(1)Subject to the following provisions of this section, where any works affecting a scheduled monument which were previously authorised under this Part of this Act cease to be so, then, if any person who has an interest in the whole or any part of the monument—
(a)has incurred expenditure in carrying out works which are rendered abortive by the fact that any further works have ceased to be so authorised; or
(b)has otherwise sustained loss or damage which is directly attributable to that fact ;
the Secretary of State shall pay to that person compensation in respect of that expenditure, loss or damage.
(2)Subsection (1) above only applies where the works cease to be authorised under this Part of this Act—
(a)by virtue of the fact that a scheduled monument consent granted by order under section 3 of this Act ceases to apply to any scheduled monument (whether by virtue of variation or revocation of the order or by virtue of a direction under subsection (3) of that section); or
(b)by virtue of the modification or revocation of a scheduled monument consent by a direction given under section 4 of this Act; or
(c)in accordance with paragraph 8 of Schedule 1 to this Act, by virtue of the service of a notice of proposed modification or revocation of a scheduled monument consent under paragraph 5 of that Schedule.
(3)A person shall not be entitled to compensation under this section in a case falling within subsection (2)(a) above unless, on an application for scheduled monument consent for the works in question, consent is refused, or is granted subject to conditions other than those which previously applied under the order.
(4)For the purposes of this section, any expenditure incurred in the preparation of plans for the purposes of any works, or upon other similar matters preparatory thereto, shall be taken to be included in the expenditure incurred in carrying out those works.
(5)Subject to subsection (4) above, no compensation shall be paid under this section in respect of any works carried out before the grant of the scheduled monument consent in question, or in respect of any other loss or damage (not being loss or damage consisting of depreciation of the value of an interest in land) arising out of anything done or omitted to be done before the grant of that consent.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: