41Chapter applies before application is made

(1)This Chapter applies where a person (“the applicant”) proposes to make an application for an order granting development consent.

(2)In the following provisions of this Chapter—

  • “the proposed application” means the proposed application mentioned in subsection (1);

  • “the land” means the land to which the proposed application relates or any part of that land;

  • “the proposed development” means the development for which the proposed application (if made) would seek development consent.

42Duty to consult

The applicant must consult the following about the proposed application—

(a)such persons as may be prescribed,

(b)each local authority that is within section 43,

(c)the Greater London Authority if the land is in Greater London, and

(d)each person who is within one or more of the categories set out in section 44.

43Local authorities for purposes of section 42(b)

(1)A local authority is within this section if the land is in the authority’s area.

(2)A local authority (“A”) is within this section if—

(a)the land is in the area of another local authority (“B”), and

(b)any part of the boundary of A’s area is also a part of the boundary of B’s area.

(3)In this section “local authority” means—

(a)a county council, or district council, in England;

(b)a London borough council;

(c)the Common Council of the City of London;

(d)the Council of the Isles of Scilly;

(e)a county council, or county borough council, in Wales;

(f)a council constituted under section 2 of the Local Government etc. (Scotland) Act 1994 (c. 39);

(g)a National Park authority;

(h)the Broads Authority.

44Categories for purposes of section 42(d)

(1)A person is within Category 1 if the applicant, after making diligent inquiry, knows that the person is an owner, lessee, tenant (whatever the tenancy period) or occupier of the land.

(2)A person is within Category 2 if the applicant, after making diligent inquiry, knows that the person—

(a)is interested in the land, or

(b)has power—

(i)to sell and convey the land, or

(ii)to release the land.

(3)An expression, other than “the land”, that appears in subsection (2) of this section and also in section 5(1) of the Compulsory Purchase Act 1965 (c. 56) has in subsection (2) the meaning that it has in section 5(1) of that Act.

(4)A person is within Category 3 if the applicant thinks that, if the order sought by the proposed application were to be made and fully implemented, the person would or might be entitled—

(a)as a result of the implementing of the order,

(b)as a result of the order having been implemented, or

(c)as a result of use of the land once the order has been implemented,

to make a relevant claim.

This is subject to subsection (5).

(5)A person is within Category 3 only if the person is known to the applicant after making diligent inquiry.

(6)In subsection (4) “relevant claim” means—

(a)a claim under section 10 of the Compulsory Purchase Act 1965 (c. 56) (compensation where satisfaction not made for the taking, or injurious affection, of land subject to compulsory purchase);

(b)a claim under Part 1 of the Land Compensation Act 1973 (c. 26) (compensation for depreciation of land value by physical factors caused by use of public works).

45Timetable for consultation under section 42

(1)The applicant must, when consulting a person under section 42, notify the person of the deadline for the receipt by the applicant of the person’s response to the consultation.

(2)A deadline notified under subsection (1) must not be earlier than the end of the period of 28 days that begins with the day after the day on which the person receives the consultation documents.

(3)In subsection (2) “the consultation documents” means the documents supplied to the person by the applicant for the purpose of consulting the person.

46Duty to notify Commission of proposed application

(1)The applicant must supply the Commission with such information in relation to the proposed application as the applicant would supply to the Commission for the purpose of complying with section 42 if the applicant were required by that section to consult the Commission about the proposed application.

(2)The applicant must comply with subsection (1) on or before commencing consultation under section 42.

47Duty to consult local community

(1)The applicant must prepare a statement setting out how the applicant proposes to consult, about the proposed application, people living in the vicinity of the land.

(2)Before preparing the statement, the applicant must consult each local authority that is within section 43(1) about what is to be in the statement.

(3)The deadline for the receipt by the applicant of a local authority’s response to consultation under subsection (2) is the end of the period of 28 days that begins with the day after the day on which the local authority receives the consultation documents.

(4)In subsection (3) “the consultation documents” means the documents supplied to the local authority by the applicant for the purpose of consulting the local authority under subsection (2).

(5)In preparing the statement, the applicant must have regard to any response to consultation under subsection (2) that is received by the applicant before the deadline imposed by subsection (3).

(6)Once the applicant has prepared the statement, the applicant must publish it—

(a)in a newspaper circulating in the vicinity of the land, and

(b)in such other manner as may be prescribed.

(7)The applicant must carry out consultation in accordance with the proposals set out in the statement.

48Duty to publicise

(1)The applicant must publicise the proposed application in the prescribed manner.

(2)Regulations made for the purposes of subsection (1) must, in particular, make provision for publicity under subsection (1) to include a deadline for receipt by the applicant of responses to the publicity.

49Duty to take account of responses to consultation and publicity

(1)Subsection (2) applies where the applicant—

(a)has complied with sections 42, 47 and 48, and

(b)proposes to go ahead with making an application for an order granting development consent (whether or not in the same terms as the proposed application).

(2)The applicant must, when deciding whether the application that the applicant is actually to make should be in the same terms as the proposed application, have regard to any relevant responses.

(3)In subsection (2) “relevant response” means—

(a)a response from a person consulted under section 42 that is received by the applicant before the deadline imposed by section 45 in that person’s case,

(b)a response to consultation under section 47(7) that is received by the applicant before any applicable deadline imposed in accordance with the statement prepared under section 47, or

(c)a response to publicity under section 48 that is received by the applicant before the deadline imposed in accordance with section 48(2) in relation to that publicity.

50Guidance about pre-application procedure

(1)Guidance may be issued about how to comply with the requirements of this Chapter.

(2)Guidance under this section may be issued by the Commission or the Secretary of State.

(3)The applicant must have regard to any guidance under this section.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Show Explanatory Notes for Sections: Displays relevant parts of the explanatory notes interweaved within the legislation content.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources