Article 11
Borough | Street to be altered | Description of alteration | Relevant Site |
---|---|---|---|
London Borough of Ealing | Canham Road | Works to provide site access, temporary removal of on street parking, introduction of temporary waiting restrictions and footway widening works. | Acton Storm Tanks |
London Borough of Ealing | Warple Way | Works to provide site access, temporary removal of on street parking and introduction of temporary waiting restrictions | Acton Storm Tanks |
London Borough of Ealing | Stanley Gardens | Works associated with the temporary modification to kerb line, temporary removal of on street parking and introduction of temporary waiting restrictions | Acton Storm Tanks |
London Borough of Hammersmith and Fulham | Distillery Road | Works to provide site accesses | Hammersmith Pumping Station |
London Borough of Hammersmith and Fulham | Chancellor’s Road | Temporary removal of on street parking and introduction of temporary waiting restrictions. Modification to kerb line on its junction with Distillery Road | Hammersmith Pumping Station |
London Borough of Wandsworth | The Embankment | Works to provide site access, temporary removal of on street parking, the introduction of temporary waiting restrictions, formation of access to temporary slipway, temporary suspension of one-way, kerb line modifications and temporary removal of traffic island | Putney Embankment Foreshore |
Works associated with environmental enhancement including footway surfacing and street furniture | |||
London Borough of Wandsworth | Glendarvon Street | Temporary removal of on street parking and introduction of waiting restrictions | Putney Embankment Foreshore |
London Borough of Wandsworth | Lower Richmond Road | Installation of ducting within carriageway and pedestrian site access gate | Putney Embankment Foreshore |
London Borough of Wandsworth | Putney High Street/Putney Bridge | Installation of vent column | Putney Embankment Foreshore |
Hammersmith and Fulham | Carnwath Road | Works to provide site access, temporary removal of on street parking and introduction of temporary waiting restrictions, footway and junction modifications at its junction with Wandsworth Bridge Road | Carnwath Road Riverside |
Hammersmith and Fulham | Wandsworth Bridge Road | Modification to traffic signalised junction | Carnwath Road Riverside |
London Borough of Wandsworth | Dormay Street | Works to provide site access | Dormay Street |
London Borough of Wandsworth | The Causeway | Works to provide site access Temporary removal of on street parking and introduction of temporary waiting restrictions | Dormay Street |
London Borough of Wandsworth | Armoury Way | Temporary kerb line and junction modifications | Dormay Street |
London Borough of Wandsworth | Neville Gill Close | Provision of construction access, temporary modification to kerb lines and pedestrian refuge | King George’s Park |
London Borough of Wandsworth | Buckhold Road | Modification to kerb lines, pedestrian refuge and park entrance | King George’s Park |
London Borough of Wandsworth | York Road | Works to provide site accesses and works associated with the relocation of bus stop facilities | Falconbrook Pumping Station |
London Borough of Wandsworth | York Gardens | Woks to provide site access and temporary removal of parking | Falconbrook Pumping Station |
Royal Borough of Kensington and Chelsea | Lots Road | Works to provide site access, temporary removal of on street parking and introduction of temporary waiting restrictions | Cremorne Wharf Depot |
Royal Borough of Kensington and Chelsea | Chelsea Embankment | Works to provide site accesses Works to facilitate the provision of traffic management including provision of a temporary formal crossing, temporary removal of traffic island, provision of site hoarding Works associated with environmental enhancement including footway surfacing and street furniture | Chelsea Embankment Foreshore |
Royal Borough of Kensington and Chelsea | The Bull Ring | Works associated with environmental enhancement including footway and carriageway surfacing and street furniture | Chelsea Embankment Foreshore |
London Borough of Wandsworth | Kirtling Street | Works to provide site access, the provision of traffic management, temporary removal of on street parking and introduction of temporary waiting restrictions Works to undertake environmental enhancements | Kirtling Street |
London Borough of Wandsworth | Cringle Street | Works to provide site access Works to undertake carriageway crossing for services Works associated with environmental enhancement including footway surfacing and street furniture | Kirtling Street |
London Borough of Wandsworth | Nine Elms Lane | Works to provide site access Works associated with environmental enhancement including footway surfacing, tree planting, and street furniture | Heathwall Pumping Station |
London Borough of Lambeth | Albert Embankment | Works to provide site access | Albert Embankment Foreshore |
City of Westminster | Victoria Embankment | Works to provide site access. Works to facilitate the provision of traffic management, modification to waiting restrictions, removal of central carriageway reserve, provision of site hoarding, removal of cycle parking station Works to facilitate the temporary and permanent provision of access to boat moorings Works associated with environmental enhancement including footway surfacing and street furniture Works to construct a ramp and stairs on the footway | Victoria Embankment Foreshore |
City of London | Victoria Embankment / Blackfriars Underpass / Blackfriars Bridge head / Blackfriars Bridge | Works to provide site access. Provision of traffic management including modification to waiting restrictions/loading bays, provision of site hoarding Works to facilitate the temporary and permanent provision of access to boat moorings Works associated with environmental enhancement including footway surfacing, step access from Blackfriars Bridge, lift access from Blackfriars Bridge, and street furniture Works to construct a ramp and stairs on the footway | Blackfriars Bridge Foreshore |
City of London | New Bridge Street / Blackfriars Bridge / Blackfriars Bridge head | Provision of Temporary traffic management Provision of pedestrian lift | Blackfriars Bridge Foreshore |
City of London | White Lion Hill | Modification of kerb, boundary wall, railing and provision of loading bay | Blackfriars Bridge Foreshore |
London Borough of Southwark | Maguire Street and Shad Thames | Works to provide site access Works for the provision of traffic management, provision of temporary turning head, temporary removal of on street parking, introduction of temporary waiting restrictions and works for the provision of chambers, pipeline and ducts | Shad Thames Pumping Station |
London Borough of Southwark | Gainsford Street | Works for the provision of in sewer equipment | Shad Thames Pumping Station |
London Borough of Southwark | Chambers Street | Works to provide site access The temporary removal of on street parking and introduction of temporary waiting restrictions | Chambers Wharf |
London Borough of Southwark | Loftie Street | Works to provide site access | Chambers Wharf |
London Borough of Southwark | Bevington Street | The temporary removal of on street parking and introduction of temporary waiting restrictions, provision of temporary pedestrian refuge | Chambers Wharf |
London Borough of Southwark | Croft Street | The temporary removal of on street parking and introduction of temporary waiting restrictions modification to traffic calming features Service connection to existing sewer | Earl Pumping Station |
London Borough of Southwark | Chilton Grove | Works to provide site access and service connections to existing sewer, temporary removal of traffic calming, on street parking and introduction of temporary waiting restrictions | Earl Pumping Station |
London Borough of Lewisham | Croft Street | Works to provide site access The temporary removal of on street parking and introduction of temporary waiting restrictions, modification to traffic calming features. Service connection to existing sewer | Earl Pumping Station |
London Borough of Lewisham | Yeoman Street | Works to provide site access, service connections to existing sewer, temporary removal of traffic calming, on street parking and introduction of temporary waiting restrictions | Earl Pumping Station |
London Borough of Lewisham | Chilton Grove | Works to provide site access, service connections to existing sewer, temporary removal of traffic calming, on street parking and introduction of temporary waiting restrictions | Earl Pumping Station |
London Borough of Lewisham | Deptford Church Street | Works associated with the temporary suspension of the pedestrian crossing, provision of temporary pedestrian crossing, temporary removal of central carriageway divide, temporary removal of bus lanes. Temporary relocation of bus stops introduction of temporary waiting restrictions Works associated with environmental enhancement including footway surfacing and street furniture | Deptford Church Street |
London Borough of Lewisham | Coffey Street | Works to provide site access Temporary removal of on street parking and introduction of temporary waiting restrictions Works associated with temporary one way use, including associated signs Works associated with environmental enhancement including footway surfacing and street furniture | Deptford Church Street |
London Borough of Lewisham | Crossfield Street | Works to provide site access Temporary removal of on street parking and introduction of temporary waiting restrictions. Works associated with temporary one way use, including associated signs Works to form a temporary traffic management system and emergency evacuation point Works associated with the provision of a temporary section of carriageway linking Crossfield Road to Coffey Street Works associated with environmental enhancement including footway surfacing and street furniture | Deptford Church Street |
Royal Borough of Greenwich | Norman Road | Works to provide site access | Greenwich Pumping Station |
Royal Borough of Greenwich | Greenwich High Road | Works to provide site access | Greenwich Pumping Station |
Royal Borough of Greenwich | Unnamed pedestrian/cycle route between Norman Road and Creekside | Temporary diversion of route and associated works | Greenwich Pumping Station |
London Borough of Tower Hamlets | Glamis Road | Works to provide site access Temporary removal of on street parking and introduction of temporary waiting restrictions, modification to traffic signal stop lines | King Edward Memorial Park Foreshore |
London Borough of Tower Hamlets | Bekesbourne Street | Temporary removal of on street parking and introduction of temporary waiting restrictions, provision of construction area, provision of plant (control kiosk) | Bekesbourne Street |
London Borough of Tower Hamlets | Ratcliffe Lane | Provision of construction area, provision of plant (vent pipe), temporary removal of on street parking and introduction of temporary waiting restrictions | Bekesbourne Street |
London Borough of Newham | Gay Road | Works to provide site access, temporary removal of on street parking, and the introduction of temporary waiting restrictions | Abbey Mills Pumping Station |
London Borough of Newham | Abbey Lane | Temporary removal of on street parking and introduction of temporary waiting restrictions | Abbey Mills Pumping Station |
London Borough of Newham | Jenkins Lane | Works to provide construction / permanent site access | Beckton Sewage Treatment Works |
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: