4. After Article 45 of the Electricity Order there shall be inserted the following Article—
45A.—(1) Each public electricity supplier shall, in such form and manner and with such frequency as the Director may direct, take steps to inform his customers of—
(a)the standards of overall performance determined under Article 43 which are applicable to that supplier; and
(b)that supplier’s level of performance as respects each of those standards.
(2) In giving any such direction, the Director shall not specify a frequency of less than once in every period of 12 months.”.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: