Article 3(2)
1. The exemption granted by article 3(1) to Banks Renewables (Kype Muir Wind Farm) Limited in respect of Kype Muir Wind Farm is subject to the conditions that—
(a)Kype Muir Wind Farm is connected to the total system;
(b)except in circumstances outside the reasonable control of Banks Renewables (Kype Muir Wind Farm) Limited, Kype Muir Wind Farm does not export more than 100 megawatts of electrical power to the total system; and
(c)Banks Renewables (Kype Muir Wind Farm) Limited does not hold a licence under section 6(1)(a) of the Act.
2. The exemption granted by article 3(1) to Banks Renewables (Middle Muir Wind Farm) Limited in respect of Middle Muir Wind Farm is subject to the conditions that—
(a)Middle Muir Wind Farm is connected to the total system;
(b)except in circumstances outside the reasonable control of Banks Renewables (Middle Muir Wind Farm) Limited, Middle Muir Wind Farm does not export more than 100 megawatts of electrical power to the total system; and
(c)Banks Renewables (Middle Muir Wind Farm) Limited does not hold a licence under section 6(1)(a) of the Act.
3. The exemption granted by article 3(1) to Brockloch Rig Windfarm Limited in respect of Brockloch Rig Windfarm is subject to the conditions that—
(a)Brockloch Rig Windfarm is connected to the total system;
(b)except in circumstances outside the reasonable control of Brockloch Rig Windfarm Limited, Brockloch Rig Windfarm does not export more than 100 megawatts of electrical power to the total system; and
(c)Brockloch Rig Windfarm Limited does not hold a licence under section 6(1)(a) of the Act.
4. The exemption granted by article 3(1) to Heck Fen Wind Park Limited in respect of Heckington Fen Wind Park is subject to the conditions that—
(a)Heckington Fen Wind Park is connected to the total system;
(b)except in circumstances outside the reasonable control of Heck Fen Wind Park Limited, Heckington Fen Wind Park does not export more than 100 megawatts of electrical power to the total system; and
(c)Heck Fen Wind Park Limited does not hold a licence under section 6(1)(a) of the Act.
5. The exemption granted by article 3(1) to Innogy Renewables UK Limited in respect of Brechfa Forest West Wind Farm is subject to the conditions that—
(a)Brechfa Forest West Wind Farm is connected to the total system;
(b)except in circumstances outside the reasonable control of Innogy Renewables UK Limited, Brechfa Forest West Wind Farm does not export more than 100 megawatts of electrical power to the total system; and
(c)Innogy Renewables UK Limited does not hold a licence under section 6(1)(a) of the Act.
6. The exemption granted by article 3(1) to Ray Wind Farm Limited in respect of Ray Wind Farm is subject to the conditions that—
(a)Ray Wind Farm is connected to the total system;
(b)except in circumstances outside the reasonable control of Ray Wind Farm Limited, Ray Wind Farm does not export more than 100 megawatts of electrical power to the total system; and
(c)Ray Wind Farm Limited does not hold a licence under section 6(1)(a) of the Act.
7. The exemption granted by article 3(1) to RWE Cogen UK Limited in respect of Cheshire Power Station is subject to the conditions that—
(a)Cheshire Power Station is connected to the total system;
(b)except in circumstances outside the reasonable control of RWE Cogen UK Limited, Cheshire Power Station does not export more than 100 megawatts of electrical power to the total system; and
(c)RWE Cogen UK Limited does not hold a licence under section 6(1)(a) of the Act.
8. The exemption granted by article 3(1) to Snowdonia Pumped Hydro Limited in respect of Glyn Rhonwy Pumped Hydro is subject to the conditions that—
(a)Glyn Rhonwy Pumped Hydro is connected to the total system;
(b)except in circumstances outside the reasonable control of Snowdonia Pumped Hydro Limited, Glyn Rhonwy Pumped Hydro does not export more than 100 megawatts of electrical power to the total system; and
(c)Snowdonia Pumped Hydro Limited does not hold a licence under section 6(1)(a) of the Act.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: