(1)When the Welsh Ministers have decided an application for infrastructure consent, the Welsh Ministers must either—
(a)make an order granting infrastructure consent (“an infrastructure consent order”), or
(b)refuse infrastructure consent.
(2)The Welsh Ministers must notify the following of their decision to either make an infrastructure consent order or refuse infrastructure consent—
(a)the applicant;
(b)any planning authority or community council that has submitted a local impact report to the Welsh Ministers in respect of the application;
(c)Natural Resources Wales if it has submitted a marine impact report to the Welsh Ministers in respect of the application;
(d)any other person or persons of a description specified in regulations.
(3)When the examining authority has decided an application for infrastructure consent, they must either—
(a)notify the Welsh Ministers of their decision that an infrastructure consent order is to be made, or
(b)refuse infrastructure consent.
(4)The examining authority must notify the following of its decision either that an infrastructure consent order is to be made or to refuse infrastructure consent—
(a)the applicant;
(b)any planning authority or community council that has submitted a local impact report to the Welsh Ministers in respect of the application;
(c)Natural Resources Wales if it has submitted a marine impact report to the Welsh Ministers in respect of the application;
(d)any other person or persons of a description specified in regulations.
(5)When the Welsh Ministers receive a notice under subsection (3)(a), they must make an infrastructure consent order in respect of the application to which the notice relates.
(6)Regulations may make provision regulating the procedure to be followed if—
(a)the Welsh Ministers propose to make an infrastructure consent order on terms which are materially different from those proposed in the application;
(b)the Welsh Ministers propose to make an infrastructure consent order on terms which are materially different from those proposed in the application as a result of a notice under subsection (3)(a).
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.
Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: