Chwilio Deddfwriaeth

Regulation (EU) 2019/943 of the European Parliament and of the CouncilDangos y teitl llawn

Regulation (EU) 2019/943 of the European Parliament and of the Council of 5 June 2019 on the internal market for electricity (recast) (Text with EEA relevance)

 Help about what version

Pa Fersiwn

 Help about advanced features

Nodweddion Uwch

 Help about UK-EU Regulation

Deddfwriaeth yn deillio o’r UE

Pan adawodd y DU yr UE, cyhoeddodd legislation.gov.uk ddeddfwriaeth yr UE a gyhoeddwyd gan yr UE hyd at ddiwrnod cwblhau’r cyfnod gweithredu (31 Rhagfyr 2020 11.00 p.m.). Ar legislation.gov.uk, mae'r eitemau hyn o ddeddfwriaeth yn cael eu diweddaru'n gyson ag unrhyw ddiwygiadau a wnaed gan y DU ers hynny.

Close

Mae'r eitem hon o ddeddfwriaeth yn tarddu o'r UE

Mae legislation.gov.uk yn cyhoeddi fersiwn y DU. Mae EUR-Lex yn cyhoeddi fersiwn yr UE. Mae Archif Gwe Ymadael â’r UE yn rhoi cipolwg ar fersiwn EUR-Lex o ddiwrnod cwblhau’r cyfnod gweithredu (31 Rhagfyr 2020 11.00 p.m.).

Changes to legislation:

There are currently no known outstanding effects by UK legislation for Regulation (EU) 2019/943 of the European Parliament and of the Council, CHAPTER V. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

CHAPTER VU.K.TRANSMISSION SYSTEM OPERATION

F1Article 28U.K.European network of transmission system operators for electricity

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 29U.K.The ENTSO for Electricity

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 30U.K.Tasks of the ENTSO for Electricity

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 31U.K.Consultations

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 32U.K.Monitoring by ACER

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 33U.K.Costs

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 34U.K.Regional cooperation of transmission system operators

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 35U.K.Establishment and mission of regional coordination centres

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 36U.K.Geographical scope of regional coordination centres

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 37U.K.Tasks of regional coordination centres

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 38U.K.Cooperation within and between regional coordination centres

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 39U.K.Working arrangements

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 40U.K.Consultation procedure

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 41U.K.Transparency

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 42U.K.Adoption and review of coordinated actions and recommendations

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 43U.K.Management board of regional coordination centres

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 44U.K.Organisational structure

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 45U.K.Equipment and staff

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 46U.K.Monitoring and reporting

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 47U.K.Liability

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 48U.K.Ten-year network development plan

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F1Article 49U.K.Inter-transmission system operator compensation mechanism

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Article 50U.K.Provision of information

1.Transmission system operators shall put in place coordination and information exchange mechanisms to ensure the security of the networks in the context of congestion management.

2.The safety, operational and planning standards used by transmission system operators shall be made public. The information published shall include a general scheme for the calculation of the total transfer capacity and the transmission reliability margin based upon the electrical and physical features of the network. Such schemes shall be subject to approval by the regulatory [F2authority].

3.Transmission system operators shall publish estimates of available transfer capacity for each day, indicating any available transfer capacity already reserved. Those publications shall be made at specified intervals before the day of transport and shall include, in any event, week-ahead and month-ahead estimates, as well as a quantitative indication of the expected reliability of the available capacity.

4.Transmission system operators shall publish relevant data on aggregated forecast and actual demand, on availability and actual use of generation and load assets, on availability and use of the networks and interconnections, on balancing power and reserve capacity and on the availability of flexibility. For the availability and actual use of small generation and load assets, aggregated estimate data may be used.

5.The market participants concerned shall provide the transmission system operators with the relevant data.

6.Generation undertakings which own or operate generation assets, where at least one generation asset has an installed capacity of at least 250 MW, or which have a portfolio comprising at least 400 MW of generation assets, shall keep at the disposal of the regulatory authority [F3and the competition authority], for five years all hourly data per plant that is necessary to verify all operational dispatching decisions and the bidding behaviour at power exchanges, interconnection auctions, reserve markets and over-the-counter-markets. The per-plant and per hour information to be stored shall include, but shall not be limited to, data on available generation capacity and committed reserves, including allocation of those committed reserves on a per-plant level, at the times the bidding is carried out and when production takes place.

7.Transmission system operators shall exchange regularly a set of sufficiently accurate network and load flow data in order to enable load flow calculations for each transmission system operator in its relevant area. The same set of data shall be made available to the regulatory [F4authority and the Secretary of State] upon request. The regulatory [F5authority and the Secretary of State] shall treat that set of data confidentially, and shall ensure that confidential treatment is also given by any consultant carrying out analytical work on their request, on the basis of those data.

F6Article 51U.K.Certification of transmission system operators

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Yn ôl i’r brig

Options/Cymorth

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i mabwysiadwyd gan yr UE): Mae'r wreiddiol version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel adopted version that was used for the EU Official Journal
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

Mae’r llinell amser yma yn dangos y fersiynau gwahanol a gymerwyd o EUR-Lex yn ogystal ag unrhyw fersiynau dilynol a grëwyd ar ôl y diwrnod ymadael o ganlyniad i newidiadau a wnaed gan ddeddfwriaeth y Deyrnas Unedig.

Cymerir dyddiadau fersiynau’r UE o ddyddiadau’r dogfennau ar EUR-Lex ac efallai na fyddant yn cyfateb â’r adeg pan ddaeth y newidiadau i rym ar gyfer y ddogfen.

Ar gyfer unrhyw fersiynau a grëwyd ar ôl y diwrnod ymadael o ganlyniad i newidiadau a wnaed gan ddeddfwriaeth y Deyrnas Unedig, bydd y dyddiad yn cyd-fynd â’r dyddiad cynharaf y daeth y newid (e.e. ychwanegiad, diddymiad neu gyfnewidiad) a weithredwyd i rym. Am ragor o wybodaeth gweler ein canllaw i ddeddfwriaeth ddiwygiedig ar Ddeall Deddfwriaeth.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel adopted fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill