Search Legislation

Directive 2009/73/EC of the European Parliament and of the CouncilShow full title

Directive 2009/73/EC of the European Parliament and of the Council of 13 July 2009 concerning common rules for the internal market in natural gas and repealing Directive 2003/55/EC (Text with EEA relevance)

 Help about what version

What Version

 Help about advanced features

Advanced Features

More Resources

Close

This is a legislation item that originated from the EU

After exit day there will be three versions of this legislation to consult for different purposes. The legislation.gov.uk version is the version that applies in the UK. The EU Version currently on EUR-lex is the version that currently applies in the EU i.e you may need this if you operate a business in the EU.

The web archive version is the official version of this legislation item as it stood on exit day before being published to legislation.gov.uk and any subsequent UK changes and effects applied. The web archive also captured associated case law and other language formats from EUR-Lex.

Status:

EU Directives are being published on this site to aid cross referencing from UK legislation. After IP completion day (31 December 2020 11pm) no further amendments will be applied to this version.

CHAPTER VIIU.K.ORGANISATION OF ACCESS TO THE SYSTEM

Article 32U.K.Third-party access

1.Member States shall ensure the implementation of a system of third party access to the transmission and distribution system, and LNG facilities based on published tariffs, applicable to all eligible customers, including supply undertakings, and applied objectively and without discrimination between system users. Member States shall ensure that those tariffs, or the methodologies underlying their calculation are approved prior to their entry into force in accordance with Article 41 by a regulatory authority referred to in Article 39(1) and that those tariffs — and the methodologies, where only methodologies are approved — are published prior to their entry into force.

2.Transmission system operators shall, if necessary for the purpose of carrying out their functions including in relation to cross-border transmission, have access to the network of other transmission system operators.

3.The provisions of this Directive shall not prevent the conclusion of long-term contracts in so far as they comply with Community competition rules

Article 33U.K.Access to storage

1.For the organisation of access to storage facilities and linepack when technically and/or economically necessary for providing efficient access to the system for the supply of customers, as well as for the organisation of access to ancillary services, Member States may choose either or both of the procedures referred to in paragraphs 3 and 4. Those procedures shall operate in accordance with objective, transparent and non-discriminatory criteria.

The regulatory authorities where Member States have so provided or Member States shall define and publish criteria according to which the access regime applicable to storage facilities and linepack may be determined. They shall make public, or oblige storage and transmission system operators to make public, which storage facilities, or which parts of those storage facilities, and which linepack is offered under the different procedures referred to in paragraphs 3 and 4.

The obligation referred to in the second sentence of the second subparagraph shall be without prejudice to the right of choice granted to Member States in the first subparagraph.

2.The provisions of paragraph 1 shall not apply to ancillary services and temporary storage that are related to LNG facilities and are necessary for the re-gasification process and subsequent delivery to the transmission system.

3.In the case of negotiated access, Member States or, where Member States have so provided, the regulatory authorities shall take the necessary measures for natural gas undertakings and eligible customers either inside or outside the territory covered by the interconnected system to be able to negotiate access to storage facilities and linepack, when technically and/or economically necessary for providing efficient access to the system, as well as for the organisation of access to other ancillary services. The parties shall be obliged to negotiate access to storage, linepack and other ancillary services in good faith.

Contracts for access to storage, linepack and other ancillary services shall be negotiated with the relevant storage system operator or natural gas undertakings. The regulatory authorities where Member States have so provided or Member States shall require storage system operators and natural gas undertakings to publish their main commercial conditions for the use of storage, linepack and other ancillary services by 1 January 2005 and on an annual basis every year thereafter.

When developing the conditions referred to in the second subparagraph, storage operators and natural gas undertakings shall consult system users.

4.In the case of regulated access, the regulatory authorities where Member States have so provided or Member States shall take the necessary measures to give natural gas undertakings and eligible customers either inside or outside the territory covered by the interconnected system a right to access to storage, linepack and other ancillary services, on the basis of published tariffs and/or other terms and obligations for use of that storage and linepack, when technically and/or economically necessary for providing efficient access to the system, as well as for the organisation of access to other ancillary services. The regulatory authorities where Member States have so provided or Member States shall consult system users when developing those tariffs or the methodologies for those tariffs. The right of access for eligible customers may be given by enabling them to enter into supply contracts with competing natural gas undertakings other than the owner and/or operator of the system or a related undertaking.

Article 34U.K.Access to upstream pipeline networks

1.Member States shall take the necessary measures to ensure that natural gas undertakings and eligible customers, wherever they are located, are able to obtain access to upstream pipeline networks, including facilities supplying technical services incidental to such access, in accordance with this Article, except for the parts of such networks and facilities which are used for local production operations at the site of a field where the gas is produced. The measures shall be notified to the Commission in accordance with the provisions of Article 54.

2.The access referred to in paragraph 1 shall be provided in a manner determined by the Member State in accordance with the relevant legal instruments. Member States shall apply the objectives of fair and open access, achieving a competitive market in natural gas and avoiding any abuse of a dominant position, taking into account security and regularity of supplies, capacity which is or can reasonably be made available, and environmental protection. The following matters may be taken into account:

(a)the need to refuse access where there is an incompatibility of technical specifications which cannot reasonably be overcome;

(b)the need to avoid difficulties which cannot reasonably be overcome and could prejudice the efficient, current and planned future production of hydrocarbons, including that from fields of marginal economic viability;

(c)the need to respect the duly substantiated reasonable needs of the owner or operator of the upstream pipeline network for the transport and processing of gas and the interests of all other users of the upstream pipeline network or relevant processing or handling facilities who may be affected; and

(d)the need to apply their laws and administrative procedures, in conformity with Community law, for the grant of authorisation for production or upstream development.

3.Member States shall ensure that they have in place dispute-settlement arrangements, including an authority independent of the parties with access to all relevant information, to enable disputes relating to access to upstream pipeline networks to be settled expeditiously, taking into account the criteria in paragraph 2 and the number of parties which may be involved in negotiating access to such networks.

[F14. In the event of cross-border disputes, the dispute-settlement arrangements for the Member State having jurisdiction over the upstream pipeline network which refuses access shall be applied. Where, in cross-border disputes, more than one Member State covers the network concerned, the Member States concerned shall consult each other with a view to ensuring that the provisions of this Directive are applied consistently. Where the upstream pipeline network originates from a third country and connects to at least one Member State, the Member States concerned shall consult each other and the Member State where the first entry point to the Member States' network is located shall consult the third country concerned where the upstream pipeline network originates, with a view to ensuring, as regards the network concerned, that this Directive is applied consistently in the territory of the Member States.]

Article 35U.K.Refusal of access

1.Natural gas undertakings may refuse access to the system on the basis of lack of capacity or where the access to the system would prevent them from carrying out the public service obligations referred to in Article 3(2) which are assigned to them or on the basis of serious economic and financial difficulties with take-or-pay contracts having regard to the criteria and procedures set out in Article 48 and the alternative chosen by the Member State in accordance with paragraph 1 of that Article. Duly substantiated reasons shall be given for any such a refusal.

2.Member States may take the measures necessary to ensure that the natural gas undertaking refusing access to the system on the basis of lack of capacity or a lack of connection makes the necessary enhancements as far as it is economic to do so or when a potential customer is willing to pay for them. In circumstances where Member States apply Article 4(4), Member States shall take such measures.

Article 36U.K.New infrastructure

1.Major new gas infrastructure, i.e. interconnectors, LNG and storage facilities, may, upon request, be exempted, for a defined period of time, from the provisions of Articles 9, 32, 33 and 34 and Article 41(6), (8) and (10) under the following conditions:

(a)the investment must enhance competition in gas supply and enhance security of supply;

(b)the level of risk attached to the investment must be such that the investment would not take place unless an exemption was granted;

(c)the infrastructure must be owned by a natural or legal person which is separate at least in terms of its legal form from the system operators in whose systems that infrastructure will be built;

(d)charges must be levied on users of that infrastructure; and

[F1(e) the exemption must not be detrimental to competition in the relevant markets which are likely to be affected by the investment, to the effective functioning of the internal market in natural gas, the efficient functioning of the regulated systems concerned, or to security of supply of natural gas in the Union.]

2.Paragraph 1 shall also apply to significant increases of capacity in existing infrastructure and to modifications of such infrastructure which enable the development of new sources of gas supply.

[F13. The regulatory authority referred to in Chapter VIII may, on a case-by-case basis, decide on the exemption referred to in paragraphs 1 and 2.

Before the adoption of the decision on the exemption, the national regulatory authority, or where appropriate another competent authority of that Member State, shall consult:

(a) the national regulatory authorities of the Member States the markets of which are likely to be affected by the new infrastructure; and

(b) the relevant authorities of the third countries, where the infrastructure in question is connected with the Union network under the jurisdiction of a Member State, and originates from or ends in one or more third countries.

Where the third-country authorities consulted do not respond to the consultation within a reasonable time frame or within a set deadline not exceeding three months, the national regulatory authority concerned may adopt the necessary decision.]

4.Where the infrastructure in question is located in the territory of more than one Member State, the Agency may submit an advisory opinion to the regulatory authorities of the Member States concerned, which may be used as a basis for their decision, within two months from the date on which the request for exemption was received by the last of those regulatory authorities.

[F1Where all the regulatory authorities concerned agree on the request for exemption within six months of the date on which it was received by the last of the regulatory authorities, they shall inform the Agency of their decision. Where the infrastructure concerned is a transmission line between a Member State and a third country, before the adoption of the decision on the exemption, the national regulatory authority, or where appropriate another competent authority of the Member State where the first interconnection point with the Member States' network is located, may consult the relevant authority of that third country with a view to ensuring, as regards the infrastructure concerned, that this Directive is applied consistently in the territory and, where applicable, in the territorial sea of that Member State. Where the third country authority consulted does not respond to the consultation within a reasonable time or within a set deadline not exceeding three months, the national regulatory authority concerned may adopt the necessary decision.]

The Agency shall exercise the tasks conferred on the regulatory authorities of the Member States concerned by the present Article:

(a)where all regulatory authorities concerned have not been able to reach an agreement within a period of six months from the date on which the request for exemption was received by the last of those regulatory authorities; or

(b)upon a joint request from the regulatory authorities concerned.

All regulatory authorities concerned may, jointly, request that the period referred to in point (a) of the third subparagraph is extended by up to three months.

5.Before taking a decision, the Agency shall consult the relevant regulatory authorities and the applicants.

6.An exemption may cover all or part of the capacity of the new infrastructure, or of the existing infrastructure with significantly increased capacity.

In deciding to grant an exemption, consideration shall be given, on a case-by-case basis, to the need to impose conditions regarding the duration of the exemption and non-discriminatory access to the infrastructure. When deciding on those conditions, account shall, in particular, be taken of the additional capacity to be built or the modification of existing capacity, the time horizon of the project and national circumstances.

Before granting an exemption, the regulatory authority shall decide upon the rules and mechanisms for management and allocation of capacity. The rules shall require that all potential users of the infrastructure are invited to indicate their interest in contracting capacity before capacity allocation in the new infrastructure, including for own use, takes place. The regulatory authority shall require congestion management rules to include the obligation to offer unused capacity on the market, and shall require users of the infrastructure to be entitled to trade their contracted capacities on the secondary market. In its assessment of the criteria referred to in points (a), (b) and (e) of paragraph 1, the regulatory authority shall take into account the results of that capacity allocation procedure.

The exemption decision, including any conditions referred to in the second subparagraph of this paragraph, shall be duly reasoned and published.

7.Notwithstanding paragraph 3, Member States may provide that their regulatory authority or the Agency, as the case may be, shall submit, for the purposes of the formal decision, to the relevant body in the Member State its opinion on the request for an exemption. That opinion shall be published together with the decision.

8.The regulatory authority shall transmit to the Commission, without delay, a copy of every request for exemption as of its receipt. The decision shall be notified, without delay, by the competent authority to the Commission, together with all the relevant information with respect to the decision. That information may be submitted to the Commission in aggregate form, enabling the Commission to reach a well-founded decision. In particular, the information shall contain:

(a)the detailed reasons on the basis of which the regulatory authority, or Member State, granted or refused the exemption together with a reference to paragraph 1 including the relevant point or points of that paragraph on which such decision is based, including the financial information justifying the need for the exemption;

(b)the analysis undertaken of the effect on competition and the effective functioning of the internal market in natural gas resulting from the grant of the exemption;

(c)the reasons for the time period and the share of the total capacity of the gas infrastructure in question for which the exemption is granted;

(d)in case the exemption relates to an interconnector, the result of the consultation with the regulatory authorities concerned; and

(e)the contribution of the infrastructure to the diversification of gas supply.

9.Within a period of two months from the day following the receipt of a notification, the Commission may take a decision requiring the regulatory authority to amend or withdraw the decision to grant an exemption. That two-month period may be extended by an additional period of two months where further information is sought by the Commission. That additional period shall begin on the day following the receipt of the complete information. The initial two-month period may also be extended with the consent of both the Commission and the regulatory authority.

Where the requested information is not provided within the period set out in the request, the notification shall be deemed to be withdrawn unless, before the expiry of that period, either the period has been extended with the consent of both the Commission and the regulatory authority, or the regulatory authority, in a duly reasoned statement, has informed the Commission that it considers the notification to be complete.

The regulatory authority shall comply with the Commission decision to amend or withdraw the exemption decision within a period of one month and shall inform the Commission accordingly.

The Commission shall preserve the confidentiality of commercially sensitive information.

The Commission’s approval of an exemption decision shall lose its effect two years from its adoption in the event that construction of the infrastructure has not yet started, and five years from its adoption in the event that the infrastructure has not become operational unless the Commission decides that any delay is due to major obstacles beyond control of the person to whom the exemption has been granted.

10.The Commission may adopt Guidelines for the application of the conditions laid down in paragraph 1 of this Article and to set out the procedure to be followed for the application of paragraphs 3, 6, 8 and 9 of this Article. Those measures, designed to amend non-essential elements of this Directive by supplementing it, shall be adopted in accordance with the regulatory procedure with scrutiny referred to in Article 51(3).

Article 37U.K.Market opening and reciprocity

1.Member States shall ensure that the eligible customers comprise:

(a)until 1 July 2004, eligible customers as specified in Article 18 of Directive 98/30/EC of the European Parliament and of the Council of 22 June 1998 concerning common rules for the internal market in natural gas(1). Member States shall publish, by 31 January each year, the criteria for the definition of those eligible customers;

(b)from 1 July 2004, all non-household customers;

(c)from 1 July 2007, all customers.

2.To avoid imbalance in the opening of the gas markets:

(a)contracts for the supply with an eligible customer in the system of another Member State shall not be prohibited if the customer is eligible in both systems involved; and

(b)where transactions as described in point (a) are refused because the customer is eligible in only one of the two systems, the Commission may, taking into account the situation in the market and the common interest, oblige the refusing party to execute the requested supply, at the request of one of the Member States of the two systems.

Article 38U.K.Direct lines

1.Member States shall take the necessary measures to enable:

(a)natural gas undertakings established within their territory to supply the eligible customers through a direct line; and

(b)any such eligible customer within their territory to be supplied through a direct line by natural gas undertakings.

2.In circumstances where an authorisation (for example, licence, permission, concession, consent or approval) is required for the construction or operation of direct lines, the Member States or any competent authority they designate shall lay down the criteria for the grant of authorisations for the construction or operation of such lines in their territory. Those criteria shall be objective, transparent and non-discriminatory.

3.Member States may issue an authorisation to construct a direct line subject either to the refusal of system access on the basis of Article 35 or to the opening of a dispute-settlement procedure under Article 41.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources