8.—(1) The licence holder must submit to the MMO for approval a scour and accretion monitoring and mitigation strategy. The MMO will issue their decision in respect of the scour and accretion monitoring and mitigation strategy:
(a)by 30th September 2014; or
(b)within 5 days of the grant of the DCO; or
(c)by the expiry of 20 business days from receipt of the scour and accretion monitoring and mitigation strategy submission to the MMO,
(d)whichever is the latest.
(2) Prior to the commencement of any part of a licensed activity, a scour and accretion monitoring and mitigation plan for that licensed activity shall be prepared by the licence holder in accordance with the agreed scour and accretion monitoring and mitigation strategy in consultation with the MMO, and submitted to the MMO for approval, in accordance with the procedure in Part 3.
(3) The carrying out of any licensed activity shall proceed only in accordance with the agreed scour and accretion monitoring and mitigation plan approved under condition 8(2).
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: