Commission Delegated Regulation (EU) No 480/2014 of 3 March 2014 supplementing Regulation (EU) No 1303/2013 of the European Parliament and of the Council laying down common provisions on the European Regional Development Fund, the European Social Fund, the Cohesion Fund, the European Agricultural Fund for Rural Development and the European Maritime and Fisheries Fund and laying down general provisions on the European Regional Development Fund, the European Social Fund, the Cohesion Fund and the European Maritime and Fisheries Fund
Pan adawodd y DU yr UE, cyhoeddodd legislation.gov.uk ddeddfwriaeth yr UE a gyhoeddwyd gan yr UE hyd at ddiwrnod cwblhau’r cyfnod gweithredu (31 Rhagfyr 2020 11.00 p.m.). Ar legislation.gov.uk, mae'r eitemau hyn o ddeddfwriaeth yn cael eu diweddaru'n gyson ag unrhyw ddiwygiadau a wnaed gan y DU ers hynny.
Mae legislation.gov.uk yn cyhoeddi fersiwn y DU. Mae EUR-Lex yn cyhoeddi fersiwn yr UE. Mae Archif Gwe Ymadael â’r UE yn rhoi cipolwg ar fersiwn EUR-Lex o ddiwrnod cwblhau’r cyfnod gweithredu (31 Rhagfyr 2020 11.00 p.m.).
There are currently no known outstanding effects by UK legislation for Commission Delegated Regulation (EU) No 480/2014, CHAPTER III.![]()
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1.The quality review of major projects referred to in the third paragraph of Article 101 of Regulation (EU) No 1303/2013, shall be carried out by independent experts that have:
(a)significant technical experience of all stages of the project cycle;
(b)broad international experience of the investment sectors concerned;
(c)significant expertise in the analysis and evaluation of socioeconomic benefits;
(d)significant knowledge and experience of relevant Union law, policies and procedures;
(e)independence from all authorities involved directly or indirectly in the approval, implementation, or operation of the major project;
(f)no conflict of interest at any level in relation to the major project;
(g)no commercial interest in relation to the major project;
(h)the necessary linguistic competence.
2.Where a Member State proposes to mandate independent experts other than those supported by technical assistance at the initiative of the Commission in accordance with Article 58 of Regulation (EU) No 1303/2013, it shall in accordance with the third paragraph of Article 101 of that Regulation submit a request for the Commission's agreement. That agreement shall be based on documents demonstrating compliance of the experts with the requirements laid down in paragraph 1 of this Article.
The Commission shall inform the Member State within three months from the submission of the request whether it agrees with the proposal regarding the independent experts.
1.The independent experts shall carry out their assessment on the basis of the information referred to in points (a) to (i) of the first paragraph of Article 101 of Regulation (EU) No 1303/2013. The independent experts may request additional elements relating to this information which they deem necessary for the quality review.
The Member State and the independent experts may agree that this work shall be complemented by site visits.
The independent experts may, in agreement with the Member States, consult the Commission on relevant State aid issues for the purpose of their assessment.
2.The independent experts shall for the purposes of the quality review undertake the following steps:
(a)the independent experts shall verify that the operation is a major project within the meaning of Article 100 of Regulation (EU) No 1303/2013, that the major project is not a completed operation within the meaning of Articles 2(14) and 65(6) of that Regulation, and that the major project is included within the relevant operational programme;
(b)the independent experts shall check the completeness, consistency and accuracy of the information under points (a) to (i) of the first subparagraph of Article 101 of Regulation (EU) No 1303/2013 provided for in the format referred to in the fifth paragraph of Article 101 of Regulation (EU) No 1303/2013;
(c)the independent experts shall appraise the quality of the major project on the basis of the criteria set out in Annex II to this Regulation;
(d)the independent experts shall produce an independent quality review report (hereinafter the ‘IQR report’) in the format provided for in the third subparagraph of Article 102(1) of Regulation (EU) No 1303/2013. In the IQR report, the independent experts shall formulate and justify their statements in an unambiguous manner for the elements referred to in this paragraph.
3.A major project is appraised positively by the quality review in the meaning of Article 102(1) of Regulation (EU) No 1303/2013 if the independent experts conclude that all the criteria referred to in Annex II of this Regulation have been fulfilled.]
Textual Amendments
F1Ch. 3 omitted for specified purposes (31.12.2020) by virtue of The European Structural and Investment Funds Common Provisions Rules etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/783), regs. 1, 5(16); 2020 c. 1, Sch. 5 para. 1(1)
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i mabwysiadwyd gan yr UE): Mae'r wreiddiol version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Mae’r llinell amser yma yn dangos y fersiynau gwahanol a gymerwyd o EUR-Lex yn ogystal ag unrhyw fersiynau dilynol a grëwyd ar ôl y diwrnod ymadael o ganlyniad i newidiadau a wnaed gan ddeddfwriaeth y Deyrnas Unedig.
Cymerir dyddiadau fersiynau’r UE o ddyddiadau’r dogfennau ar EUR-Lex ac efallai na fyddant yn cyfateb â’r adeg pan ddaeth y newidiadau i rym ar gyfer y ddogfen.
Ar gyfer unrhyw fersiynau a grëwyd ar ôl y diwrnod ymadael o ganlyniad i newidiadau a wnaed gan ddeddfwriaeth y Deyrnas Unedig, bydd y dyddiad yn cyd-fynd â’r dyddiad cynharaf y daeth y newid (e.e. ychwanegiad, diddymiad neu gyfnewidiad) a weithredwyd i rym. Am ragor o wybodaeth gweler ein canllaw i ddeddfwriaeth ddiwygiedig ar Ddeall Deddfwriaeth.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys