- Latest available (Revised)
- Original (As enacted)
This is the original version (as it was originally enacted).
(1)This subsection applies to—
(a)a decision under section 3 refusing an application for a direction dispensing with or relaxing a provision of building regulations,
(b)a decision of a verifier under section 9 refusing to grant a building warrant or an amendment to the terms of a warrant,
(c)a decision of a verifier under section 14 refusing to extend the period for the demolition of a building intended to have a limited life,
(d)a decision of a verifier under section 18 rejecting a completion certificate,
(e)a decision of a verifier under section 22 imposing continuing requirements,
(f)a decision of a verifier under section 23 refusing to discharge or vary a continuing requirement,
(g)a building regulations compliance notice, a continuing requirement enforcement notice, a building warrant enforcement notice, a defective building notice and a dangerous building notice.
(2)Where a verifier has not, within such period as may be specified in procedure regulations or such extended period as may at any time be agreed between the verifier and the owner of a building, determined—
(a)an application for a building warrant or for an amendment to a building warrant,
(b)an application to extend the period for the demolition of a building intended to have a limited life,
(c)whether to accept or reject a completion certificate submitted to it, or
(d)an application for discharge or variation of a continuing requirement imposed under section 22,
the verifier is deemed, for the purposes of subsection (1), to have taken a decision of a description specified in paragraph (b), (c), (d) or, as the case may be, (f) of that subsection on the last day of the specified period or extended period.
(3)Any person aggrieved by a decision or notice to which subsection (1) applies may, by summary application made within 21 days of the date of the decision or notice, appeal to the sheriff.
(4)A decision or notice to which subsection (1) applies is of no effect until—
(a)the period within which an appeal may be brought under subsection (3) has elapsed without an appeal being brought, or
(b)where such an appeal is brought, the appeal is withdrawn or finally determined.
(5)Despite subsection (4), a provision of a building warrant enforcement notice made in pursuance of subsection (5)(c) of section 27—
(a)has effect as soon as the notice is served, and
(b)where an appeal is brought under subsection (3) of this section, continues to have effect (regardless of the terms of the notice), unless quashed by an order of the sheriff under subsection (6), until the enforcement notice has been complied with.
(6)On an appeal under this section the sheriff may make such order as the sheriff thinks fit.
(7)The decision of the sheriff on an appeal under this section is final.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Text created by the Scottish Government to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Acts of the Scottish Parliament except those which result from Budget Bills.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: