Section 36 - Inspection reports: compliance
This section requires reservoir managers to comply with the directions in an inspection report or any pre-commencement safety recommendation. Subsection (2) permits the reservoir manager to commission another appropriate panel engineer (who is eligible to be an inspecting engineer) to supervise the taking of measures directed or recommended. The other appropriate panel engineer if commissioned is referred to in the Act as the “other qualified engineer”. When measures or recommendations have been completed subsection (3) requires the inspecting engineer (or other qualified engineer) to issue an interim inspection compliance certificate. Subsection (4) specifies the detail to be included in an interim inspection compliance certificate.
When the inspecting engineer (or other qualified engineer) is satisfied that all of the measures (directed or recommended) have been completed, the engineer is required by subsection (5) to issue the reservoir manager with an inspection compliance certificate within 28 days. Subsection (6) requires the engineer giving an inspection compliance certificate to accept any interim inspection compliance certificates or any pre-commencement inspection report certificates given by another engineer. Subsection (7) lists the detail that must be specified in the inspection compliance certificate. Subsection (8) requires the engineer to give a copy of the certificates under this section to the Department.