Chwilio Deddfwriaeth

Flood Risk Management (Scotland) Act 2009

Paragraph 9 – Final decision following preliminary decision

296.Paragraph 9 requires the local authority to make a final decision in relation to the proposed scheme by either confirming it with or without modifications, or rejecting it, unless the scheme has been called in by the Scottish Ministers.

297.Sub-paragraph (2) lists matters which the local authority is to take into account.

298.Sub-paragraph (3) prohibits a local authority from confirming a scheme with modifications unless it has notified the relevant objectors and anyone else considered to be affected of the proposed modifications at least 28 days before confirming the scheme, given them an opportunity to make objections about the proposed modifications, and considered any objections made.

Yn ôl i’r brig

Options/Cymorth

Print Options

Close

Nodiadau Esboniadol

Text created by the Scottish Government to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Acts of the Scottish Parliament except those which result from Budget Bills.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill