5. The final payment payable under a relevant construction contract, namely the payment of an amount equal to the difference (if any) between–
(a)the contract price; and
(b)the aggregate of any instalment or stage or periodic payments which have become due under the contract,
shall become due on the expiry of–
(a)30 days following completion of the work; or
(b)the making of a claim by the payee,
whichever is the later.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: