Search Legislation

The Public Contracts (Scotland) Regulations 2015

Changes over time for: Section 35

 Help about opening options

Changes to legislation:

The Public Contracts (Scotland) Regulations 2015, Section 35 is up to date with all changes known to be in force on or before 29 April 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to Regulation 35:

  • Regulations applied by 2023 c. 54 s. 119(2)(a)
  • reg. 35(8)(a) word substituted by S.S.I. 2019/112 reg. 3(28)(a) (This amendment not applied to legislation.gov.uk. S.S.I. 2019/112 revoked immediately before IP completion day by S.S.I. 2020/468, regs. 1(3), 2(2)(a))
  • reg. 35(24) word substituted by S.S.I. 2019/112 reg. 3(28)(b) (This amendment not applied to legislation.gov.uk. S.S.I. 2019/112 revoked immediately before IP completion day by S.S.I. 2020/468, regs. 1(3), 2(2)(a))
  • reg. 35(25) word substituted by S.S.I. 2019/112 reg. 3(28)(c) (This amendment not applied to legislation.gov.uk. S.S.I. 2019/112 revoked immediately before IP completion day by S.S.I. 2020/468, regs. 1(3), 2(2)(a))
  • reg. 35(27)(27A) substituted for reg. 35(27) by S.S.I. 2019/112 reg. 3(28)(d) (This amendment not applied to legislation.gov.uk. S.S.I. 2019/112 revoked immediately before IP completion day by S.S.I. 2020/468, regs. 1(3), 2(2)(a))

Changes and effects yet to be applied to the whole Instrument associated Parts and Chapters:

Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):

  • reg. 11(1)(e)(i)(aa) words substituted by S.S.I. 2019/112 reg. 3(11)(a)(i) (This amendment not applied to legislation.gov.uk. S.S.I. 2019/112 revoked immediately before IP completion day by S.S.I. 2020/468, regs. 1(3), 2(2)(a))
  • reg. 11(1)(e)(i)(bb) words substituted by S.S.I. 2019/112 reg. 3(11)(a)(ii) (This amendment not applied to legislation.gov.uk. S.S.I. 2019/112 revoked immediately before IP completion day by S.S.I. 2020/468, regs. 1(3), 2(2)(a))
  • reg. 78(1)(i)(ii) and words inserted by S.S.I. 2019/112 reg. 3(52)(a) (This amendment not applied to legislation.gov.uk. S.S.I. 2019/112 revoked immediately before IP completion day by S.S.I. 2020/468, regs. 1(3), 2(2)(a))
Dynamic Purchasing SystemsS
This section has no associated Policy Notes

35.—(1) A contracting authority may use a dynamic purchasing system for commonly used purchases the characteristics of which, as generally available on the market, meet their requirements.

(2) The dynamic purchasing system must—

(a)be operated as a completely electronic process; and

(b)throughout the period of validity of the system, be open to any economic operator that satisfies the selection criteria.

(3) The dynamic purchasing system may be divided into categories of works, supplies or services that are objectively defined on the basis of characteristics of the procurement to be undertaken under the category concerned.

(4) The characteristics referred to in paragraph (3) may include reference to either or both of—

(a)the maximum allowable size of the subsequent specific contracts; and

(b)a specific geographic area in which subsequent specific contracts will be performed.

(5) In order to procure under a dynamic purchasing system, a contracting authority must follow the restricted procedure, and accordingly the provisions of regulation 29 (restricted procedure) apply, subject to the following provisions of this regulation.

(6) A contracting authority must admit to a dynamic purchasing system all of the candidates satisfying the selection criteria and must not limit the number of candidates to be admitted whether under regulations 29(4) (restricted procedure) or 66 (reduction of the number of otherwise qualified candidates to be invited to participate) or otherwise.

(7) Where a contracting authority has divided the system into categories of works, supplies or services in accordance with paragraph (3), the authority must specify the applicable selection criteria for each category.

(8) The minimum time limit for receipt of requests to participate shall be 30 days from the date on which—

(a)the contract notice is [F1submitted];F2...

F2(b). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(9) No further time limits for receipt of requests to participate shall apply once the invitation to tender for the first specific procurement under the dynamic purchasing system has been sent.

(10) The minimum time limit for receipt of tenders shall be 10 days from the date on which the invitation to tender is sent.

(11) All communications in the context of a dynamic purchasing system must be made only by electronic means in accordance with regulation 23(1) to (7) and (11) to (20) (Rules applicable to communication).

(12) For the purposes of awarding contracts under a dynamic purchasing system, a contracting authority must—

(a)publish a call for competition making it clear that a dynamic purchasing system is involved;

(b)indicate in the procurement documents at least the nature and estimated quantity of the purchases envisaged, as well as all the necessary information concerning the dynamic purchasing system, including how the system operates, the electronic equipment used and the technical connection arrangements and specifications;

(c)indicate in the procurement documents any division into categories of works, supplies or services and the characteristics defining them; and

(d)throughout the period of validity of the system, offer unrestricted and full direct access to the procurement documents in accordance with regulation 54 (electronic availability of procurement documents).

(13) A contracting authority must, throughout the period of validity of the dynamic purchasing system, give any economic operator the possibility of requesting to participate in the system under the conditions referred to in paragraphs (5) to (12).

(14) A contracting authority must finalise evaluation of such requests in accordance with the selection criteria within 10 working days following their receipt.

(15) The deadline referred to in paragraph (14) may be extended to a maximum of 15 working days in individual cases where justified, in particular, because of the need to examine additional documentation or otherwise to verify whether the selection criteria are met.

(16) Despite paragraphs (14) and (15), as long as the invitation to tender for the first specific procurement under the dynamic purchasing system has not been sent, a contracting authority may extend the evaluation period provided that no invitation to tender is issued during the extended evaluation period.

(17) Where a contracting authority intends to extend the evaluation period in accordance with paragraph (16), the authority must indicate in the procurement documents the length of the extended period that the authority intends to apply.

(18) A contracting authority must inform the economic operator concerned at the earliest possible opportunity of whether or not it has been admitted to the dynamic purchasing system.

(19) A contracting authority must invite all admitted participants to submit a tender for each specific procurement under the dynamic purchasing system, in accordance with regulation 55 (invitations to candidates).

(20) Where the dynamic purchasing system has been divided into categories of works, supplies or services, a contracting authority must invite every relevant participant to submit a tender.

(21) In paragraph (20), “relevant participant” means an economic operator which has been admitted to the dynamic purchasing system in relation to the category corresponding to the specific procurement concerned.

(22) A contracting authority must award the contract to the tenderer that submitted the most economically advantageous tender on the basis of the award criteria set out in the contract notice for the dynamic purchasing system F3....

(23) Those criteria may, where appropriate, be formulated more precisely in the invitation to tender.

(24) A contracting authority may, at any time throughout the period of validity of the dynamic purchasing system, require admitted participants to submit a renewed [F4SPD] within 5 working days from the date on which that request is transmitted.

(25) Regulation 60(8) to (11) (F5...Single Procurement Document: use, content and form of the [F6SPD]) shall apply throughout the period of validity of the dynamic purchasing system.

(26) A contracting authority must indicate the period of validity of the dynamic purchasing system in the call for competition.

[F7(27) Where the period of validity is changed without terminating the dynamic purchasing system, the contracting authority shall submit for publication on the UK e-notification service a notice of the kind used initially for the call for competition for the dynamic purchasing system.

(27A) Where a dynamic purchasing system is terminated before the end of the period of validity that had most recently been indicated under paragraph (26) or (27), the contracting authority shall submit for publication on the UK e-notification service a contract award notice under regulation 51 (contract award notices).]

(28) No charges may be made to any economic operators which are interested in or are a party to the dynamic purchasing system.

Back to top

Options/Help

Print Options

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Policy Note

Policy Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2012 onwards. Prior to this date these type of notes existed as ‘Executive Notes’ and accompanied Scottish Statutory Instruments from July 2005 until July 2012.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources