Citation, commencement and expiry

1.—(1) These Regulations may be cited as the Climate Change Agreements (Eligible Facilities) Regulations 2012.

(2) They come into force on 1st January 2013.

(3) Regulations 3 to 8 cease to have effect at the end of 31st March 2023.

Interpretation

2.  In these Regulations—

“the Act” means the Finance Act 2000;

“the Waste Framework Directive” means Directive 2008/98/EC of the European Parliament and of the Council on waste(1);

“aircraft” includes gliders and missiles;

“coating material” means paint, printing ink, varnish, lacquer, dye, any metal oxide coating, any adhesive coating, any elastomer coating, any metal or plastic coating and any other coating material;

“eligible process” means a process or activity or a combination of processes or activities listed in the Schedule to these Regulations carried out at an installation or site;

“food” includes—

(a)

drink,

(b)

articles and substances of no nutritional value which are used for human consumption, and

(c)

articles and substances used as ingredients in the preparation of food;

“hazardous waste” means waste which displays any of the characteristics listed in Annex III of the Waste Framework Directive;

“installation” means—

(a)

an installation falling within any one or more of the descriptions of installations set out in the Table to paragraph 51 of Schedule 6 to the Act; or

(b)

an installation covered by paragraph 51 of Schedule 6 to the Act by virtue of the Climate Change Agreements (Energy-intensive) Regulations 2006(2) carrying out an eligible process;

“reckonable energy” has the meaning given by regulation 4;

“recovery” has the same meaning as in the Waste Framework Directive and related terms are to be construed accordingly;

“relevant commodities” means—

(a)

taxable commodities;

(b)

hydrocarbon oil within the meaning of the Hydrocarbon Oil Duties Act 1979(3);

(c)

any mixture of gases which originates from an oil refinery;

(d)

biomass;

(e)

non-renewable waste;

“waste” means anything that—

(a)

is waste within the meaning of Article 3(1) of the Waste Framework Directive; and

(b)

is not excluded from the scope of that Directive by Article 2(1), (2) or (3) of that Directive;

“waste incineration plant” means any stationary or mobile technical unit and equipment dedicated to the thermal treatment of waste, with or without recovery of the combustion heat generated, through the incineration by oxidation of waste as well as other thermal treatment processes, such as pyrolysis, gasification or plasma process, if the substances resulting from the treatment are subsequently incinerated;

“waste co-incineration plant” means any stationary or mobile technical unit whose main purpose is the generation of energy or production of material products and which uses waste as a regular or additional fuel or in which waste is thermally treated for the purpose of disposal through the incineration by oxidation of waste as well as other thermal treatment processes, such as pyrolysis, gasification or plasma process, if the substances resulting from the treatment are subsequently incinerated.

Eligible Facilities

3.—(1) An installation or a site is to be taken to be a facility for the purposes mentioned in paragraph 50(1) of Schedule 6 to the Act only if—

(a)at least 70% of the reckonable energy supplied to the installation or to the site is intended to be used in the installation, installations or parts of installations on the site; and

(b)the taxable commodities supplied to the installation or to the site by taxable supplies in the following 12 month period are intended to be burned (or, in the case of electricity, consumed)—

(i)in the installation, installations or part of installations on the site; or

(ii)on the site where the installation, installations or parts of installations are situated.

(2) For the purposes of paragraph (1)(a), supply or use of reckonable energy during the previous 12 month period must be used to determine the intended supply or use of reckonable energy in the following 12 month period.

Reckonable energy

4.  Reckonable energy is—

(a)energy obtained from the burning or using of relevant commodities in the installations or parts of installations on the site;

(b)electrical energy supplied to the installation, installations or parts of installations on the site;

(c)energy in cooling supplies; or

(d)energy in supplies of steam.

Calculation of reckonable energy from relevant commodities and electricity

5.—(1) Reckonable energy from relevant commodities, other than electricity, must be calculated by reference to the gross calorific value of the commodity burned to produce it.

(2) Subject to regulations 6 and 7, the quantity of electricity must be multiplied by a factor of 2.6 to convert it into reckonable energy.

Calculation of reckonable energy from dedicated electricity generation plant

6.  Except where regulation 7 applies, for electricity generated in plant which is located in, and intended for supplying electricity for use by a facility—

(a)reckonable energy must be calculated by reference to the gross calorific value of the commodity burned to produce the electricity; and

(b)where the electricity is used on other parts of a site, the electricity generated must be attributed to the facility and the rest of the site on a pro rata basis.

Calculation of reckonable energy from combined heat and power stations

7.—(1) Reckonable energy from a combined heat and power station must be calculated by reference to the gross calorific value of the commodity burned to produce it.

(2) Where part of the energy from a combined heat and power station is used in a place, the formulae set out in paragraphs (3) to (5) must apply for calculating the reckonable energy from the station in relation to that place.

(3) The following formula applies in respect of electricity from the combined heat and power station which is used in that place—

where—

  • RE is the reckonable energy in respect of electricity from the combined heat and power station which is used in that place;

  • EC is the total energy content of the relevant commodities burned in the combined heat and power station calculated by reference to the gross calorific value of each commodity;

  • EP is the quantity of electricity produced by the combined heat and power station which is used in that place;

  • ET is the total quantity of electricity produced by the combined heat and power station which is used in that place and elsewhere; and

  • HT is the total quantity of heat produced by the combined heat and power station which is used in that place and elsewhere.

(4) If no electricity from the combined heat and power station is put into public supply, the following formula applies in respect of heat which is used in that place—

where—

  • RHN is the reckonable energy in respect of heat from the combined heat and power station which is used in that place;

  • EC is the total energy content of the relevant commodities burned in the combined heat and power station calculated by reference to the gross calorific value of each commodity;

  • HP is the quantity of heat produced by the combined heat and power station which is used in that place;

  • ET is the total quantity of electricity produced by the combined heat and power station which is used in that place and elsewhere; and

  • HT is the total quantity of heat produced by the combined heat and power station which is used in that place and elsewhere.

(5) If electricity from the combined heat and power station is put into public supply, the following formula applies in respect of heat which is used in that place—

where—

  • RHS is the reckonable energy in respect of heat from the combined heat and power station which is used in that place;

  • EC is the total energy content of the relevant commodities burned in the combined heat and power station calculated by reference to the gross calorific value of each commodity;

  • HP is the quantity of heat produced by the combined heat and power station which is used in that place;

  • ES is the quantity of electricity produced by the combined heat and power station and put into public supply;

  • ET is the total quantity of electricity produced by the combined heat and power station which is used in that place and elsewhere; and

  • HT is the total quantity of heat produced by the combined heat and power station which is used in that place and elsewhere.

(6) For the purposes of paragraphs (4) and (5), electricity is put into public supply when it is supplied to an electricity utility.

(7) Where absorption cooling is used to produce a cooling supply for use in the installation, installations or parts of installations on a site and the heat for the absorption cooling is from a combined heat and power station—

(a)the heat used to provide the cooling supply must be treated for the purposes of paragraphs (1) to (6) as used in the place where the cooling supply is used; and

(b)the quantity of that heat must be estimated by dividing the output of the cooling supply by the coefficient of performance of the cooling system.

Calculation of reckonable energy from steam

8.  The reckonable energy in respect of steam supplied to the installation, installations or parts of installations on a site must be calculated by taking the enthalpy of the steam consumed by the installation, installations or parts of installations and dividing it by the efficiency of the system which generates the steam and supplies it to that installation, those installations or parts of those installations where it is used.

Revocations and transitional provision

9.—(1) Subject to paragraph (2), the following Regulations are revoked—

(a)the Climate Change Agreements (Eligible Facilities) Regulations 2001(4);

(b)the Climate Change Agreements (Eligible Facilities) Regulations 2006(5);

(c)the Climate Change Agreements (Eligible Facilities) (Amendment) Regulations 2006(6);

(d)the Climate Change Agreements (Eligible Facilities) (Amendment) Regulations 2009(7).

(2) The regulations listed in paragraph (1) continue to have effect in relation to climate change agreements entered into with the Secretary of State before the coming into force of these Regulations.

Review

10.—(1) Before the end of the review period, the Secretary of State must—

(a)carry out a review of regulations 3 to 8,

(b)set out the conclusions of the review in a report, and

(c)publish the report.

(2) The report must in particular—

(a)set out the objectives intended to be achieved by the regulatory system established by regulations 3 to 8,

(b)assess the extent to which those objectives are achieved, and

(c)assess whether those objectives remain appropriate and, if so, the extent to which they could be achieved with a system that imposes less regulation.

(3) “Review period” means the period of five years beginning with the day on which these Regulations came into force.

Gregory Barker

Minister of State

Department of Energy and Climate Change

29th November 2012

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources