Section 38 – Procedure and time limits

77.Prior to a supplier bringing proceedings under section 37 which may be brought in the sheriff court or Court of Session, the supplier must notify the contracting authority of its intention to bring proceedings and the failure to comply with the duties referred to above. The time limit for bringing proceedings under section 38 is 30 days from the day on which the supplier knew or ought to have known that grounds for starting the proceedings had arisen, or such longer period of up to three months as the court considers appropriate. Extension of the period may be permitted by the court only if it considers that there is good reason for doing so.

Back to top

Options/Help

Print Options

Close

Explanatory Notes

Text created by the Scottish Government to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Acts of the Scottish Parliament except those which result from Budget Bills.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources