This is the original version (as it was originally enacted).
(1)The following kinds of development are significant infrastructure projects—
(a)the construction of—
(i)a generating station in Wales (other than a wind generating station), or
(ii)a generating station in the Welsh marine area,
that is expected to have an installed generating capacity of between 50 and 350 megawatts when constructed;
(b)the extension or alteration of—
(i)a generating station in Wales (other than a wind generating station), or
(ii)a generating station in the Welsh marine area,
where the effect of the extension or alteration is expected to increase the installed generating capacity by at least 50 megawatts, but not so that the installed generating capacity exceeds 350 megawatts;
(c)the construction of a wind generating station in Wales that is expected to have an installed generating capacity of at least 50 megawatts when constructed;
(d)the extension or alteration of a wind generating station in Wales where the effect of the extension or alteration is expected to increase the installed generating capacity by at least 50 megawatts;
(e)the installation of an electric line above ground in Wales that is—
(i)expected to have a nominal voltage of 132 kilovolts and be no less than 2 kilometres long (to the extent it is in Wales), and
(ii)associated with the construction, extension or alteration of a generating station to which paragraphs (a) to (d) apply.
(2)In this section—
“installed generating capacity” (“capasiti cynyrchu gosodedig”) means the maximum capacity of electricity generation (in megawatts) at which that generating station could be operated for a sustained period without damage being caused to it (assuming the source of energy used to generate electricity is available without interruption);
“wind generating station” (“gorsaf ynni gwynt”) means a generating station which generates electricity from wind.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.
Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: