Commission Delegated Regulation (EU) 2019/331 of 19 December 2018 determining transitional Union-wide rules for harmonised free allocation of emission allowances pursuant to Article 10a of Directive 2003/87/EC of the European Parliament and of the Council (Text with EEA relevance)
Pan adawodd y DU yr UE, cyhoeddodd legislation.gov.uk ddeddfwriaeth yr UE a gyhoeddwyd gan yr UE hyd at ddiwrnod cwblhau’r cyfnod gweithredu (31 Rhagfyr 2020 11.00 p.m.). Ar legislation.gov.uk, mae'r eitemau hyn o ddeddfwriaeth yn cael eu diweddaru'n gyson ag unrhyw ddiwygiadau a wnaed gan y DU ers hynny.
Mae legislation.gov.uk yn cyhoeddi fersiwn y DU. Mae EUR-Lex yn cyhoeddi fersiwn yr UE. Mae Archif Gwe Ymadael â’r UE yn rhoi cipolwg ar fersiwn EUR-Lex o ddiwrnod cwblhau’r cyfnod gweithredu (31 Rhagfyr 2020 11.00 p.m.).
There are currently no known outstanding effects by UK legislation for Commission Delegated Regulation (EU) 2019/331, Article 5.![]()
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1.The operator of an installation at which a regulated activity is carried out and for which a greenhouse gas emissions permit (including a greenhouse gas emissions permit within the meaning of GGETSR 2012) issued for the first time is in force may apply to the regulator:
(a)for free allocation in the 2021-2025 allocation period, if the permit is issued in the period beginning on 1 July 2019 and ending on 30 June [F22025];
(b)for free allocation in the [F32026 allocation period and the 2027-2030] allocation period, if the permit is issued in the period beginning on 1 July [F22025] and ending on 30 June 2029.
2.An application may be made at any time after the end of the year in which the start of normal operation occurs.
3.But where an installation has not been operating for a full calendar year after the start of normal operation, an application may not be made unless:
(a)in the case of an application under paragraph 1(a), the start of normal operation is on or after 1 January 2021;
(b)in the case of an application under paragraph 1(b), the start of normal operation is on or after 1 January 2026.
F43a.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.For the purposes of the application, the operator must divide the installation into sub-installations in accordance with Article 10.
5.The application must set out the start of normal operation and be accompanied by:
(a)a new entrant data report, verified in accordance with the Verification Regulation 2018, containing each parameter set out in sections 1 and 2 of Annex 4 for each sub-installation separately from the start of normal operation until the end of the year before the year in which the application is made;
(b)a monitoring methodology plan in accordance with Article 8 and Annex 6;
(c)the verification report on the new entrant data report, which must contain the confirmation relating to the monitoring methodology plan referred to in Article 27(3)(f) of the Verification Regulation 2018.
6.The regulator:
(a)must assess the new entrant data report and the verification report to ensure conformity with the requirements of this Regulation;
(b)where appropriate, may request corrections by the operator of any non-conformity or error that impacts on the determination of activity levels;
(c)must not determine historical activity levels under Article 17, activity levels for the purpose of Article 18(2) or calculate the preliminary or final annual number of allowances under Article 18 or 18a unless:
(i)the regulator considers that the date set out in the application as the start of normal operation, or such other date proposed by the operator, is accurate;
(ii)the data relating to the installation has been verified as satisfactory or, where it has not been verified as satisfactory, the regulator considers that any data gaps referred to in the verifier's opinion are due to exceptional and unforeseeable circumstances that could not have been avoided even if all due care had been exercised; and
(iii)any corrections requested under point (b) have been made.]
Textual Amendments
F1Art. 5 substituted (31.12.2020) by The Greenhouse Gas Emissions Trading Scheme (Amendment) Order 2020 (S.I. 2020/1557), art. 2(2), Sch. 1 para. 9
F2Word in Art. 5(1) substituted (31.3.2024) by The Greenhouse Gas Emissions Trading Scheme (Amendment) Order 2024 (S.I. 2024/192), arts. 2, 12(2)
F3Words in Art. 5(1)(b) substituted (31.3.2025) by The Greenhouse Gas Emissions Trading Scheme (Amendment) (No. 2) Order 2025 (S.I. 2025/124), arts. 2, 39(2)
F4Art. 5(3a) omitted (E.W.S.) (1.1.2024 immediately after S.I. 2023/850 comes into force) by virtue of The Greenhouse Gas Emissions Trading Scheme (Amendment) (No. 2) Order 2023 (S.I. 2023/1387), arts. 2(1), 15(2) (which amendment was extended to N.I. (1.1.2025) by virtue of S.I. 2024/1366, arts. 2(2)(a), 45(2))
Modifications etc. (not altering text)
C1Art. 5(3) modified (1.1.2024) by The Greenhouse Gas Emissions Trading Scheme (Amendment) Order 2023 (S.I. 2023/850), arts. 2, 20(7)
The Whole Regulation you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i mabwysiadwyd gan yr UE): Mae'r wreiddiol version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Mae’r llinell amser yma yn dangos y fersiynau gwahanol a gymerwyd o EUR-Lex yn ogystal ag unrhyw fersiynau dilynol a grëwyd ar ôl y diwrnod ymadael o ganlyniad i newidiadau a wnaed gan ddeddfwriaeth y Deyrnas Unedig.
Cymerir dyddiadau fersiynau’r UE o ddyddiadau’r dogfennau ar EUR-Lex ac efallai na fyddant yn cyfateb â’r adeg pan ddaeth y newidiadau i rym ar gyfer y ddogfen.
Ar gyfer unrhyw fersiynau a grëwyd ar ôl y diwrnod ymadael o ganlyniad i newidiadau a wnaed gan ddeddfwriaeth y Deyrnas Unedig, bydd y dyddiad yn cyd-fynd â’r dyddiad cynharaf y daeth y newid (e.e. ychwanegiad, diddymiad neu gyfnewidiad) a weithredwyd i rym. Am ragor o wybodaeth gweler ein canllaw i ddeddfwriaeth ddiwygiedig ar Ddeall Deddfwriaeth.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys