3. Where–
(a)the parties to a construction contract are unable to reach agreement for the purposes mentioned respectively in Articles 8, 10 and 12 of the 1997 Order; or
(b)a construction contract does not make provision as required by Article 9 of the 1997 Order,
the relevant provisions in Part II of the Schedule shall apply.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: