There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Reservoirs Act 1975 (Capacity, Registration, Prescribed Forms, etc.) (England) Regulations 2013. Those changes will be listed when you open the content using the Table of Contents below. Any changes that have already been made by the team appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the affected provisions when you open the content using the Table of Contents below.
13.Prescribed information under section 21(1) to be provided by undertakers when intending to construct or bring back into use a large raised reservoir
Information to be given in English registers of large raised reservoirs
4.A summary of the contents of all certificates or reports...
5.The following information if it is revealed by any certificate,...
6.Name and business address of the supervising engineer or, if...
8.Particulars of any appointment made by the Agency under section...
9.Particulars of any appointment made by the Agency under section...
10.Whether the large raised reservoir is designated as high-risk.
Prescribed matters relating to high-risk reservoirs of which an undertaker is to keep a record
Information to be given in a notice under section 21(1) of the 1975 Act
3.National grid reference of approximate centre of the reservoir.
4.Whether the undertakers intend— (a) to construct a new large...
5.The date when it is intended that construction will commence...
6.Name and address of the construction engineer or, in the...
7.The following information about the reservoir as it will be...
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: