18. Every consent shall include conditions to the effect that—
(a)work in relation to the relevant project shall be commenced within such period (not being more than 5 years beginning with the date consent is granted) as is specified in the consent; and
(b)no work shall be carried out in relation to the project after the expiration of such period (not being more than 10 years beginning with the date consent is granted) as is specified in the consent.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: