Search Legislation

Petroleum Act 1998

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As enacted)
 Help about advanced features

Advanced Features

Changes over time for: PART 1A

 Help about opening options

Changes to legislation:

There are currently no known outstanding effects for the Petroleum Act 1998, PART 1A. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

[F1PART 1AU.K.Maximising economic recovery of UK petroleum

Extent Information

E1Pt. 1A extended (N.I.) (1.10.2016) by Energy Act 2016 (c. 20), ss. 74(1), 84(3); S.I. 2016/920, reg. 2(c)

Textual Amendments

9AThe principal objective and the strategyU.K.

(1)In this Part the “principal objective” is the objective of maximising the economic recovery of UK petroleum, in particular through—

(a)development, construction, deployment and use of equipment used in the petroleum industry (including upstream petroleum infrastructure), and

(b)collaboration among the following persons—

(i)holders of petroleum licences;

(ii)operators under petroleum licences;

(iii)owners of upstream petroleum infrastructure;

(iv)persons planning and carrying out the commissioning of upstream petroleum infrastructure.

[F2(v)owners of relevant offshore installations.]

(2)The [F3OGA] must produce one or more strategies for enabling the principal objective to be met.

(3)A strategy may relate to matters other than those mentioned in subsection (1)(a) and (b).

(4)For provision about producing and revising a strategy, see sections 9F and 9G.

Textual Amendments

F2S. 9A(1)(b)(v) inserted (1.10.2016) by Energy Act 2016 (c. 20), ss. 73(2), 84(3); S.I. 2016/920, reg. 2(c)

F3Word in s. 9A(2) substituted (1.10.2016) by Energy Act 2016 (c. 20), s. 84(3), Sch. 1 para. 7; S.I. 2016/920, reg. 2(a)

9BExercise of certain functions of the [F4OGA]U.K.

The [F4OGA] must act in accordance with the current strategy or strategies when—

(a)exercising functions under the other Parts of this Act (except Part 4),

(b)exercising functions under Part 4 F5... ,

(c)exercising functions under Chapter 3 of Part 2 of the Energy Act 2011 (upstream petroleum infrastructure),

[F6(ca)exercising functions under Part 2 of the Energy Act 2016,]

(d)exercising any function or using any power under a petroleum licence, and

(e)exercising any other function or using any power—

(i)to provide advice or assistance to another person, or

(ii)to acquire, use or supply information,

for the purpose of enabling the principal objective to be met.

Textual Amendments

F4Word in s. 9B substituted (1.10.2016) by Energy Act 2016 (c. 20), s. 84(3), Sch. 1 para. 8(a); S.I. 2016/920, reg. 2(a)

F5Words in s. 9B(b) omitted (1.10.2016) by virtue of Energy Act 2016 (c. 20), s. 84(3), Sch. 1 para. 8(b); S.I. 2016/920, reg. 2(a)

[F79BAExercise of certain functions of the Secretary of StateU.K.

(1)The Secretary of State must act in accordance with the current strategy or strategies when exercising the functions mentioned in subsection (2).

(2)Those functions are functions under Part 4 to the extent that they concern reduction of the costs of abandonment of offshore installations and submarine pipelines (including the reduction of such costs by means of the timing of measures proposed in abandonment programmes and by the inclusion in such programmes of provision for collaboration with other persons).]

Textual Amendments

9CCarrying out of certain petroleum industry activitiesU.K.

(1)A person who is the holder of a petroleum licence must act in accordance with the current strategy or strategies when planning and carrying out activities as the licence holder.

(2)A person who is an operator under a petroleum licence must act in accordance with the current strategy or strategies when planning and carrying out activities as the operator under the licence.

F8(3). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(4)A person must act in accordance with the current strategy or strategies when planning and carrying out the commissioning of upstream petroleum infrastructure.

[F9(5)A person who is the owner of—

(a)a relevant offshore installation, or

(b)upstream petroleum infrastructure,

must act in accordance with the current strategy or strategies when planning and carrying out the activities mentioned in subsection (6).

(6)Those activities are—

(a)the person's activities as the owner of the installation or infrastructure (including the development, construction, deployment and use of the infrastructure or installation);

(b)the abandonment or decommissioning of the installation or infrastructure.

(7)For the purposes of subsection (5), planning the activities mentioned in subsection (6)(b) includes the preliminary stage of—

(a)deciding whether or when to proceed with the proposed abandonment or decommissioning, and

(b)considering alternative measures to abandonment or decommissioning such as re-use or preservation.]

Textual Amendments

F8S. 9C(3) omitted (1.10.2016) by virtue of Energy Act 2016 (c. 20), ss. 73(3)(a), 84(3); S.I. 2016/920, reg. 2(c)

F9Ss. 9C(5)-(7) inserted (1.10.2016) by Energy Act 2016 (c. 20), ss. 73(3)(b), 84(3); S.I. 2016/920, reg. 2(c)

F109DReports by the Secretary of StateU.K.

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Textual Amendments

9E [F11OGA's] security and resilience functionsU.K.

(1)This Part does not limit the exercise of the [F12OGA's] security and resilience functions.

(2)This Part is subject to the exercise of the security and resilience functions by the [F13OGA].

(3)In this section “security and resilience function” means any function which relates to—

(a)the security of petroleum supplies, or

(b)the resilience of the petroleum industry.

Textual Amendments

F11Word in s. 9E heading substituted (1.10.2016) by Energy Act 2016 (c. 20), s. 84(3), Sch. 1 para. 11(4); S.I. 2016/920, reg. 2(a)

F12Word in s. 9E(1) substituted (1.10.2016) by Energy Act 2016 (c. 20), s. 84(3), Sch. 1 para. 11(2); S.I. 2016/920, reg. 2(a)

F13Word in s. 9E(2) substituted (1.10.2016) by Energy Act 2016 (c. 20), s. 84(3), Sch. 1 para. 11(3); S.I. 2016/920, reg. 2(a)

9FProducing and revising a strategyU.K.

F14(1). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

[F15(2)After the first strategy has been produced, the OGA may—

(a)produce a new strategy, or

(b)revise a current strategy,

whenever the OGA thinks appropriate.]

(3)The [F16OGA] must review each current strategy before the end of each relevant four year period.

F17(4). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(5)In this section “relevant four year period”, in relation to a current strategy, means a period of four years beginning with—

(a)the date on which the strategy was issued, or

(b)if later, the date on which the last review under subsection (3) was concluded.

Textual Amendments

F14S. 9F(1) omitted (1.10.2016) by virtue of Energy Act 2016 (c. 20), s. 84(3), Sch. 1 para. 12(2); S.I. 2016/920, reg. 2(a)

F16Word in s. 9F(3) substituted (1.10.2016) by Energy Act 2016 (c. 20), s. 84(3), Sch. 1 para. 12(4); S.I. 2016/920, reg. 2(a)

F17S. 9F(4) omitted (1.10.2016) by virtue of Energy Act 2016 (c. 20), s. 84(3), Sch. 1 para. 12(5); S.I. 2016/920, reg. 2(a)

9GProcedure for producing and revising a strategyU.K.

(1)Before—

F18(a). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(b)producing a new strategy, or

(c)revising a current strategy,

the [F19OGA] must prepare a draft of the strategy or revised strategy.

(2)The [F20OGA] must—

(a)consult such persons as the [F20OGA] thinks appropriate about the draft, and

(b)consider any representations made by them.

[F21(3)If, after complying with that duty, the OGA decides to proceed with the draft (in its original form or with modifications), the OGA must send the draft to the Secretary of State.

(3A)The Secretary of State must either—

(a)lay a copy of the draft before each House of Parliament, or

(b)return the draft to the OGA and publish the Secretary of State's reasons for doing so.

(3B)The Secretary of State may return the draft to the OGA only if the Secretary of State thinks that—

(a)the OGA has failed to comply with subsection (2), or

(b)the strategy will not enable the principal objective to be met.]

(4)[F22Where a copy of the draft has been laid in accordance with subsection (3A)(a), the OGA] may not take any further steps in relation to the draft if, within the 40 day period, either House resolves not to approve the draft (a “negative resolution”).

(5)If neither House passes a negative resolution, the [F23OGA] may issue the strategy or revised strategy in the form laid before Parliament.

(6)The strategy or revised strategy comes into force on the date specified by the [F24OGA] (which must not be before the date when it is issued).

(7)Subsection (4) does not prevent a new draft of a strategy or revised strategy from being laid before Parliament.

(8)In this section “40 day period”, in relation to the draft of a strategy or revised strategy, means the period of 40 days beginning with the day on which the draft is laid before Parliament (or if the draft is not laid before each House on the same day, the later of the 2 days on which it is laid).

(9)For the purposes of calculating the 40 day period, no account is to be taken of any period during which Parliament is dissolved or prorogued or during which both Houses are adjourned for more than four days.

Textual Amendments

F18S. 9G(1)(a) omitted (1.10.2016) by virtue of Energy Act 2016 (c. 20), s. 84(3), Sch. 1 para. 13(2)(a); S.I. 2016/920, reg. 2(a)

F19Word in s. 9G(1) substituted (1.10.2016) by Energy Act 2016 (c. 20), s. 84(3), Sch. 1 para. 13(2)(b); S.I. 2016/920, reg. 2(a)

F20Word in s. 9G(2) substituted (1.10.2016) by Energy Act 2016 (c. 20), s. 84(3), Sch. 1 para. 13(3); S.I. 2016/920, reg. 2(a)

F21Ss. 9G(3)-(3B) substituted for s. 9G(3) (1.10.2016) by Energy Act 2016 (c. 20), s. 84(3), Sch. 1 para. 13(4); S.I. 2016/920, reg. 2(a)

F22Words in s. 9G(4) substituted (1.10.2016) by Energy Act 2016 (c. 20), s. 84(3), Sch. 1 para. 13(5); S.I. 2016/920, reg. 2(a)

F23Word in s. 9G(5) substituted (1.10.2016) by Energy Act 2016 (c. 20), s. 84(3), Sch. 1 para. 13(6); S.I. 2016/920, reg. 2(a)

F24Word in s. 9G(6) substituted (1.10.2016) by Energy Act 2016 (c. 20), s. 84(3), Sch. 1 para. 13(7); S.I. 2016/920, reg. 2(a)

[F259H“Upstream petroleum infrastructure” and its ownersU.K.

(1)In this Part “upstream petroleum infrastructure” means anything that for the purposes of section 82(1) of the Energy Act 2011 is—

(a)a relevant upstream petroleum pipeline,

(b)a relevant oil processing facility, or

(c)a relevant gas processing facility,

if and in so far as it is used in relation to petroleum within subsection (2) (including such petroleum after it has been got).

(2)Petroleum is within this subsection if it is petroleum which for the time being exists in its natural condition in strata beneath—

(a)the territorial sea adjacent to Great Britain, or

(b)the sea in any area designated under section 1(7) of the Continental Shelf Act 1964.

(3)In this Part “owner”, in relation to upstream petroleum infrastructure, means—

(a)a person in whom the pipeline or facility is vested;

(b)a lessee and any person occupying or controlling the pipeline or facility; and

(c)any person who has the right to have things conveyed by the pipeline or processed by the facility.]

Textual Amendments

[F269HA“Relevant offshore installations” and their ownersU.K.

(1)For the purposes of this Part an offshore installation is a relevant offshore installation if and in so far as it is used in relation to petroleum within subsection (2) (including such petroleum after it has been got).

(2)Petroleum is within this subsection if it is petroleum which for the time being exists in its natural condition in strata beneath—

(a)the territorial sea adjacent to Great Britain, or

(b)the sea in any area designated under section 1(7) of the Continental Shelf Act 1964.

(3)In this Part “owner”, in relation to a relevant offshore installation, means—

(a)a person in whom the installation is vested, and

(b)a lessee and any person occupying or controlling the installation.]

Textual Amendments

9IOther interpretationU.K.

In this Part—

  • current strategy”, in relation to any particular time, means a strategy under section 9A(2) in force at that time;

  • [F27offshore installation” has the same meaning as in Part 4 (see section 44);]

  • operator under a petroleum licence” means a person who is responsible for organising or supervising any of the operations of searching for, boring for, or getting UK petroleum in pursuance of the petroleum licence;

  • [F27owner”, in relation to a relevant offshore installation, has the meaning given in section 9HA;]

  • owner”, in relation to upstream petroleum infrastructure, has the meaning given in section 9H;

  • “petroleum” has meaning given in section 1;

  • petroleum licence” means a licence granted under—

    (a)

    section 3 of this Act, or

    (b)

    section 2 of the Petroleum (Production) Act 1934;

  • principal objective” has the meaning given in section 9A;

  • [F27relevant offshore installation” has the meaning given in section 9HA;]

  • relevant UK waters” means—

    (a)

    the territorial sea adjacent to the United Kingdom, and

    (b)

    the sea in any area designated under section 1(7) of the Continental Shelf Act 1964;

  • [F27submarine pipeline” has the meaning given in section 45;]

  • UK petroleum” means petroleum which for the time being exists in its natural condition in strata beneath relevant UK waters;

  • upstream petroleum infrastructure” has the meaning given in section 9H.]

Textual Amendments

F27Words in s. 9I inserted (1.10.2016) by Energy Act 2016 (c. 20), ss. 73(5), 84(3); S.I. 2016/920, reg. 2(c)

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources