Search Legislation

The Hornsea Four Offshore Wind Farm (Correction) Order 2024

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Article 2

SCHEDULECorrections

Column (1)

Where the correction is made

Column (2)

How the correction is made

Column (3)

Text substituted, inserted or omitted

Preamble, para 1For “an” substitute“and”
Article 2(1), the 2016 RegulationsOmit “:” insert“;”
Article 2(1), energy balancing infrastructureAfter “to” insert“or from”
Article 2(1), highwayAfter “(a)” insert“;”
Article 2(1), maintainAfter “not including” insert“the”
After “onshore project substation” insert“,”
Article 2(1), offshore transformer substationAfter “storage, workshop” insert“,”
Article 2(3)(a)For “(requirement)” substitute“(requirements)”
Article 5(4)For “(1)” substitute“(2)”
After “paragraph (2) or (3)” insert“,”
Article 5(7)For “(1)” substitute“(2)”
Article 5(7)(c)For “(1)” substitute“(2)”
Article 7(b)(i)After “noise during”Omit “the”
Article 9(1)(b)For “(temporary closure of streets and public rights of way)” substitute“(temporary closure and restriction of streets and public rights of way)”
Article 10(4)For “closure” substitute“close”
For “column (10)” substitute“column (1)”
Article 11(1)(d)After “Part 3” insert“of”
Article 15(3)After “any watercourse or” insert“any”
After “public sewer” insert“or”
Article 16(4)For “paragraphs(5)” substitute“paragraph (5)”
Article 21(8)After “article 43” insert“(crown rights)”
Article 22(1)For “article 18” substitute“this Order”
Article 25(1)article 18 (compulsory acquisition of land etc.)Omit “etc”
Article 26(5)After paragraph (4) insert

(5) In Schedule 2A (counter-notice requiring purchase of land not in notice to treat)(c)—

(a)for paragraphs 1(2) and 14(2) substitute—

(2) But see article 25(3) (acquisition of subsoil only) of the Hornsea Four Offshore Wind Farm Order 2023, which excludes the acquisition of subsoil only from this Schedule.; and

(b)at the end insert—

PART 4INTERPRETATION

30.  .In this Schedule, references to entering on and taking possession of land do not include doing so under article 16 (protective work to buildings), article 28 (temporary use of land for carrying out the authorised project) or article 29 (temporary use of land for maintaining the authorised project) of the Hornsea Four Offshore Wind Farm Order 2023.

Article 27(5)For “(5)” substitute“(4)”
Article 37(1)After “preparation works” insert“,”
Article 46For “(modifications to the Dogger Bank Cryke Beck Offshore Wind Farm Order 2015)” substitute“(modifications to and amendments of the Dogger Bank Cryke Beck Offshore Wind Farm Order 2015)”
Article 47(3)(a)For “in the case of the secretary of” substitute“in the case of the secretary or”
Schedule 1, Part 1, paragraph 1, Work No. 5For “-” substitute“—”
Schedule 1, Part 1, paragraph 1, Work No. 7After “Work No. 7—”Insert a space
Schedule 1, Part 1, paragraph 2, Point ID 73After “56.253” insert“””
Schedule 1, Part 3, requirement 7(1)(h)For “below, ground” substitute“below ground”
Schedule 1, Part 3, requirement 22(1)After “Work Nos. 7(a), (b) and (c)” insert“must not”
Schedule 6, column (2) (four references)For “ecological measures the right to pass” substitute“ecological measures, the right to pass”
Schedule 7, paragraph 3(2)For “land,” substitute“land;”
Schedule 7, paragraph 9For “article 29(3)” substitute“article 26(3)”
Schedule 7, paragraph 10 (paragraph 1(1))For “serve” substitute“serves”
Schedule 7, paragraph 10 (paragraph 1(1))For “(application of the Compulsory Purchase (Vesting Declarations) Act 1981)” substitute“(application of the 1981 Act)”
Schedule 9, Part 1, paragraph 1For “Part 10” substitute“Part 9”
Schedule 9, Part 1, paragraph 2For “Part 3 or Part 10” insert“Part 3A or 3B, Part 7 or Part 9”
Schedule 9, Part 1, paragraph 7(4)For “paragraph5”Replace with “paragraph 5”
Schedule 9, Part 1, paragraph 8(4)For “sub-paragraph (2)” substitute“sub-paragraph (3)”
Schedule 9, Part 2, paragraph 2For “Chapter 1 of Part 2 of the 2003 Act(;”Omit “(“
Schedule 9, Part 3A, paragraph 3For “(apparatus of National Grid in streets subject to temporary stopping up)” substitute“(apparatus of National Grid in streets subject to temporary closure)”
Schedule 9, Part 3A, paragraph 9(4)For “(2)(2)” substitute“(2)”
Schedule 9, Part 3B, paragraph 23(3) and (5) (three occurrences)Omit“7”
Schedule 9, Part 3B, paragraph 24(2) (two occurrences)Omit“8”
Schedule 9, Part 3B, paragraph 25(2), (3), (5), (6) and (10) (five occurrences)Omit“9”
Schedule 9, Part 3B, paragraph 26(2), (3), (4) and (5) (four occurrences)Omit“10”
Schedule 9, Part 4, paragraph 2Within the definition of specified work, for “(maintenance of authorised development)” substitute“(power to maintain the authorised project)”
Schedule 9, Part 4, paragraph 4(1)(a)For “(development consent granted by the Order)” substitute“(development consent etc. granted by this Order)”
Schedule 9, Part 4, paragraph 4(1)Omit blank line between (h) and (i)
Schedule 9, Part 4, paragraph 4(1)(r)After “any powers” omit“under”
Schedule 9, Part 4, paragraph 4(3)For “(power to override easements and other rights)” substitute“(statutory authority to override easements and other rights)”
Schedule 9, Part 4, paragraph 12(5)For “sub-paragraph” substitute“sub-paragraphs in paragraph 6”
Schedule 9, Part 4, paragraph 22For “(certification of plans, etc.)” substitute“(certification of plans and documents, etc.)”
Schedule 9, Part 5, paragraph 1(2)(d)After “resources” omit“.”
Schedule 9, Part 6, paragraph 2(e)After “other means whatsoever” insert“of”
Schedule 9, Part 7, paragraph 3For “£50,000,000” substitute“£50,000,000.00”
Schedule 9, Part 7, paragraph 4(2)(b)For “(temporary restrictions of streets and public rights of way)” substitute“(temporary closure and restriction of streets and public rights of way)”
Schedule 9, Part 7, paragraph 4(2)(c)For “stopping up” substitute“closure”
Schedule 9, Part 7, paragraph 4(2)(i)After “minerals)” insert“;”
Schedule 9, Part 7, paragraph 4(2)(j)After “rights” insert“etc.”
Schedule 9, Part 7, paragraph 4(2)(o)After “carrying out” insert“the”
Schedule 9, Part 7, paragraph 4(2)(p)After “land for maintaining” insert“the”
For “development” substitute“project”
Schedule 9, Part 7, paragraph 4(2)(q)For “31” substitute“30”
Schedule 9, Part 7, paragraph 9(7)For “works.” substitute“works,”
Schedule 9, Part 9, paragraph 4(1)Omit“the relevant”
Schedule 9, Part 9, paragraph 8(1)(a)For “paragraph 7(3)” substitute“paragraph 5(3)”
Schedule 9, Part 9, paragraph 9(5)For “request” substitute“requested”
For “The undertaker is only liable under sub-paragraph (1) for claim” substitute“The undertaker is only liable under sub-paragraph (1) for claims”
Schedule 9, Part 10, paragraph 2(a)Replace “the no licence is granted”With “no licence is granted”
Schedule 13, paragraph 1 (paragraph 2)For “£50,000,000” insert“£50,000,000.00”
Schedule 13, paragraph 1 (paragraph 2)At the end of the definition ground subsistence event omit“and”
Schedule 13, paragraph 1 (paragraph 3(2)(m))For “(temporary use of land for maintaining authorised development)” substitute“(temporary use of land for maintaining authorised project)”
Schedule 13, paragraph 1 (paragraphs 8 and 10)For “Part 2” insert“Part 3”
Schedule 13, paragraph 1 (paragraph 13(2))Omit “,”
Schedule 13, paragraph 1 (paragraph 13(5))After “under sub-paragraph (1) for” insert“any”
Schedule 14, paragraph 3(4)After “serving its statements” insert“under”
Schedule 15, Part 3, examination referenceFor “REP7-058” substitute“Post-examination F2.7”
Schedule 15, Part 3, the outline marine monitoring plan, versionFor “7” substitute“3”
Schedule 15, Part 3, the outline marine monitoring plan, dateFor “10 August 2022” substitute“11 May 2023”
Schedule 16, Part 1, paragraph 2(c)For “of the KCIMP, the GCIMP and the RCIMP” substitute“of the KCIMP and GCIMP”
Schedule 16, Part 2, paragraph 6After “include any finding” insert“(if relevant)”
Schedule 16, Part 3, paragraph 10(a)(v)(cc)After “programmes” insert“;”

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources