Directive 2004/18/EC of the European Parliament and of the Council of 31 March 2004 on the coordination of procedures for the award of public works contracts, public supply contracts and public service contracts (repealed)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
This is the original version (as it was originally adopted).
1.Member States may provide that contracting authorities may conclude framework agreements.
2.For the purpose of concluding a framework agreement, contracting authorities shall follow the rules of procedure referred to in this Directive for all phases up to the award of contracts based on that framework agreement. The parties to the framework agreement shall be chosen by applying the award criteria set in accordance with Article 53.
Contracts based on a framework agreement shall be awarded in accordance with the procedures laid down in paragraphs 3 and 4. Those procedures may be applied only between the contracting authorities and the economic operators originally party to the framework agreement.
When awarding contracts based on a framework agreement, the parties may under no circumstances make substantial amendments to the terms laid down in that framework agreement, in particular in the case referred to in paragraph 3.
The term of a framework agreement may not exceed four years, save in exceptional cases duly justified, in particular by the subject of the framework agreement.
Contracting authorities may not use framework agreements improperly or in such a way as to prevent, restrict or distort competition.
3.Where a framework agreement is concluded with a single economic operator, contracts based on that agreement shall be awarded within the limits of the terms laid down in the framework agreement.
For the award of those contracts, contracting authorities may consult the operator party to the framework agreement in writing, requesting it to supplement its tender as necessary.
4.Where a framework agreement is concluded with several economic operators, the latter must be at least three in number, insofar as there is a sufficient number of economic operators to satisfy the selection criteria and/or of admissible tenders which meet the award criteria.
Contracts based on framework agreements concluded with several economic operators may be awarded either:
by application of the terms laid down in the framework agreement without reopening competition, or
where not all the terms are laid down in the framework agreement, when the parties are again in competition on the basis of the same and, if necessary, more precisely formulated terms, and, where appropriate, other terms referred to in the specifications of the framework agreement, in accordance with the following procedure:
for every contract to be awarded, contracting authorities shall consult in writing the economic operators capable of performing the contract;
contracting authorities shall fix a time limit which is sufficiently long to allow tenders for each specific contract to be submitted, taking into account factors such as the complexity of the subject-matter of the contract and the time needed to send in tenders;
tenders shall be submitted in writing, and their content shall remain confidential until the stipulated time limit for reply has expired;
contracting authorities shall award each contract to the tenderer who has submitted the best tender on the basis of the award criteria set out in the specifications of the framework agreement.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: