6. For the purposes of section 113, an undertaker, in addition to giving notice in accordance with regulation 7, shall, for each of the categories of work specified in column (1) of the table below, give a period of advance notice in relation to that category not less than that shown in column (2) of that table.
Category of works | Notice period |
---|---|
(1) | (2) |
Major works. | 3 months. |
Standard works in a traffic sensitive road. | 1 month. |
Minor works involving breaking up the road in a traffic sensitive road. | 1 month. |
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Executive Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: