HPC Development Site
HPC Permanent Development Site
Site PlansDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A1-SL-00-GA-002 | 01 | HPC Site Parameter Plan | 1:1000 | A0 |
HINK-A1-SL-00-GA-010 | 01 | Site Layout Plan (Operational) | 1:2500 | A1 |
Nuclear Island (Unit 1)
Unit 1: Reactor Building / Fuel Building / Fuel Building Hall / Boron Storage / Safeguard Buildings / Nuclear Auxiliary Building / Access TowerDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HR-01-GP-090 | 01 | Roof Plan | 1:200 | A0 |
HINK-A2-HR-01-GE-001 | 01 | South and West Elevations | 1:200 | A0 |
HINK-A2-HR-01-GE-002 | 01 | North and East Elevations | 1:200 | A0 |
HINK-A2-HR-01-DT-001 | 01 | Part Elevation Detail | 1:50 | A0 |
Radioactive Waste Storage / Radioactive Waste Process BuildingDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HQ-00-GA-001 | 01 | Roof Plan and Elevations | 1:200 | A0 |
HINK-A2-HQ-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A0 |
Hot Laundry / Hot workshop / Hot warehouse / Facilities for Decontamination / Effluent TanksDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HV-00-GP-020 | 01 | Roof Plan | 1:200 | A1 |
HINK-A2-HV-00-GE-001 | 01 | Elevations | 1:200 | A1 |
HINK-A2-HV-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Emergency Diesel Generator – ADrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HD-01-GP-040 | 01 | Roof Plan | 1:200 | A1 |
HINK-A2-HD-01-GE-001 | 01 | Elevations | 1:200 | A1 |
HINK-A2-HD-01-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Emergency Diesel Generator – BDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HD-02-GP-040 | 01 | Roof Plan | 1:200 | A1 |
HINK-A2-HD-02-GE-001 | 01 | Elevations | 1:200 | A1 |
HINK-A2-HD-02-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Nuclear Island (Unit 2)
Unit 2: Reactor Building / Fuel Building / Fuel Building Hall / Boron Storage / Safeguard Buildings / Nuclear Auxiliary Building / Access TowerDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HR-02-GP-090 | 01 | Roof Plan | 1:200 | A0 |
HINK-A2-HR-02-GE-001 | 01 | South and West Elevations | 1:200 | A0 |
HINK-A2-HR-02-GE-002 | 01 | North and East Elevations | 1:200 | A0 |
HINK-A2-HR-02-DT-001 | 01 | Part Elevation Detail | 1:50 | A0 |
Radioactive Waste Treatment BuildingDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HQC-00-GP-040 | 01 | Roof Plan | 1:100 | A1 |
HINK-A2-HQC-00-GE-001 | 01 | Elevations | 1:100 | A1 |
HINK-A2-HQC-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Emergency Diesel Generator – CDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HD-03-GP-040 | 01 | Roof Plan | 1:200 | A1 |
HINK-A2-HD-03-GE-001 | 01 | Elevations | 1:200 | A1 |
HINK-A2-HD-03-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Emergency Diesel Generator – DDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HD-04-GP-040 | 01 | Roof Plan | 1:200 | A1 |
HINK-A2-HD-04-GE-001 | 01 | Elevations | 1:200 | A1 |
HINK-A2-HD-04-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Conventional Island (Unit 1)
Unit 1: Turbine HallDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A1-HM-01-GA-006 | 01 | Roof Plan, North and South Elevations | 1:200 | A0 |
HINK-A1-HM-01-GE-001 | 01 | West and East Elevations | 1:200 | A0 |
HINK-A1-HM-01-DT-001 | 01 | Part Elevation Detail | 1:50 | A0 |
Unit 1: Sky BridgesDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A1-BR-01-GP-010 | 01 | Roof Plan | 1:100 | A1 |
HINK-A1-BR-01-GE-001 | 01 | North and South Elevations | 1:100 | A1 |
HINK-A1-BR-01-GE-002 | 01 | East and West Elevations | 1:100 | A1 |
HINK-A1-BR-01-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Unit 1: Non Classified Electrical BuildingDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HF-01-GP-030 | 01 | Roof Plan (Lev 10.70m) | 1:100 | A1 |
HINK-A2-HF-01-GE-001 | 01 | South Elevation | 1:100 | A1 |
HINK-A2-HF-01-GE-002 | 01 | North and East Elevations | 1:100 | A1 |
HINK-A2-HF-01-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Unit 1: Gas Insulated Switch Gear / Main Transformer / Unit Transformer / Auxiliary TransformerDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HT-01-GP-003 | 01 | Roof | 1:200 | A1 |
HINK-A2-HT-01-GE-001 | 01 | Elevations | 1:200 | A1 |
HINK-A2-HT-01-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Unit 1: Hydrazine and Ammonia StorageDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-SIR-01-GA-001 | 01 | Roof Plan and Elevations | 1:100 | A1 |
Unit 1: Auxiliary Feedwater StorageDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HSB-01-GA-001 | 01 | Plan, Section A:A and East and South Elevations | 1:100 | A1 |
Conventional Island (Unit 2)
Unit 2: Turbine HallDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A1-HM-02-GA-006 | 01 | Roof Plan, North and South Elevations | 1:200 | A0 |
HINK-A1-HM-02-GE-001 | 01 | West and East Elevations | 1:200 | A0 |
HINK-A1-HM-02-DT-001 | 01 | Part Elevation Detail | 1:50 | A0 |
Unit 2: Sky BridgesDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A1-BR-02-GP-010 | 01 | Roof Plan | 1:100 | A1 |
HINK-A1-BR-02-GE-001 | 01 | North and South Elevations | 1:100 | A1 |
HINK-A1-BR-02-GE-002 | 01 | East and West Elevations | 1:100 | A1 |
HINK-A1-BR-02-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Unit 2: Non Classified Electrical BuildingDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HF-02-GP-030 | 01 | Roof Plan (Lev 10.70m) | 1:100 | A1 |
HINK-A2-HF-02-GE-001 | 01 | South Elevation | 1:100 | A1 |
HINK-A2-HF-02-GE-002 | 01 | North and West Elevations | 1:100 | A1 |
HINK-A2-HF-02-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Unit 2: Gas Insulated Switch Gear / Main Transformer / Unit Transformer / Auxiliary TransformerDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HT-02-GP-003 | 01 | Roof | 1:200 | A1 |
HINK-A2-HT-02-GE-001 | 01 | Elevations | 1:200 | A1 |
HINK-A2-HT-02-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Unit 2: Hydrazine and Ammonia StorageDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-SIR-02-GA-001 | 01 | Roof Plan and Elevations | | |
Unit 2: Auxiliary Feedwater StorageDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HSB-02-GA-001 | 01 | Plan, Section A:A and East and South Elevations | 1:100 | A1 |
Operations
Operational Service CentreDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A1-HB-00-GP-090 | 01 | Roof Plan | 1:200 | A1 |
HINK-A1-HB-00-GE-001 | 01 | North and South Elevations | 1:200 | A1 |
HINK-A1-HB-00-GE-002 | 01 | East and West Elevations | 1:200 | A1 |
HINK-A1-HB-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Cooling Water Pumphouse and Associated Buildings (Unit 1)
Unit 1: Cooling Water Pumphouse / Forebay / Outfall Pond (Surge Chamber) / Filtering Debris Recovery PitDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HP-01-GP-030 | 01 | Roof Plan | 1:200 | A0 |
HINK-A2-HP-01-GE-001 | 01 | Elevations | 1:200 | A0 |
HINK-A2-HP-01-DT-001 | 01 | Part Elevation Detail | 1:50 | A0 |
Unit 1: Fire-Fighting Water BuildingDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HOJ-01-GA-003 | 01 | Roof Plan and Elevations | 1:200 | A1 |
HINK-A2-HOJ-01-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Cooling Water Pumphouse and Associated Buildings (Unit 2)
Unit 2: Cooling Water Pumphouse / Forebay / Outfall Pond (Surge Chamber) / Filtering Debris Recovery PitDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HP-02-GP-030 | 01 | Roof Plan | 1:200 | A0 |
HINK-A2-HP-02-GE-001 | 01 | Elevations | 1:200 | A0 |
HINK-A2-HP-02-DT-001 | 01 | Part Elevation Detail | 1:50 | A0 |
Unit 2: Fire-Fighting Water BuildingDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HOJ-02-GA-003 | 01 | Roof Plan and Elevations | 1:200 | A1 |
HINK-A2-HOJ-02-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Remaining Balance of Plant and Other Plant (Unit 1)
Unit 1: Hydrogen StorageDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HZH-01-GA-002 | 01 | Roof Plan and Elevations | 1:100 | A1 |
Unit 1: Oxygen StorageDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HZO-01-GA-002 | 01 | Roof Plan and Elevations | 1:100 | A1 |
Remaining Balance of Plant and Other Plant (Unit 2)
Unit 2: Hydrogen StorageDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HZH-02-GP-010 | 01 | Roof Plan | 1:100 | A1 |
HINK-A2-HZH-02-GE-001 | 01 | Elevations | 1:100 | A1 |
Unit 2: Oxygen StorageDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HZO-02-GA-002 | 01 | Roof Plan and Elevations | 1:100 | A1 |
Remaining Balance of Plant and Other Plant (Shared Between both Units)
Attenuation PondDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-01-HXO-00-GA-001 | 01 | Roof Plan and Elevations | 1:200 | A1 |
Demineralisation StationDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HY-00-GP-030 | 01 | Roof Plan | 1:100 | A1 |
HINK-A2-HY-00-GE-001 | 01 | North and South Elevations | 1:100 | A1 |
HINK-A2-HY-00-GE-002 | 01 | East and West Elevations | 1:100 | A1 |
HINK-A2-HY-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Auxiliary BoilersDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HVB-00-GA-004 | 01 | Roof Plan | 1:100 | A1 |
HINK-A2-HVB-00-GE-001 | 01 | Elevations | 1:100 | A1 |
HINK-A2-HVB-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Chemical Products StorageDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HZC-00-GA-001 | 01 | Roof Plan and Elevations | 1:100 | A1 |
HINK-A2-HZC-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Sewage Treatment PlantDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-STP-00-GA-001 | 01 | Plans and Elevations | 1:100 | A1 |
Conventional Island Water Storage Tank – ADrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-SER-01-GA-002 | 01 | Roof Plan and East Elevation | 1:200 | A1 |
Conventional Island Water Storage Tank – BDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-SER-02-GA-002 | 01 | Roof Plan and East Elevation | 1:200 | A1 |
Nuclear Island Water Storage TankDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-SED-00-GA-002 | 01 | Roof Plan and South and East Elevations | 1:100 | A1 |
Fuel Waste and Storage
Interim Spent Fuel StoreDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HHK-00-GP-000 | 01 | Plan | 1:200 | A0 |
HINK-A2-HHK-00-GE-001 | 01 | North and South Elevations | 1:200 | A0 |
HINK-A2-HHK-00-GE-002 | 01 | East and West Elevations | 1:200 | A0 |
Access Control BuildingDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HUD-00-GA-001 | 01 | Plans and Elevations | 1:100 | A1 |
Intermediate Level Waste Interim Storage FacilityDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HHI-00-GA-002 | 01 | Roof Plan and Elevations | 1:200 | A0 |
HINK-A2-HHI-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A0 |
Ancillary, Office and Storage
Main Access Control BuildingDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HU-00-GP-010 | 01 | Roof Plan | 1:100 | A1 |
HINK-A2-HU-00-GE-001 | 01 | Elevations | 1:100 | A1 |
HINK-A2-HU-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Entry Relay BuildingDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-ERB-00-GA-002 | 01 | Roof Plan and Elevations | 1:100 | A1 |
HINK-A2-ERB-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Off-site Vehicle Search AreaDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-VSA-00-GA-001 | 01 | Roof Plan and Elevations | 1:50 | A1 |
Auxiliary Administration CentreDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HUC-00-GP-020 | 01 | Roof Plan | 1:100 | A1 |
HINK-A2-HUC-00-GE-001 | 01 | North and South Elevations | 1:100 | A1 |
HINK-A2-HUC-00-GE-002 | 01 | East and West Elevations | 1:100 | A1 |
HINK-A2-HUC-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Medical CentreDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HBM-00-GP-010 | 01 | Roof Plan | 1:100 | A1 |
HINK-A2-HBM-00-GE-001 | 01 | External Elevations | 1:100 | A1 |
HINK-A2-HBM-00-GE-002 | 01 | Courtyard Elevations | 1:100 | A1 |
HINK-A2-HBM-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
EDF Site OfficesDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HAO-00-GP-020 | 01 | Roof Plan | 1:200 | A1 |
HINK-A2-HAO-00-GE-001 | 01 | Elevations | 1:200 | A1 |
HINK-A2-HAO-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Garage for Handling FacilitiesDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HBG-00-GP-010 | 01 | Roof Plan | 1:100 | A1 |
HINK-A2-HBG-00-GE-001 | 01 | Elevations | 1:100 | A1 |
HINK-A2-HBG-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Oil and Grease Storage and Oil Ancillary BuildingDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HOG-00-GA-002 | 01 | Roof Plan | 1:100 | A1 |
HINK-A2-HOG-00-GE-001 | 01 | North and South Elevations | 1:100 | A1 |
HINK-A2-HOG-00-GE-002 | 01 | East and West Elevations | 1:100 | A1 |
HINK-A2-HOG-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
AREVA WarehouseDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HBW-00-GP-010 | 01 | Roof Plan | 1:200 | A1 |
HINK-A2-HBW-00-GE-001 | 01 | Elevations | 1:200 | A1 |
HINK-A2-HBW-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Meteorological StationDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HSM-00-GA-002 | 01 | Roof Plan and Elevations | 1:50 | A1 |
Outage Access Control BuildingDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-TU1-00-GA-002 | 01 | Roof Plan and Elevations | 1:100 | A1 |
HINK-A2-TU1-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Contaminated Tools Storage 1Drawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HHC-01-GA-002 | 01 | Roof Plan and Elevations | 1:200 | A1 |
HINK-A2-HHC-01-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Contaminated Tools Storage 2Drawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HHC-02-GA-002 | 01 | Roof Plan and Elevations | 1:200 | A1 |
HINK-A2-HHC-02-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Conventional Waste StorageDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-CWS-00-GA-002 | 01 | Roof Plan and Elevations | 1:200 | A1 |
Transit Area for Very Low Level Waste and Low Level WasteDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HHL-00-GE-001 | 01 | Elevations | 1:100 | A1 |
Public and Training
Simulator Building / Training CentreDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A1-HBS-00-GP-020 | 01 | Roof Plan | 1:200 | A1 |
HINK-A1-HBS-00-GE-001 | 01 | Elevations | 1:200 | A1 |
HINK-A1-HBS-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
Public Information CentreDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A1-PIC-00-GP-040 | 01 | Roof Plan | 1:100 | A1 |
HINK-A1-PIC-00-GE-001 | 01 | North and West Elevations | 1:100 | A1 |
HINK-A1-PIC-00-GE-002 | 01 | South and East Elevations | 1:100 | A1 |
HINK-A1-PIC-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A1 |
National Grid SubstationDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-SS-00-GP-010 | 01 | Roof Plan | 1:200 | A0 |
HINK-A2-SS-00-GE-001 | 01 | Elevations | 1:200 | A0 |
HINK-A2-SS-00-DT-001 | 01 | Part Elevation Detail | 1:50 | A0 |
Other Site Structures
Sea Wall (Incorporating Coastal Footpath)Drawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A2-HSW-00-GA-001 | 01 | Plans | 1:500 | A0 |
HINK-A2-HSW-00-GA-002 | 01 | North Elevation | 1:50 | A0 |
HINK-A2-HSW-00-GA-003 | 01 | Detail Plans and Elevations | 1:50 | A0 |
HINK-A2-HSW-00-GA-004 | 01 | Detail Plan and Elevation | 1:100 | A0 |
EDF Energy PylonsDrawing number | Rev | Drawing title | Scale | Paper size |
---|
HINK-A1-PL-00-GA-001 | 01 | Location Plan, Plans, Elevations and Axonometric | Various | A1 |
Highways Plans
Drawing number | Rev | Drawing title | Scale | Paper size |
---|
HPC-GEN124-R1-RFC-DRW-000045 | 01 | Northern Roundabout Proposed Layout | 1:500 | A1 |
HPC-GEN124-R1-RFC-DRW-000046 | 01 | Vehicle Search Area Layby and Turning Head Proposed Layout | 1:250 | A1 |
HPC-GEN124-R1-RFC-DRW-000047 | 01 | Southern Roundabout Proposed Layout During Operation | 1:500 | A1 |
HPC-GEN124-R1-RFC-DRW-000048 | 01 | Southern Roundabout Proposed Layout During Construction | 1:500 | A1 |
HPC-GEN124-R1-RFC-DRW-000049 | 01 | Emergency Access Road Junction with Existing Highway Proposed Layout | 1:250 | A1 |
Site Preparation Plans
Drawing number | Rev | Drawing title | Scale | Paper size |
---|
HPCSPW002a Rev1 | 01 | Site Layout Plan | 1:3500 | A1 |
HPCSPW002b | 00 | Beach Access Road Plan and Cross Sections | 1:250 / 1:50 | A1 |
HPCSPW004 Rev1 | 01 | Planning Application Fencing Arrangement (Sheet 1 of 3) | 1:3500 | A1 |
HPCSPW005 Rev1 | 01 | Fencing Enlarged Detail West (Sheet 2 of 3) | 1:1500 | A1 |
HPCSPW006 Rev1 | 01 | Fencing Enlarged Detail East (Sheet 3 of 3) | 1:1500 | A1 |
HPCSPW007 Rev1 | 01 | Indicative Earthworks Cut and Fill Arrangement | 1:3500 | A1 |
HPCSPW008 | 00 | Early Works Water Management Zone | 1:2500 | A1 |
HPCSP009 Rev1 | 01 | Surface Water Catchment Area Overall General Arrangement | 1:3000 | A1 |
HPCSPW010 | 00 | Arrangement of Construction Drainage Outfall to Foreshore | 1:75 | A1 |
HPCSPW011 Rev1 | 01 | Surface Water Drainage Holford Stream Culvert | 1:1500 / 1:150 | A1 |
HPCSPW012a | 00 | Deep Water Drainage Arrangement | 1:2000 / 1:100 | A1 |
HPCSPW012b | 00 | Deep Water Arrangement Spine Drain Sections A and B | 1:200 | A1 |
HPCSPW012c | 00 | Deep Water Assessment Spine Drain Sections C | 1:200 | A1 |
HPCSPW013b | 00 | Typical Cross Section Through Haul Road | 1:50 | A1 |
HPCSPW014 | 00 | 11kv Sub Station Plan and Elevations | 1:100 | A1 |
HPCSPW015 | 00 | Raw Water Reservoir Plans and Sections | 1:150 | A1 |
HPCSPW016 Rev1 | 01 | Surface Water Drainage in the Built Development Areas | 1:1750 | A1 |
HPCSPW017 | 00 | Site Access Control Arrangement, Floor and Elevation | 1:50 | A1 |
HPCSPW019 Rev1 | 01 | Landscape Proposal Plan | 1:5000 | A1 |
HPCSPW022 | 00 | Proposed Sewage Treatment Plant – Plans and Sections | 1:100 | A1 |
HPCSPW023a | 00 | Existing and Reinstated Ground Level Cross Sections | 1:2500 / 1:500 | A1 |
HPCSPW023b | 00 | Earthworks Platforms Cross Sections | 1:2500 / 1:500 | A1 |
HPCSPW025a Rev2 | 02 | Tree and Hedgerow Retention and Removal | 1:4000 | A1 |
HPCSPW025b Rev1 | 01 | Proposed Advanced Planting, Plan | 1:1000 | A1 |
HPCSPW026 | 00 | Primary and Secondary Access Tracks | 1:3500 | A1 |
HPCSPW027 | 00 | NW Boundary Mitigation During Construction Cross Sections A and B | 1:200 | A1 |
HPCSPW028 | 00 | NW Boundary Mitigation During Construction Cross Sections C and D | 1:200 | A1 |
HPCSPW029 | 00 | NW Boundary Mitigation During Construction Planting Plan | 1:750 | A1 |
Back to top