SCHEDULE 1UNITS OF COMPETENCE FOR TRAINED OPERATIVES

UNIT 1Location and avoidance of underground apparatus.
UNIT 2Signing, lighting and guarding.
UNIT 3Excavation in the highway.
UNIT 4Reinstatement and compaction of backfill materials.
UNIT 5Reinstatement of sub-base and roadbase in non-bituminous materials.
UNIT 6Reinstatement in cold-lay bituminous materials.
UNIT 7Reinstatement in hot-lay bituminous materials.
UNIT 8Reinstatement of concrete slabs.
UNIT 9Reinstatement of modular surfaces and concrete footways.

SCHEDULE 2QUALIFICATIONS FOR TRAINED OPERATIVES

Type of WorkUnits of Competence Required
(1)(2)

1.  Excavation in the highway.

Units 1, 2 and 3.

2.  Excavation, backfilling and reinstatement of construction layers with a cold-lay bituminous surface.

Units 1, 2, 3, 4, 5 and 6.

3.  Reinstatement of construction layers in hot-lay and cold-lay bituminous materials.

Units 1, 2, 6 and 7.

4.  Reinstatement of concrete slabs.

Units 1, 2 and 8.

5.  Reinstatement of modular surfaces and concrete footways.

Units 1, 2 and 9.

SCHEDULE 3UNITS OF COMPETENCE FOR SUPERVISORS

UNIT 1Location and avoidance of underground apparatus.
UNIT 10Monitoring signing, lighting and guarding.
UNIT 11Monitoring excavation in the highway.
UNIT 12Monitoring reinstatement and compaction of backfill materials.
UNIT 13Monitoring reinstatement of sub-base and roadbase in non-bituminous materials.
UNIT 14Monitoring reinstatement in bituminous materials.
UNIT 15Monitoring reinstatement of concrete slabs.
UNIT 16Monitoring reinstatement of modular surfaces and concrete footways.

SCHEDULE 4QUALIFICATIONS FOR SUPERVISORS

Type of Supervisory WorkUnits of Competence Required
(1)(2)

1.  Monitoring excavation in the highway.

Units 1, 10 and 11.

2.  Monitoring excavation, backfilling and reinstatement of construction layers with bituminous materials.

Units 1, 10, 11, 12, 13 and 14.

3.  Monitoring reinstatement of construction layers in bituminous materials.

Units 1, 10 and 14.

4.  Monitoring reinstatement of concrete slabs.

Units 1, 10 and 15.

5.  Monitoring reinstatement of modular surfaces and concrete footways.

Units 1, 10 and 16.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources