289.Where the Scottish Ministers receive notification of a proposed scheme under paragraph 5(5), paragraph 6 requires them to call in the proposed scheme where any relevant objector is a local authority or National Park Authority. Otherwise, the Scottish Ministers must advise the local authority within 28 days of receipt, whether or not they will call in the proposed scheme for decision by them. In reaching this decision whether to call in, the Scottish Ministers must have regard to the factors listed in paragraph 6(3).

290.Sub-paragraphs (4) and (5) allow the Scottish Ministers to extend the time in which they must decide whether or not to call in a scheme by up to 28 days, but they must make any decision to extend within the original 28 day period and must notify the local authority of the extension as soon as practicable.

Yn ôl i’r brig

Options/Cymorth

Print Options

Close

Nodiadau Esboniadol

Text created by the Scottish Government to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Acts of the Scottish Parliament except those which result from Budget Bills.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill