Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

  1. Introductory Text

  2. PART I PRELIMINARY

    1. 1.Citation and commencement

    2. 2.Interpretation

  3. PART II APPLICATION

    1. 3.Pressure equipment and assemblies

    2. 4.Excluded pressure equipment and assemblies

    3. 5.Pressure equipment and assemblies placed on the market before 29th November 1999

    4. 6.Exclusion until 30th May 2002 of pressure equipment and assemblies complying with provisions in force on 28th November 1999

  4. PART III GENERAL REQUIREMENTS

    1. 7.General duty relating to the placing on the market or putting into service of pressure equipment

    2. 8.General duty relating to the placing on the market or putting into service of assemblies

    3. 9.Requirement for pressure equipment or assemblies to comply with sound engineering practice

    4. 10.General duty relating to the supply of pressure equipment and assemblies

    5. 11.Exceptions to placing on the market or supply in respect of certain pressure equipment and assemblies

    6. 12.Classification of pressure equipment

    7. 13.Conformity assessment procedures for pressure equipment

    8. 14.Conformity assessment procedure for assemblies

    9. 15.Exclusion for pressure equipment and assemblies for use for experimentation

    10. 16.CE marking

    11. 17.European approval for materials

    12. 18.Notified bodies

    13. 19.Recognised third-party organisations

    14. 20.Notified bodies and recognised third-party organisations appointed by the Secretary of State

    15. 21.Fees

    16. 22.User inspectorates

    17. 23.Conditions for pressure equipment and assemblies being taken to conform with the provisions of these Regulations

  5. PART IV ENFORCEMENT

    1. 24.Application of Schedule 8

    2. 25.Offences

    3. 26.Penalties

    4. 27.Defence of due diligence

    5. 28.Liability of persons other than the principal offender

    6. 29.Consequential amendments

  6. Signature

    1. SCHEDULE 1

      EXCLUDED PRESSURE EQUIPMENT AND ASSEMBLIES

      1. 1.Pipelines comprising piping or a system of piping designed for...

      2. 2.Networks for the supply, distribution and discharge of water and...

      3. 3.Equipment covered by Directive 87/404/EEC on simple pressure vessels;

      4. 4.Equipment covered by Council Directive 75/324/EEC of 20 May 1975...

      5. 5.Equipment intended for the functioning of vehicles defined by the...

      6. 6.Equipment classified as no higher than category I under Article...

      7. 7.Equipment covered by Article 346(1)(b) of the Treaty on the...

      8. 8.Items specifically designed for nuclear use, failure of which may...

      9. 9.Well-control equipment used in the petroleum, gas or geothermal exploration...

      10. 10.Equipment comprising casings or machinery where the dimensioning, choice of...

      11. 11.Blast furnaces including the furnace cooling system, hot-blast recuperators, dust...

      12. 12.Enclosures for high-voltage electrical equipment such as switchgear, control gear,...

      13. 13.Pressurised pipes for the containment of transmission systems, including for...

      14. 14.Ships, rockets, aircraft and mobile off-shore units, as well as...

      15. 15.Pressure equipment consisting of a flexible casing, including for example...

      16. 16.Exhaust and inlet silencers;

      17. 17.Bottles or cans for carbonated drinks for final consumption;

      18. 18.Vessels designed for the transport and distribution of drinks having...

      19. 19.Equipment covered by the ADR, the RID, the IMDG and...

      20. 20.Radiators and pipes in warm water heating systems;

      21. 21.Vessels designed to contain liquids with a gas pressure above...

    2. SCHEDULE 2

      (Annex I to the Pressure Equipment Directive)

      1. PRELIMINARY OBSERVATIONS

        1. 1.The obligations arising from the essential requirements listed in this...

        2. 2.The essential requirements laid down in the Directive are compulsory....

        3. 3.The manufacturer is under an obligation to analyse the hazards...

        4. 4.The essential requirements are to be interpreted and applied in...

        5. 1.GENERAL

        6. 1.1.Pressure equipment must be designed, manufactured and checked, and if...

        7. 1.2.In choosing the most appropriate solutions, the manufacturer must apply...

        8. 1.3.Where the potential for misuse is known or can be...

        9. 2.DESIGN

        10. 2.1.General The pressure equipment must be properly designed taking all...

        11. 2.2.Design for adequate strength (2.2.1) The pressure equipment must be...

        12. 2.3.Provisions to ensure safe handling and operation The method of...

        13. 2.4.Means of examination (a) Pressure equipment must be designed and...

        14. 2.5.Means of draining and venting Adequate means must be provided...

        15. 2.6.Corrosion or other chemical attack Where necessary, adequate allowance or...

        16. 2.7.Wear Where severe conditions of erosion or abrasion may arise,...

        17. 2.8.Assemblies Assemblies must be so designed that: the components to...

        18. 2.9.Provisions for filling and discharge Where appropriate, the pressure equipment...

        19. 2.10.Protection against exceeding the allowable limits of pressure equipment Where,...

        20. 2.11.Safety accessories (2.11.1) Safety accessories must: be so designed and...

        21. 2.12.External fire Where necessary, pressure equipment must be so designed...

        22. 3.MANUFACTURING

        23. 3.1.Manufacturing procedures The manufacturer must ensure the competent execution of...

        24. 3.2.Final assessment Pressure equipment must be subjected to final assessment...

        25. 3.3.Marking and labelling In addition to the CE marking referred...

        26. 3.4.Operating instructions (a) When pressure equipment is placed on the...

        27. 4.MATERIALS

        28. 4.1.Materials for pressurised parts must: (a) have appropriate properties for...

        29. 4.2.(a) The pressure equipment manufacturer must define in an appropriate...

        30. 4.3.The equipment manufacturer must take appropriate measures to ensure that...

      2. SPECIFIC PRESSURE EQUIPMENT REQUIREMENTS

        1. 5.FIRED OR OTHERWISE HEATED PRESSURE EQUIPMENT WITH A RISK OF OVERHEATING AS REFERRED TO IN ARTICLE 3(1)

        2. 6.PIPING AS REFERRED TO IN ARTICLE 3, SECTION 1.3

        3. 7.SPECIFIC QUANTITATIVE REQUIREMENTS FOR CERTAIN PRESSURE EQUIPMENT

        4. 7.1.Allowable stresses (7.1.1) Symbols Re/t, yield limit, indicates the value...

        5. 7.2.Joint coefficients For welded joints, the joint coefficient must not...

        6. 7.3.Pressure limiting devices, particularly for pressure vessels The momentary pressure...

        7. 7.4.Hydrostatic test pressure For pressure vessels, the hydrostatic test pressure...

        8. 7.5.Material characteristics Unless other values are required in accordance with...

    3. SCHEDULE 3

      (Annex II to the Pressure Equipment Directive)

      1. 1.The references in the tables to categories of modules are...

      2. 2.The safety accessories defined in Article 1, Section 2.1.3, and...

      3. 3.The pressure accessories defined in Article 1, Section 2.1.4, and...

      4. 4.The demarcation lines in the following conformity assessment tables indicate...

    4. SCHEDULE 4

      (Annex III to the Pressure Equipment Directive)

      1. 1.Module A (internal production control)

      2. 2.The manufacturer must draw up the technical documentation described in...

      3. 3.The technical documentation must enable an assessment to be made...

      4. 2.The manufacturer, or his authorised representative established within the European...

      5. 5.The manufacturer must take all measures necessary to ensure that...

      6. Module A1 (internal manufacturing checks with monitoring of the final assess ment)

      7. Final assessment must be performed by the manufacturer and monitored...

      8. During such visits, the notified body must: establish that the...

      9. Should one or more of the items of pressure equipment...

      10. On the responsibility of the notified body, the manufacturer must...

      11. 1.Module B (EC type-examination)

      12. 2.The application for EC type-examination must be lodged by the...

      13. 3.The technical documentation must enable an assessment to be made...

      14. 4.The notified body must: (4.1) examine the technical documentation, verify...

      15. 5.Where the type satisfies the provisions of the Directive which...

      16. 6.The applicant must inform the notified body that holds the...

      17. 7.Each notified body must communicate to the Member States the...

      18. 8.The other notified bodies may receive copies of the EC...

      19. 9.The manufacturer, or his authorised representative established within the European...

      20. 1.Module B1 (EC design-examination)

      21. 2.The manufacturer, or his authorised representative established within the European...

      22. 3.The technical documentation must enable an assessment to be made...

      23. 4.The notified body must: (4.1) examine the technical documentation and...

      24. 5.Where the design meets the provisions of the Directive which...

      25. 6.The applicant must inform the notified body that holds the...

      26. 7.Each notified body must communicate to the Member States the...

      27. 8.The other notified bodies may on request obtain the relevant...

      28. 9.The manufacturer, or his authorised representative established within the European...

      29. 1.Module C1 (conformity to type)

      30. 2.The manufacturer must take all measures necessary to ensure that...

      31. 3.The manufacturer, or his authorised representative established within the European...

      32. 4.Final assessment must be subject to monitoring in the form...

      33. 1.Module D (production quality assurance)

      34. 2.The manufacturer must operate an approved quality system for production,...

      35. 3.Quality system (3.1) The manufacturer must lodge an application for...

      36. 4.Surveillance under the responsibility of the notified body

      37. 5.The manufacturer must, for a period of ten years after...

      38. 6.Each notified body must communicate to the Member States the...

      39. 1.Module D1 (production quality assurance)

      40. 2.The manufacturer must draw up the technical documentation described below....

      41. 3.The manufacturer must operate an approved quality system for production,...

      42. 4.Quality system (4.1) The manufacturer must lodge an application for...

      43. 5.Surveillance under the responsibility of the notified body

      44. 6.The manufacturer must, for a period of ten years after...

      45. 7.Each notified body must communicate to the Member States the...

      46. 1.Module E (product quality assurance)

      47. 2.The manufacturer must operate an approved quality system for the...

      48. 3.Quality system (3.1) The manufacturer must lodge an application for...

      49. 4.Surveillance under the responsibility of the notified body

      50. 5.The manufacturer must, for a period of ten years after...

      51. 6.Each notified body must communicate to the Member States the...

      52. 1.Module E1 (product quality assurance)

      53. 2.The manufacturer must draw up the technical documentation described below....

      54. 3.The manufacturer must operate an approved quality system for the...

      55. 4.Quality system (4.1) The manufacturer must lodge an application for...

      56. 5.Surveillance under the responsibility of the notified body

      57. 6.The manufacturer must, for a period of ten years after...

      58. 7.Each notified body must communicate to the Member States the...

      59. 1.Module F (product verification)

      60. 2.The manufacturer must take all measures necessary to ensure that...

      61. 3.The notified body must perform the appropriate examinations and tests...

      62. 4.Verification by examination and testing of each item of pressure...

      63. 1.Module G (EC unit verification)

      64. 2.The manufacturer must apply to a notified body of his...

      65. 3.The technical documentation must enable the conformity of the pressure...

      66. 4.The notified body must examine the design and construction of...

      67. 1.Module H (full quality assurance)

      68. 2.The manufacturer must implement an approved quality system for design,...

      69. 3.Quality system (3.1) The manufacturer must lodge an application for...

      70. 4.Surveillance under the responsibility of the notified body

      71. 5.The manufacturer must, for a period of ten years after...

      72. 6.Each notified body must communicate to the Member States the...

      73. 1.Module H1 (full quality assurance with design examination and special surveillance of the final assessment)

      74. 2.Final assessment as referred to in section 3.2 of Annex...

    5. SCHEDULE 5

      (Annex VI to the Pressure Equipment Directive)

      1. 1.The CE marking shall consist of the initials “CE” taking...

      2. 2.If the CE marking is reduced or enlarged the proportions...

      3. 3.The various components of the CE marking must have substantially...

    6. SCHEDULE 6

      (Annex VII to the Pressure Equipment Directive)

    7. SCHEDULE 7

      EUROPEAN APPROVAL FOR MATERIALS

      1. 1.The notified body shall determine and perform, or arrange for...

      2. 2.The notified body shall not issue a European approval for...

      3. 3.A copy of the European approval for pressure equipment materials...

      4. 4.The materials used for the manufacture of pressure equipment conforming...

      5. 5.The notified body which issued the European approval for pressure...

    8. SCHEDULE 8

      ENFORCEMENT

      1. 1.Enforcement in Great Britain

      2. 2.In Great Britain, in relation to pressure equipment or assemblies...

      3. 3.Enforcement in Northern Ireland in relation to pressure equipment or assemblies

      4. 4.Forfeiture of pressure equipment or assemblies for private use or consumption: England and Wales and Northern Ireland

      5. 5.Forfeiture of pressure equipment or assemblies for private use or consumption: Scotland

      6. 6.Duty of enforcement authority to inform Secretary of State of action taken

      7. 7.Savings

      8. 8.Interpretation

  7. Explanatory Note

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.