8(1)Where any works for the erection or alteration of a building had been begun but not completed before the appointed day, then if—
(a)immediately before that day those works could have been completed in conformity with the provisions of a planning scheme or of permission granted thereunder, or in accordance with permission granted by or under an interim development order, and
(b)where any permission was required under the Restriction of Ribbon Development Act, 1935, for the carrying out of those works, that permission was granted,
planning permission shall be deemed to have been granted in respect of the completion of those works.
(2)The planning permission deemed to have been granted by virtue of this paragraph shall be deemed to have been so granted subject to any conditions applicable thereto under the scheme or the permission granted by or under the interim development order, as the case may be, and to any conditions imposed by the permission (if any) granted under the Restriction of Ribbon Development Act. 1935, and shall include permission to use the building, when erected or altered.—
(a)where the purpose for which it could be so used was prescribed by or under the planning scheme, or by the permission granted by or under the interim development order, as the case may be, for that purpose;
(b)in any other case, for the purpose for which the building, or the building as altered, was designed.
(3)In relation to any such works as are mentioned in sub-paragraph (1) of mis paragraph, being works in respect of which permission was granted after the twenty-first day of July, nineteen hundred and forty-three, on an application in that behalf made under an interim development order, the provisions of this paragraph shall have effect in substitution for the provisions of the last preceding paragraph.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: