PART 3 ACQUISITION AND POSSESSION OF LAND
SCHEDULES
PUBLIC RIGHTS OF WAY AND PERMISSIVE PATHS TO BE EXTINGUISHED
PUBLIC RIGHTS OF NAVIGATION TO BE AFFECTED BY THE AUTHORISED PROJECT
LAND OF WHICH ONLY SUBSOIL MORE THAN 9 METRES BENEATH THE SURFACE MAY BE ACQUIRED
PROVISIONS FOR PROTECTION OF SPECIFIED UNDERTAKERS
SECTION 1 Protection of TfL Railway Companies
1.The provisions of this Part of this Schedule shall have...
2.In this Part of this Schedule— “approval” in relation to...
3.(1) The undertaker shall not under the powers conferred by...
4.(1) The undertaker shall, before commencing the specified works, furnish...
6.Without prejudice to the generality of paragraphs 4 and 5...
7.The undertaker shall at all times afford reasonable facilities to...
8.During the construction of any part of the specified works...
9.(1) If any alterations or additions either permanent or temporary,...
10.The undertaker shall repay to any protected person all costs,...
11.(1) In this paragraph— “apparatus” means any lines, circuits, wires...
13.Any additional expenses which a protected person may reasonably incur...
15.Any difference arising between the undertaker and a protected person...
SECTION 2 For the Protection of London River Services Limited
1.The provisions of this Part of this Schedule shall have...
2.In this Part of this Schedule— “approval” in relation to...
3.(1) The undertaker shall not under the powers conferred by...
4.(1) The undertaker shall, before commencing the specified works, furnish...
6.Without prejudice to the generality of paragraphs 4 and 5...
7.The undertaker shall at all times afford reasonable facilities to...
8.During the construction of any part of the specified works...
9.(1) If any alterations or additions either permanent or temporary,...
10.The undertaker shall repay to LRSL all costs, charges and...
12.Any additional expenses which a LRSL may reasonably incur in...
13.(1) The undertaker shall be responsible for, and make good...
14.Any difference arising between the undertaker and LRSL under this...
SECTION 3 Protection for Highways Structures
1.The provisions of this Part of this Schedule shall have...
2.In this Part of this Schedule— “approval” in relation to...
4.(1) The undertaker shall, before commencing the specified works, furnish...
6.Without prejudice to the generality of paragraphs 4 and 5...
7.The undertaker shall at all times afford reasonable facilities to...
8.During the construction of any part of the specified works...
9.(1) If any alterations or additions either permanent or temporary,...
10.The undertaker shall repay to TfL all costs, charges and...
12.Any additional expenses which TfL may reasonably incur in altering,...
13.(1) The undertaker shall be responsible for and make good...
14.Any difference arising between the undertaker and TfL under this...
1.The following provisions of this Part of this Schedule shall...
2.In this Schedule— “asset protection agreement” means an agreement to...
4.(1) The undertaker shall not exercise the powers conferred by...
5.(1) The undertaker shall before commencing construction of any specified...
7.The undertaker shall— (a) at all times afford reasonable facilities...
8.Network Rail shall at all times afford reasonable facilities to...
9.(1) If any permanent or temporary alterations or additions to...
10.The undertaker shall repay to Network Rail all reasonable fees,...
12.The undertaker shall not provide any illumination or illuminated sign...
13.Any additional expenses which Network Rail may reasonably incur in...
14.(1) The undertaker shall pay to Network Rail all reasonable...
17.The undertaker and Network Rail may, subject in the case...
18.Nothing in this Order, or in any enactment incorporated with...
19.The undertaker shall give written notice to Network Rail if...
21.Notwithstanding article 54 (Discharge of requirements, etc) any difference or...