are held by an entity other than the contracting authority, the contracting authority must ensure that the contract documents are sent to economic operators by the most rapid means of communication possible.

(15) The contracting authority must include the following information in the invitation—

(a)the final date for the receipt by it of tenders, the address to which they must be sent and the language or languages in which they must be drawn up;

(b)a reference to the contract notice published in accordance with paragraph (2);

(c)an indication of the information to be included with the tender which the contracting authority may require to be provided in accordance with regulations 24 to 26; and

(d)the relative weighting of criteria for the award of the contract or, where appropriate, the descending order of importance for such criteria, if this information was not specified in the contract notice published in accordance with paragraph (2).

(16) Subject to paragraphs (18) and (19), the date which the contracting authority fixes as the last date for the receipt by it of tenders and which must be specified in the invitation to tender in accordance with paragraph (15)(a), must be not less than 40 days from the date of the dispatch of the invitation.

(17) Where compliance with the minimum time limit of 40 days referred to in paragraph (16) is rendered impractical for reasons of urgency, the contracting authority may substitute for that time limit, a time limit of not less than 10 days from the date of dispatch of the invitation.

(18) Where—

(a)the contracting authority has published a prior information notice in accordance with regulation 11;

(b)the prior information notice contained as much of the information referred to in the form of a contract notice in Annex II to Commission Regulation (EC) No 1564/2005 as was available at the time of publication; and

(c)the prior information notice was sent to the Official Journal at least 52 days and no more than 12 months before the date on which the contract notice provided for in paragraph (2) is dispatched,

the contracting authority may substitute for the period of not less than 40 days in paragraph (16), a period of generally not less than 36 days and in any event not less than 22 days.

(19) The contracting authority may reduce the time limits for the receipt by it of tenders referred to in paragraphs (16) and (18) by 5 days provided that—

(a)the contracting authority offers unrestricted and full direct access by electronic means to the contract documents from the date of publication of the contract notice; and

(b)the contract notice specifies the internet address at which the documents referred to in sub-paragraph (a) are available.

(20) The contracting authority or entity referred to in paragraph (13)(c) must supply such further information relating to the contract documents as may be reasonably requested by an economic operator provided that the request for such information is received in sufficient time to enable the contracting authority to supply it not less than 4 days before the date specified in the invitation to tender as the final date for the receipt by it of tenders.

(21) The contracting authority must extend the time limit for receipt by it of tenders in order that all the information necessary for the preparation of a tender is available to all economic operators where—

(a)an economic operator requests the contract documents in sufficient time to allow the contracting authority to respond in accordance with paragraph (20) and, for whatever reason, the contract documents or further information are not supplied in accordance with that paragraph; or

(b)it is necessary that the economic operators be given the opportunity to inspect the site or premises or documents relating to the contract documents.

(22) The contracting authority may combine the reductions in the periods of time referred to in paragraphs (5) and (19).

(23) The contracting authority must by notice in writing as soon as reasonably practicably after sending the invitations referred to in paragraph (13), inform any candidates that have not been selected to be invited to tender that they have been unsuccessful.

(1)

The annex to Commission Regulation (EC) No 1564/2005 was amended by Commission Regulation (EC) 1150/2009, OJ L 313, 29.11.2009, p.3.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Executive Note

Executive Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources