  1. Introductory Text

  2. PART 1

    1. 1.Citation and commencement

    2. 2.Interpretation

    3. 3.Application of the 1991 Act

  3. PART 2

    1. Principal powers

      1. 4.Power to construct and maintain works

      2. 5.Power to deviate

    2. Streets

      1. 6.Power to alter layout, etc., of streets

      2. 7.Power to execute street works

      3. 8.Stopping up of streets

      4. 9.Temporary stopping up and diversion of streets

      5. 10.Access to works

      6. 11.Construction and maintenance of altered or diverted streets

      7. 12.Agreements with street authorities

    3. Supplemental powers

      1. 13.Discharge of water

      2. 14.Protective works to buildings

      3. 15.Planning permission: supplementary matters

      4. 16.Power to survey and investigate land, etc.

  4. PART 3

    1. Powers of acquisition

      1. 17.Power to acquire land

      2. 18.Application of Part 1 of the Compulsory Purchase Act 1965

      3. 19.Application of the Compulsory Purchase (Vesting Declarations) Act 1981

      4. 20.Power to acquire new rights

      5. 21.Powers to acquire subsoil only

      6. 22.Power to acquire land limited to subsoil lying more than 4.5 metres beneath surface

      7. 23.Rights under or over streets

    2. Temporary possession of land

      1. 24.Temporary use of land for construction of works

      2. 25.Temporary use of land for maintenance of works

    3. Compensation

      1. 26.Disregard of certain interests and improvements

      2. 27.Set-off for enhancement in value of retained land

    4. Supplementary

      1. 28.Acquisition of part of certain properties

      2. 29.Extinction or suspension of private rights of way

      3. 30.Time limit for exercise of powers of acquisition

  5. PART 4

    1. 31.Statutory undertakers, etc.

    2. 32.For protection of Network Rail

    3. 33.For protection of specified undertakers

  6. PART 5

    1. 34.Traffic regulation

    2. 35.Street traders

    3. 36.Obstruction of construction of authorised works

    4. 37.Disclosure of confidential information

    5. 38.Defence to proceedings in respect of statutory nuisance

    6. 39.Certification of plans, etc.

    7. 40.Service of notices

    8. 41.No double recovery

    9. 42.Arbitration

  7. Signature

  8. SCHEDULES

    1. SCHEDULE 1

      SCHEDULED WORKS

    2. SCHEDULE 2

      STREETS SUBJECT TO STREET WORKS

    3. SCHEDULE 3

      STREET TO BE STOPPED UP

    4. SCHEDULE 4

      STREETS TO BE TEMPORARILY STOPPED UP

    5. SCHEDULE 5

      MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS

      1. Compensation enactments

        1. 1.The enactments for the time being in force with respect...

        2. 2.(1) Without prejudice to the generality of paragraph 1, the...

      2. Application of the 1965 Act

        1. 3.(1) The 1965 Act shall have effect with the modifications...

        2. 4.For section 7 of the 1965 Act (measure of compensation)...

        3. 5.For section 8 of the 1965 Act (provisions as to...

        4. 6.The following provisions of the 1965 Act (which state the...

        5. 7.Section 11 of the 1965 Act (powers of entry) shall...

        6. 8.Section 20 of the 1965 Act (protection for interests of...

        7. 9.Section 22 of the 1965 Act (protection of acquiring authority’s...

    6. SCHEDULE 6

      LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

    7. SCHEDULE 7

      LAND OF WHICH ONLY SUBSOIL MORE THAN 4.5 METRES BENEATH SURFACE MAY BE ACQUIRED

    8. SCHEDULE 8

      PROVISIONS RELATING TO STATUTORY UNDERTAKERS, ETC.

      1. Apparatus of statutory undertakers, etc., on land acquired

        1. 1.(1) Subject to the following provisions of this paragraph, sections...

      2. Apparatus of statutory undertakers, etc., in stopped up streets

        1. 2.(1) Where a street is stopped up under article 8...

    9. SCHEDULE 9

      FOR PROTECTION OF NETWORK RAIL

      1. 1.The following provisions of this Schedule shall have effect, unless...

      2. 2.In this Schedule— “construction” includes execution, placing, alteration and reconstruction...

      3. 3.(1) Where under this Schedule Network Rail is required to...

      4. 4.(1) The Company shall not exercise the powers conferred by...

      5. 5.(1) The Company shall before commencing construction of any specified...

      6. 6.(1) Any specified work and any protective works to be...

      7. 7.The Company shall— (a) at all times afford reasonable facilities...

      8. 8.Network Rail shall at all times afford reasonable facilities to...

      9. 9.(1) If any permanent or temporary alterations or additions to...

      10. 10.The Company shall repay to Network Rail all reasonable fees,...

      11. 11.If at any time after the completion of a specified...

      12. 12.Any additional expenses which Network Rail may reasonably incur in...

      13. 13.(1) The Company shall pay to Network Rail all reasonable...

      14. 14.Network Rail shall, on receipt of a request from the...

      15. 15.In the assessment of any sums payable to Network Rail...

      16. 16.The Company and Network Rail may, subject in the case...

      17. 17.The Company shall no later than 28 days from the...

    10. SCHEDULE 10

      FOR PROTECTION OF SPECIFIED UNDERTAKERS

      1. Interpretation

        1. 1.In this Schedule— “apparatus” means— in the case of a...

      2. Application of Schedule 8

        1. 2.Paragraphs 1(1) and 2 of Schedule 8 (provisions relating to...

      3. Apparatus in stopped up streets

        1. 3.Where any street is stopped up under article 8 (stopping...

        2. 4.The Company shall give not less than 28 days’ notice...

      4. On-street apparatus

        1. 5.This Schedule shall not apply to anything done or proposed...

      5. Acquisition of land

        1. 6.The Company shall not acquire any apparatus from a specified...

        2. 7.The Company may in exercise of the powers conferred by...

      6. Removal of apparatus

        1. 8.Paragraphs 9 to 12 apply where— (a) the Company requires...

        2. 9.The Company shall, if it is practicable to do so,...

        3. 10.The obligation imposed upon the specified undertaker by paragraph 9...

        4. 11.Any alternative apparatus to be constructed by the specified undertaker...

        5. 12.The specified undertaker shall, after the manner of construction and...

      7. Removal of apparatus and construction of alternative apparatus by the Company

        1. 13.Paragraphs 14 to 16 apply to so much of the...

        2. 14.If the Company gives notice in writing to the specified...

        3. 15.In carrying out any work under paragraph 14 the Company...

        4. 16.Nothing in paragraph 14 shall authorise the Company to carry...

      8. Facilities and rights for alternative apparatus

        1. 17.Where, in accordance with the provisions of this Schedule, the...

        2. 18.In determining the terms and conditions mentioned in paragraph 17...

        3. 19.If the facilities and rights to be afforded by the...

      9. Retained apparatus: protection and plan approval

        1. 20.Not less than 56 days before commencing to construct or...

        2. 21.In relation to a work which is a specified work...

        3. 22.The Company shall not commence the construction or renewal of...

        4. 23.Any approval of the specified undertaker required under paragraph 22—...

        5. 24.In relation to a work to which paragraph 21 applies,...

        6. 25.A specified work shall be constructed (and in the case...

        7. 26.If within 42 days after the submission to it of...

        8. 27.Nothing in paragraph 20 or 26 shall preclude the Company...

        9. 28.The Company shall not be required to comply with paragraph...

        10. 29.Nothing in paragraph 28 shall entitle the Company to carry...

      10. Co-operation

        1. 30.Where in consequence of the proposed construction of any of...

      11. Access

        1. 31.If in consequence of the exercise of the powers conferred...

      12. Expenses

        1. 32.Subject to the provisions of the following paragraphs of this...

        2. 33.There shall be deducted from any sum payable under paragraph...

        3. 34.If in pursuance of the provisions of this Schedule—

        4. 35.For the purposes of paragraph 34— (a) an extension of...

        5. 36.An amount which apart from this paragraph would be payable...

        6. 37.In any case where work is carried out by the...

      13. Indemnity

        1. 38.If, by reason or in consequence of the construction, maintenance...

        2. 39.Nothing in paragraph 38 shall impose any liability on the...

        3. 40.The specified undertaker shall give to the Company reasonable notice...

      14. Exercise of safeguarding and survey powers

        1. 41.The Company shall, so far as is reasonably practicable, so...

        2. 42.The Company shall not, in the exercise of the powers...

      15. Arbitration

        1. 43.Any difference arising between the Company and a specified undertaker...

      16. Notices

        1. 44.Any notice in writing to be given by the Company...

    11. SCHEDULE 11

      TRAFFIC REGULATION

  9. Explanatory Note

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources