The Hinkley Point C (Nuclear Generating Station) Order 2013 No. 648 xmlns:atom="http://www.w3.org/2005/Atom"
Introductory Text
PART 1
Preliminary
1.Citation and commencement
2.Interpretation
Principal powers
3.Development consent for authorised development etc.
4.Effect of the Order on the site preparation permission
5.Maintenance of authorised project
6.Authorisation of use
7.Benefit of Order
8.Consent to transfer benefit of Order
9.Application of the 1991 Act
10.Application of the 1990 Act
11.Application of the 2010 Regulations
12.Defence to proceedings in respect of statutory nuisance
Streets
13.Street works
14.Stopping up of footpaths on HPC development site
15.Permanent stopping up of streets
16.Status of footpaths created or improved
17.Temporary stopping up of streets
18.Access to works
19.Construction and maintenance of new, altered or diverted streets
20.Agreements with street authorities
Supplemental powers
21.Discharge of water
22.Protective work to buildings
23.Authority to survey and investigate the land
Powers of acquisition
24.Compulsory acquisition of land
25.Statutory authority to override easements and other rights
26.Time limit for exercise of authority to acquire land compulsorily
27.Compulsory acquisition of rights
28.Private rights of way
29.Application of the Compulsory Purchase (Vesting Declarations) Act 1981
30.Acquisition of subsoil only
31.Acquisition of part of certain properties
32.Rights under or over streets
33.Temporary use of land for carrying out authorised project
34.Temporary use of land for maintaining authorised project
35.Apparatus and rights of statutory undertakers in land acquired or used
36.Apparatus and rights of statutory undertakers in stopped-up streets
37.Recovery of costs of new connections
Miscellaneous and general
38.Suspension of restriction on development of Bridgwater C
39.Application of landlord and tenant law
40.Operational land for purposes of the 1990 Act
41.Felling or lopping of trees
42.Trees subject to tree preservation orders
43.Certification and construction of plans and documents
44.Service of notices
45.Arbitration
46.Procedure in relation to certain approvals etc.
47.For the protection of the Environment Agency (Part 1)
48.Crown rights
PART 2
Preliminary
49.Interpretation of Part 2
50.Commencement of Part 2
51.Duration of temporary jetty powers
52.Effect of Order on temporary jetty harbour empowerment order
53.Incorporation of the Harbours, Docks and Piers Clauses Act 1847
Principal powers
54.Development consent etc. for temporary jetty works
55.Power to deviate
56.Further powers as to works and extinguishment of rights
57.Period for completion of works and termination of works powers
58.Limits of harbour
59.Maintenance of temporary jetty works
60.Subsidiary works
61.Obstruction of work
Supplemental powers
62.Right to dredge
63.Abatement of works abandoned or decayed
64.Survey of tidal works
65.Lights on tidal works etc. during construction
66.Provision against danger to navigation
67.Permanent lights on tidal works
68.Rights to lease etc.
Harbour Regulations
69.Byelaws
70.Confirmation of byelaws
71.General directions to vessels
72.Publication of general directions
73.Special directions to vessels
74.Master’s responsibility to be unaffected
75.Failure to comply with directions
76.Enforcement of special directions
77.Charges
Miscellaneous and general
78.Use of temporary jetty
79.Saving for Trinity House
80.Application and termination of permitted development rights
81.For the Protection of the Environment Agency (Part 2)
82.Closure of jetty
83.Saving for termination of Part 2
Signature
SCHEDULE 1
Authorised project
PART 1 Authorised development
HPC Development Site In the District of West Somerset and the County of Somerset
HPC Development Site: cooling water infrastructure In the District of West Somerset and the County of Somerset and the territorial sea
HPC Development Site: HPC Accommodation Campus In the District of West Somerset and the County of Somerset
Bridgwater A In the District of Sedgemoor and the County of Somerset
Bridgwater C In the District of Sedgemoor and the County of Somerset
Cannington Bypass In the District of Sedgemoor and the County of Somerset
Cannington Park and Ride In the District of Sedgemoor and the County of Somerset
Combwich In the District of Sedgemoor and the County of Somerset
Junction 23 In the District of Sedgemoor and the County of Somerset
Junction 24 In the District of Sedgemoor and the County of Somerset
Williton In the District of West Somerset and the County of Somerset
C182 Farringdon Hill Lane, horse crossing In the District of West Somerset and the County of Somerset
Claylands Corner junction In the Districts of West Somerset, Sedgemoor and the County of Somerset
A39 New Road/B3339 Sandford Hill Roundabout In the District of Sedgemoor and the County of Somerset
Washford Cross Roundabout In the District of West Somerset and the County of Somerset
A38 Bristol Road/The Drove junction In the District of Sedgemoor and the County of Somerset
Wylds Road/The Drove junction In the District of Sedgemoor and the County of Somerset
A39 Broadway/A38 Taunton Road junction In the District of Sedgemoor and the County of Somerset
M5 Junction 23 Roundabout In the District of Sedgemoor and the County of Somerset
Cannington traffic calming measures In the District of Sedgemoor and the County of Somerset
A38 Bristol Road/Wylds Road junction In the District of Sedgemoor and the County of Somerset
Huntworth Roundabout In the District of Sedgemoor and the County of Somerset
PART 2 Temporary jetty works
In the District of West Somerset and the County of Somerset and the territorial sea
PART 3 Approved plans
HPC Development Site
HPC accommodation campus
Bridgwater A
Bridgwater C
Cannington Bypass
Cannington Park and Ride
Combwich
Junction 23
Junction 24
Williton
Highway improvements
SCHEDULE 2
Requirements
Interpretation
1.(1) In this Schedule— “commencement” means the carrying out of...
Project wide
2.Unless otherwise indicated, requirements PW1 to PW36 relate to the...
HPC Development Site: site preparation works
3.Requirements P1 to P26 relate to Work No. 1A(a) to...
HPC Development Site: Work Nos. 1A, 1B and 1C
4.For the purpose of requirements MS1 to MS40, the “site”...
HPC Development Site: temporary jetty
5.For the purpose of requirements J1 to J5, the “site”...
HPC Development Site: cooling water infrastructure
6.For the purpose of requirements CW1 and CW2, the “site”...
HPC Development Site: HPC Accommodation Campus
7.For the purpose of requirements OS1 to OS8, the “site”...
Bridgwater A Accommodation Campus
8.For the purpose of requirements BRIA1 to BRIA21, the “site”...
Bridgwater C Accommodation Campus
9.For the purpose of requirements BRIC1 to BRIC18, the “site”...
Cannington Bypass
10.For the purpose of requirements CB1 to CB12, the “site”...
Cannington Park and Ride
11.For the purpose of requirements CP1 to CP15, the “site”...
Combwich Wharf and Freight Laydown facility
12.For the purpose of requirements C1 to C30, the “site”...
Junction 23
13.For the purpose of requirements J23-1 to J23-16, the “site”...
Junction 24
14.For the purpose of requirements J24-1 to J24-10, the “site”...
Williton
15.For the purpose of requirements WP1 to WP12, the “site”...
SCHEDULE 3
Deemed approval of matters referred to in requirements
SCHEDULE 4
Streets subject to street works
SCHEDULE 5
Footpaths to be stopped up on HPC Development Site
PART 1 Footpaths to be permanently stopped up on HPC Development Site
PART 2 Footpaths to be temporarily stopped up on HPC Development Site
SCHEDULE 6
Streets to be permanently stopped up
PART 1 Streets for which a substitute is to be provided
PART 2 Streets for which no substitute is to be provided
SCHEDULE 7
Status of footpaths created or improved
SCHEDULE 8
Streets to be temporarily stopped up
SCHEDULE 9
Access to works
SCHEDULE 10
Land or interests in or rights over land not to be acquired compulsorily
SCHEDULE 11
Modification of compensation and compulsory purchase enactments for creation of new rights
Compensation enactments
1.The enactments for the time being in force with respect...
2.(1) Without limitation on the scope of paragraph 1, the...
Application of the 1965 Act
3.(1) The 1965 Act has effect with the modifications necessary...
4.For section 7 of the 1965 Act (measure of compensation)...
5.For section 8 of the 1965 Act (provisions as to...
6.The following provisions of the 1965 Act (which state the...
7.Section 11 of the 1965 Act (powers of entry) is...
8.Section 20 of the 1965 Act (protection for interests of...
9.Section 22 of the 1965 Act (protection of acquiring authority’s...
SCHEDULE 12
Land of which temporary possession may be taken
SCHEDULE 13
Trees subject to Tree Preservation Orders
SCHEDULE 14
Procedure for discharge of requirements
1.Applications made under requirement
2.Further information
3.Fees
4.Appeals
5.Interpretation of Schedule 14
SCHEDULE 15
For the protection of the Environment Agency
1.(1) The following provisions shall apply for the protection of...
2.Surveys and maintenance of drainage works
3.Impairment of efficiency of drainage work for flood defence purposes
4.Indemnity as to costs and expenses
5.The fact that any work or thing has been executed...
6.Disputes and differences
SCHEDULE 16
Limits of harbour
Explanatory Note