Standard Costs for Forestry Operations/Capital Items

Column 1

Column 2

Item

Standard Cost

Fell/extract dangerous trees£200 per tree
Manual brashing£0.35 per tree
High pruning£1.30 per tree
Badger gates installed in fence lines which are cutting across an established badger run£110 per gate
Respace natural regeneration£600 per hectare
Early pruning of trees£375 per hectare
High pruning of trees£660 per hectare
Woodland thinning£520 per hectare
Removal of tree crop to waste 3-6 metres high£1,100 per hectare
Woodland clearance - felling of waste£975 per hectare
Woodland clearance - felling and extraction£1375 per hectare
Seedling tree removal£35 per hectare
Chipping/mulching of tree debris and brash£500 per hectare
Restructuring with Caledonian Scots pine£411.64 per hectare
Restructuring with diverse conifers£411.64 per hectare
Restructuring with mixed broadleaves£1,030.14 per hectare
Restructuring with native broadleaves£1,100 per hectare
Restructuring with mixed conifer and broadleaves£595.89 per hectare
Woodland deer impact reduction£30 per hectare for deer control during the first 5 years of a Deer Management Plan
Forest plan preparation£20 per hectare for first 200 hectares, £5 per hectare thereafter with a minimum payment of £400 and a maximum payment of £15,000
Dead wood management£40 per hectare
Stock fence£4 per metre
Enhancing/modifying a stock fence in black grouse and capercaillie core areas£2 per metre
New deer fence£7.25 per metre
Upgrading stock to deer fence£2.75 per metre
Scare or temporary fencing£1.50 per metre
Rabbit proofing – existing or new stock/deer fence£1.90 per metre
Enhancing/modifying a deer fence in black grouse and capercaillie core areas£5 per metre
Conversion of deer fence to stock fence in black grouse and capercaillie core areas£2 per metre
Fence removal£2 per metre
Gate for stock fence£100 each
Gate for deer fence£170 each
Ditch/drain blocking with plastic piling dams: Small ditches (up to 0.5 metres wide and deep)£60 per dam
Ditch/drain blocking with plastic piling dams: Medium ditches (between 0.5 and 1 metre wide and deep)£120 per dam
Ditch/drain blocking with plastic piling dams: Large ditches (between 1 and 2 metres wide and 0.5 and 1 metre deep)£280 per dam
Peat dam£0.26 per metre of drain or furrow blocked with peat dams. Minimum payment £300
Small scale tree and shrub planting (on a site not exceeding 0.25 hectares)£2 per tree or shrub
Provision of bat and bird boxes£15 per box
Primary treatment of bracken£200/hectare of infested land
Eradication of scrub/woody vegetation: Light vegetation£600/hectare
Eradication of scrub/woody vegetation: Intermediate vegetation£850/hectare
Eradication of scrub/woody vegetation: Heavy vegetation£1250/hectare
Removal from site of the cut shrub/woody vegetation: Light vegetation£500/hectare
Removal from site of the cut shrub/woody vegetation: Intermediate vegetation£1050/hectare
Removal from site of the cut shrub/woody vegetation: Heavy vegetation£1450/hectare
Provision of water troughs to replace traditional watering points£195 each
Installation of water supply pipe to water trough or pasture pump£3 per metre of pipe laid
Water trough pump: cattle operated pasture or nose pump£180 per installed pump

Stock bridge for bog management:

Small bridge

Large bridge (for ditch wider than 1.5 metres)

£170 per bridge

£620 per bridge

Heather management (in black grouse and Capercaillie core areas)£250/hectare

Manual eradication of rhododendron:

Light infestation/easy access

Medium infestation/access

Difficult access

£4,500 per hectare of infested land

£6,100 per hectare of infested land

£9,500 per hectare of infested land

Mechanised eradication of rhododendron:

Light infestation/easy access

Medium infestation/access

Difficult access

£1,800 per hectare of infested land

£2,400 per hectare of infested land

£2,900 per hectare of infested land

Chemical eradication of rhododendron by foliar or stem injection£1,500 per hectare of infested land
Self-closing/kissing gate for non-vehicular access£350 each
Stile£55 each
Building/restoring drystane or flagstone dykes£17.50 per square metre

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Executive Note

Executive Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources